A地塊新建項目
夾層大型管道支吊架安裝施工方案
(格式最終版)
中建三局集團有限公司
1
目錄
目錄............................................................................................................................................................1
第1章編制依據(jù)及說明..................................................................................................................4
1.1編制原則.................................................................................................................................4
1.2編制依據(jù).................................................................................................................................4
第2章工程概況.................................................................................................................................6
第3章工程重難點分析..................................................................................................................7
3.1重難點分析及解決方案..................................................................................................7
第4章施工準備.................................................................................................................................9
4.1施工準備工作流程............................................................................................................9
4.2人員、機械準備.................................................................................................................9
4.3材料準備.............................................................................................................................11
4.4技術(shù)準備.............................................................................................................................11
第5章管線綜合排布及支架選型............................................................................................13
5.1管線綜合排布...................................................................................................................13
5.2支架選型與支架排布....................................................................................................13
5.3管道管托.............................................................................................................................18
第6章管道運輸與管道安裝......................................................................................................19
6.1管道運輸.............................................................................................................................19
6.2工藝流程:........................................................................................................................19
6.3管材、管件、附屬配件的檢驗.................................................................................20
1
6.4管道支架制作安裝.........................................................................................................21
6.5管道下料及坡口加工方式...........................................................................................21
6.6管道安裝.............................................................................................................................22
6.7閥門安裝.............................................................................................................................23
第7章管道焊接..............................................................................................................................25
7.1施工一般要求...................................................................................................................25
7.2一般焊接程序...................................................................................................................25
7.3焊接工藝.............................................................................................................................26
7.4焊接檢驗.............................................................................................................................27
第8章管道試壓與清洗...............................................................................................................29
8.1管道系統(tǒng)試驗前應(yīng)具備下列條件............................................................................29
8.2管道水壓試壓、水沖洗................................................................................................29
8.3管道系統(tǒng)試驗應(yīng)注意的事項......................................................................................29
8.4管道清洗注意事項.........................................................................................................30
第9章管道除銹、防腐施工......................................................................................................31
9.1除銹及污物的清除.........................................................................................................31
9.2防腐.......................................................................................................................................31
第10章質(zhì)量控制措施..................................................................................................................33
10.1質(zhì)量目標及分解...........................................................................................................33
10.2主要質(zhì)量控制要點.......................................................................................................33
10.3主要質(zhì)量通病防治方法.............................................................................................35
10.4人員及工器具管理.......................................................................................................36
2
10.5標識和可追溯性...........................................................................................................37
第11章質(zhì)量成品保護措施........................................................................................................39
11.1成品保護管理措施.......................................................................................................39
11.2專業(yè)成品保護措施.......................................................................................................39
第12章安全文明施工措施........................................................................................................41
12.1安全施工..........................................................................................................................41
12.2文明施工..........................................................................................................................42
3
第1章編制依據(jù)及說明
1.1編制原則
為了光谷同濟兒童醫(yī)院項目夾層機電安裝工程施工的優(yōu)質(zhì)、快速、高效完成,同時便于
過程上中對工程質(zhì)量控制,針對夾層管廊特點和結(jié)合我公司類似工程施工經(jīng)驗,特編制夾層
通道機電安裝施工方案,旨在為光谷同濟兒童醫(yī)院項目機電安裝專業(yè)提供較完整的技術(shù)指導(dǎo)
性文件并規(guī)范化現(xiàn)場安全文明施工,同時為監(jiān)理、業(yè)主對本工程的施工方法、質(zhì)量、工程進
度等各方面的詳細了解提供依據(jù)。
根據(jù)設(shè)計圖紙中各種管徑的排列形式,確定各支架的選型。由于設(shè)計中沒有對重型支架
材料規(guī)格明確規(guī)定,現(xiàn)根據(jù)規(guī)范及現(xiàn)場實際情況制定方案。重型支架采用優(yōu)質(zhì)槽鋼,以達到
安全、實用、美觀的效果。
1.2編制依據(jù)
1.主要技術(shù)文件
深化設(shè)計圖紙、設(shè)計變更及洽商記錄、技術(shù)規(guī)格書、規(guī)范圖集等技術(shù)文件。
2.主要標準及技術(shù)規(guī)范
類別名稱編號或文號
《給水排水管道工程施工及驗收規(guī)范》GB50268-2008
《通風與空調(diào)工程施工質(zhì)量驗收規(guī)范》GB50243-2016
國標《建筑給排水及采暖工程施工質(zhì)量驗收規(guī)范》GB50242-2002
《建筑節(jié)能工程施工質(zhì)量驗收規(guī)范》GB50411-2014
《建筑材料及制品燃燒性能分級》GB8624-2019
《輻射供暖供冷技術(shù)規(guī)程》JGJ142-2012
JGJ174-2010
標準《多聯(lián)機空調(diào)系統(tǒng)工程技術(shù)規(guī)范》
《通風管道技術(shù)規(guī)程》JGJ141-2017
4
《金屬、非金屬風管支吊架》08K132
《管道穿墻、屋面防水套管》01R409
《室內(nèi)動力管道裝置安裝(熱力管道)》01R415
《室內(nèi)管道支吊架》05R417-1
圖集
《管道及設(shè)備保冷》98R419
《管道與設(shè)備保冷》98R419
《管道與設(shè)備保溫》98R418
《室內(nèi)熱力管道支吊架》95R402
5
第2章工程概況
機電綜合管廊位于兒童醫(yī)院地下室夾層,夾層通道總長度為206米,最寬地方為10米,
高度為1.8m,最窄的地方為2.5m,高度為1.4m。水管2趟管徑為DN100,生活熱水管2趟
管徑為DN80,熱回水管有6趟管徑為DN50,材質(zhì)均采用304薄壁不銹鋼管及配套管件,連
接方式為承插氬弧焊接,管道工作壓力為1.6MPa;
消防供水管及噴淋水管管徑為DN150,材質(zhì)采用內(nèi)外熱鍍鋅鋼管及管件,連接方式為溝
槽卡箍連接,管道工作壓力為1.6MPa;
暖通管道系統(tǒng)龐大、繁雜,管徑大(如:DN300、DN250等),施工難度大。其中蒸汽
管道采用DN300的無縫鋼管,空調(diào)供回水管采用管徑DN150的無縫鋼管,連接方式為焊接,
管道工作壓力為1.6MPa;并且夾層管廊內(nèi)的空調(diào)管道需保溫。
動力橋架包含500*200高壓電纜橋架一趟,800*200低壓電源電纜橋架一趟;
弱電500*200信息橋架一趟,消防500*150弱電橋架一趟。
還需要預(yù)留出1500*360的醫(yī)療氣體管線和軌道物流的施工區(qū)域。
夾層管道平面圖
6
第3章工程重難點分析
3.1重難點分析及解決方案
序號重難點分析解決方案及措施
1、管道的運輸:計算好管道用量,隨土建施工進度,將管道及時
轉(zhuǎn)運到夾層通道,利用卷揚機以及炮車進行運輸。
管道管徑大,在夾
2、管道安裝:利用兩個5t手動葫蘆吊裝配合安裝,安裝順序分為
層通道內(nèi)運輸與
1安裝困難。施工空左側(cè)水管綜合支架與右側(cè)橋架綜合支架同時進行。具體步驟為:
間狹小、密閉。
以6-7軸為基準,先制作好6-7軸交1-Y2~1-L兩側(cè)豎直端與橫端
支架,然后焊接形成整體支架,再將鋼管通過手動葫蘆吊裝系統(tǒng)移
至6-7軸東夾層,從北向南依次施工。
1、支架采用優(yōu)質(zhì)槽鋼,對管道進行滿水重量計算,力均分到每個
管道工程量大,系支架,根據(jù)材料力學進行受力分析,得到支架承重最大彎矩點,計
統(tǒng)復(fù)雜,支架用量
龐大,其中受力集算出支架受到的最大彎曲正應(yīng)力,同時對槽鋼進行扭矩計算,確保
2
中,對支架材質(zhì)、支架安全可靠。
規(guī)格要求嚴格。
2、支架與墻面及地面的支撐點采用預(yù)埋鋼板的做法,確保支架的
穩(wěn)定性。
1、管道焊接:保證焊接質(zhì)量和焊接效率,防止返工。支架根據(jù)現(xiàn)
場情況逐一核實定位,保證排布不但要安全可靠,還要美觀;
管道系統(tǒng)嚴密性
2、安裝施工之前,對夾層管廊施工的管道進行綜合排布,確保焊
3要求高,對于管道
接施工空間。
焊接要求高。
3、支吊架與鋼板焊接處需要滿焊,同時在250*250鋼板(10mm厚)
上打14號膨脹螺栓,螺栓對稱排布。
7
1、對于標高的復(fù)核與引線,根據(jù)土建放線,各施工部將土建所放
施工過程中對于
的標高線引到同一軸線上進行復(fù)核,復(fù)核誤差確保在5mm內(nèi)。
4管道與支架標高
2、施工過程中利用水平儀放線確保安裝支架在同一直線上。
限制嚴格。
3、支架安裝過程中確保支架底部距地面凈空滿足設(shè)計要求。
8
第4章施工準備
4.1施工準備工作流程
4.2人員、機械準備
根據(jù)夾層通道空調(diào)水工程量合理安排勞務(wù)人員數(shù)量和機具設(shè)備臺班。
1.勞動力計劃表
工期節(jié)點計劃
軸線時間節(jié)點
1-Y1~1-P交6-7軸3.1~3.31
1-P~1-D交8-10軸4.1~4.30
1-Y6~1-Y1交8-10軸4.10~4.30
B-1~B-10交B-A~B-C軸5.1~5.16
夾層通道勞動力計劃表
2021年
工種
3.1-4.104.10-5.16
9
焊工24
普工1212
管道工88
總計2222
2.主要機械需用計劃表
主要機械需用計劃表
序號機械或設(shè)備名稱型號規(guī)格數(shù)量額定功率生產(chǎn)能力用于施工部位
1手動葫蘆5t/3t/2t4套5t/3t/2t設(shè)備吊裝
2臺鉆Z4116/2B2臺1kWφ405支架制作安裝
3沖擊鉆TE-255臺1.5kWφ25支吊架安裝等
4鋼管切割機CC4202臺1kW不銹鋼管斷管
φ16~
5液壓沖孔機SH-10(B)3臺2kW沖孔
104
6交直流電焊機BX3-30020臺2.5kW支架制作安裝
7電錘D16-222臺5kW支架制作安裝
8坡口機WS-200A5臺5.1kW鋼管坡口
600*500*75
94
電焊條烘干箱0臺焊條烘干
10電動試壓泵3D-SY6臺6kW100kg管道試壓
11手動試壓泵SY-256臺25kg管道試壓
12等離子切割機ACL31004臺3kW管道加工制作
13移動腳手架1個管道加工
14臨時配電箱5套管道安裝
10
4.3材料準備
在正式安裝開始之前,所需的無縫鋼管、鍍鋅鋼管、槽鋼、波紋補償器等材料進場,并
經(jīng)過專業(yè)監(jiān)理工程師及業(yè)主的現(xiàn)場共同驗收合格后方可使用,并做好相關(guān)檢查驗收工作,達
到相關(guān)要求后方能安裝。
主要管材一覽表
專業(yè)系統(tǒng)名稱安裝位置管材型號長度/m
無縫鋼管DN300104
無縫鋼管DN250320
無縫鋼管DN200610
暖通系統(tǒng)夾層通道
無縫鋼管DN35070
無縫鋼管DN60050
無縫鋼管DN400331
不銹鋼管DN150200
不銹鋼管DN100120
給水系統(tǒng)夾層通道
不銹鋼管DN80250
不銹鋼管DN50700
消防系統(tǒng)夾層通道鍍鋅鋼管DN2001640
4.4技術(shù)準備
1.圖紙會審工作
認真熟悉圖紙、深刻理解設(shè)計意圖及設(shè)計要求,檢查設(shè)計圖紙和資料內(nèi)容是否符合有關(guān)
施工規(guī)范;設(shè)計圖紙是否齊全,圖紙本身及相互之間有無矛盾和錯誤、圖紙與設(shè)計說明是否
一致,將所發(fā)現(xiàn)的問題在圖紙會審時提出,和業(yè)主、監(jiān)理、設(shè)計師等共同商定解決,形成紀
要。
11
2.技術(shù)交底方案編制
夾層通道安裝工程正式施工之前,要針對相關(guān)施工內(nèi)容,編制詳盡的技術(shù)交底方案,方
案通過項目評審?fù)旰?,方可對所有施工人員進行交底,施工過程中嚴格按照技術(shù)交底內(nèi)容實
施。
12
第5章管線綜合排布及支架選型
5.1管線綜合排布
1.系統(tǒng)綜合排布效果圖
管道綜合排布剖面圖
2.綜合布線依據(jù)
1.預(yù)先進行排位規(guī)劃布置,對照現(xiàn)場土建、裝修作業(yè)等實際情況,以保證施工的可行性、
美觀性及實用性等。
2.最大限度地利用有限空間,管線的固定采用綜合支吊架。
3.預(yù)留施工過程中管道施工所需焊接空間,以及后期檢修所需空間。
4.保證空調(diào)水管、消防水管及給水管道開支管所需空間。
5.保證需保溫水管的保溫空間。
5.2支架選型與支架排布
支架梁的設(shè)計包括:支架梁的截面選取、支架梁的驗算。根據(jù)設(shè)計圖紙中各種管徑的排
列形式,確定支架的寬度,設(shè)計中沒有對重型支架材料規(guī)格明確規(guī)定,根據(jù)規(guī)范及現(xiàn)場實際
情況制定方案,重型支架采用優(yōu)質(zhì)槽鋼制作。
以夾層1-Y1~1-P軸空調(diào)水管聯(lián)合支架為例:
13
DN250空調(diào)水管選用無縫鋼管,取兩支架的間距L=6m;
1.對多個支架上的管道進行受力分析
先分析DN250,含水米重:q1=107.66kg/m;運行重量:q2=129.192kg/m;供回水管
道工作壓力為0.6MPa;
2.對橫向管道的支架受力分析
(1)內(nèi)力計算:桿端內(nèi)力值(乘子=1)
14
--------------------------------------------------------------------------------------------
桿端1桿端2
-----------------------------------------------------------------------------
單元碼軸力剪力彎矩軸力剪力彎矩
--------------------------------------------------------------------------------------------
10.000000002547.284190.000000000.00000000-3912.31580-4095.09484
20.000000003412.57903-4095.094840.00000000-3047.02096-2998.42061
30.000000003181.19965-2998.420610.00000000-3278.40034-3290.02268
40.000000003241.42234-3290.022680.00000000-3218.17765-3220.28863
50.000000003231.91098-3220.288630.00000000-3227.68901-3207.62275
60.000000003209.73373-3207.622750.00000000-3249.86626-3328.02033
70.000000003307.95407-3328.020330.00000000-3151.64592-2859.09591
80.000000002937.24998-2859.095910.00000000-3522.35001-4614.39602
90.000000004644.82600-4614.396020.00000000-3106.69399-0.00000000
(2)算出各個支座反力與剪切力的結(jié)果如下所示:
得到每個支座最大剪力為:Fs(max)=4.64KN;
(3)再算出彎矩的結(jié)果如下所示:
得到最大彎矩為:M(max)=4614N·m
(4)查詢資料可得:D250無縫鋼管的抗彎截面模量為:Wx=937.61m3
(5)驗證管道的彎曲正應(yīng)力:≤160MPa(滿足管道受彎曲要求)
3.固定支架垂直方向與水平方向受力分析
(1)垂直方向受力為F垂直=6*9*q1g/10=5.81KN
(2)水平方向的受力分析
考慮到管道與支架之間的摩擦力,摩擦力(木與鋼才的動摩擦系數(shù)為0.2),
為各支架對管道的合力,從而可以得到摩擦力f=0.2*5.81=1.162KN。
15
DN250管道搭設(shè)過程中需要架設(shè)DN250軸向內(nèi)壓式波紋補償器(吸收管道熱膨脹),向
廠家查詢補償器參數(shù)得知此波紋補償器的軸向剛度K=228N/mm,取無縫鋼管最大彈性型變
量L20mm;
可以算得彈性力為:;
管道內(nèi)部的內(nèi)推壓力為:;
將水平方向的力進行矢量合成得到:F水平250=Fs+P1+f=10.2KN;
將水平方向的合力與最大支座反力進行矢量合成,得F合=11.74KN
4.對單個支架進行受力分析
每個管道對支架的合力都為F合=11.74KN。
所以截面最大彎矩為:Mmax=13053.8N·M
5.豎直端支架受力分析;
管道的運行重量為:q2=129.192kg/m,14號槽鋼每米重量16.733kg/m,計算的整體重
量為W=129.192*6*4+16.733*3=3151kg。選用的14號Q235槽鋼抗拉強度為375~460MPa,
橫截面積M=2131.21mm2;計算得該支架豎直端的抗拉強度為:
W3151*10
P7.4MPa<375MPa,所以豎直端抗拉強度滿足要求;
M2*2131.21*106
6.槽鋼的選取
因為Mmax=13053.8N·M;要滿足槽鋼
所受最大彎曲許用應(yīng)力不大于160MPa,
(1)若選用14a槽鋼:>160MPa
16
(2)若選用14b槽鋼:<160MPa
(3)若選用16a槽鋼<160MPa
所以選用14號b型槽鋼。
以此類推,最后選擇支架的型號為:蒸汽管道支架、空調(diào)水管及消防水管支架全部采用14
號優(yōu)質(zhì)槽鋼。橋架綜合支架在管廊內(nèi)用12號優(yōu)質(zhì)槽鋼、架空區(qū)域采用10號優(yōu)質(zhì)槽鋼。綜合
給水管支架采用12號優(yōu)質(zhì)槽鋼。
7.膨脹螺栓的選取
查詢膨脹螺栓參數(shù)得此下表:
管道的運行重量為:q2=129.192kg/m,14號槽鋼每米重量16.733kg/m,計算的整體重
量為W=129.192*6*4+16.733*3=3151kg。支架兩端鋼板上各使用4個膨脹螺栓,選用12號
國標標準膨脹螺栓,最大承受重量G=8*2650=21200kg>W;所以可以選用12號膨脹螺栓。
依據(jù)據(jù)施工規(guī)范中對支架間距得要求以及施工現(xiàn)場情況,對于支架排布,給排水及暖通
17
專業(yè)取支架間距為6m,橋架支架間距為2m。其簡化示意圖如下圖所示,取固定支架的間距
取60m,具體情況根據(jù)現(xiàn)場預(yù)留的伸縮縫來確定,對于波紋補償器的放置位置,距離固定支
架1m左右位置放置一個波紋補償器,固定支架之間全部采用活動支架,活動支架下端部用
木托墊起,上端部用抱箍進行固定。
支架間距示意圖
5.3管道管托
管道管托示意圖如下所示,管道下端部用木托墊起來,上端部木托與下端部木托合并為
一個整體,然后用抱箍進行緊固,最后用螺栓進行固定。
管道管托示意圖
18
第6章管道運輸與管道安裝
6.1管道運輸
1.大口徑的蒸汽管道訂貨后,供貨時直接由場外運至安裝現(xiàn)場,并按照安裝位置需用的
數(shù)量依次卸貨,管道在運輸和吊裝時要采取保護措施,尤其是不銹鋼管道,以保護管道(特
別是管端)不損壞和變形。管子運至安裝現(xiàn)場后,吊車配合卸車。
2.空調(diào)水管道的安裝現(xiàn)場應(yīng)具備必要的運輸通道,以保證貨到現(xiàn)場后能夠及時送入安裝
現(xiàn)場經(jīng)檢驗后即時安裝。
3.大管徑的空調(diào)水管轉(zhuǎn)運時,利用2個5t的卷揚機進行牽引,將管道卸載到指定的地方。
6.2工藝流程:
管道安裝主要步驟有:
測量放線預(yù)制加工支架制作安裝管道安裝
管道清洗管道試壓
1.測量放線
管道安裝應(yīng)測量好管道坐標、標高、坡度線。管道安裝時,應(yīng)復(fù)核水管的公稱壓力、等
級和使用場合。管道的標識應(yīng)面向外側(cè),處于明顯位置。
2.預(yù)制加工
管材切割前,必須正確丈量和計算好所需長度,用記號筆在管表面畫出切割線。切割管
材必須使端面垂直于管軸線。管材切割應(yīng)使用管道切割機,且根據(jù)不同材質(zhì)的管材進行切割
片的跟換,不宜用鋼鋸鋸斷管材,在焊接前應(yīng)該進行坡口打磨。管材與管件的連接必須清潔、
干燥、無油污。連接彎頭或三通等管件時,應(yīng)注意管道的走向。宜先進行預(yù)裝,校正好方向,
用墨線畫出軸向定位線。
3.支吊架制作安裝
19
常用的管道支吊架按用途分為:固定支架、導(dǎo)向支架、活動支架等。管道支吊架的布置
和類型應(yīng)滿足管道荷重、補償量及位移的要求,并注意減少管道的震動;另外,還必須考慮
管道的穩(wěn)定性、強度和剛度以及輸送介質(zhì)的溫度和工作壓力,并盡量簡便易于節(jié)約鋼材。管
道支架加工制作前應(yīng)根據(jù)管道的材質(zhì)、管徑大小等按標準圖集進行選型。鋼管支吊架間距不
得大于規(guī)范要求。
支吊架與鋼板焊接處需要滿焊,同時在250*250鋼板(10mm厚)上打上4個12號膨
脹螺栓到稱重墻或梁上,螺栓對稱排布。
支架固定鋼板大樣圖
6.3管材、管件、附屬配件的檢驗
20
1.無縫鋼管、管件、閥門、焊材等必須具有材質(zhì)證明書或產(chǎn)品合格證書,并且需進行檢
查、收集和整理歸檔。
2.按設(shè)計要求核對管子、管件、附屬配件的規(guī)格、材質(zhì)、型號,并檢查其外面,不得有
裂紋、縮孔、氣泡、夾縫、折迭、重皮、毛刺、溝槽、傷痕等缺陷及銹蝕或凹陷超過壁厚的
負偏差。
3.閥門表面不得有粘砂、裂紋、縮孔等缺陷、開關(guān)應(yīng)靈活可靠,無卡澀現(xiàn)象。
6.4管道支架制作安裝
1.根據(jù)設(shè)計圖、夾層通道的尺寸,測量管架標高。
2.根據(jù)支架標準圖進行管道支架的下料、焊接制作,并按要求做好支架除銹、刷油與防
腐工作。
3.按設(shè)計及現(xiàn)場深化設(shè)計要求進行支架安裝??照{(diào)水管道系統(tǒng)的管道支架安裝時,應(yīng)按
照系統(tǒng)要求,從空調(diào)水供(回)水管道起,順著供水(回)方向依次安裝。管道分層布置時,
應(yīng)先安裝上層管道支架及管道,然后再依次安裝中層及下層。這就要求確定支架制作和管道
安裝工序先后,完成支架及管道的正常安裝。
4.夾層通道式分層管道支撐安裝時,應(yīng)考慮管道安裝時的吊裝方便,為此要求夾層通道
管道支撐安裝時,先將管道運至安裝點,做好整體支架后再行安裝,否則需安裝的管道很難
順利吊裝到位。其安裝時需借助最上層管道支撐,待管道吊裝到管架上后再行安裝,以便于
管道正常吊裝。其他的依此類推進行安裝。
6.5管道下料及坡口加工方式
1.根據(jù)施工平面圖和系統(tǒng)圖所標注的規(guī)格、尺寸,再根據(jù)現(xiàn)場實際情況,空調(diào)水管單根
管道長度大約為6m,夾層通道大部分為直線段,以6m為基準進行焊接施工。需要加工切割
的管道提前加工預(yù)制完成再運送至夾層安裝。
21
2.坡口加工(坡口加工圖見焊接檢驗部分)必須按照規(guī)范要求進行,對口焊接角度為45
度,坡口間距為0-2mm,保證其型式正確、尺寸準確,且宜采用機械方法。如采用氣割時,
坡口面上的氧化熔渣、飛濺等物必須清理干凈,并將凹凸不平處修理平整。
6.6管道安裝
1.管道安裝前,必須將管道內(nèi)部清理干凈,管節(jié)應(yīng)按管道系統(tǒng)號和預(yù)制順序號進行安裝。
每一段管道焊接完成后檢查管道內(nèi)部,不允許將施工工具遺漏在管道內(nèi)。
2.由于蒸汽管道口徑較大,在管道安裝前,首先制作好B-A~B-B軸東西兩側(cè)支架,這就
要求首先將管道通過手動葫蘆移放到位,并且管托進行預(yù)制,以盡量減少夾層通道內(nèi)作業(yè),
保證施工安全,提高施工機械利用率,加快施工進度。
3.不銹鋼管材、管件應(yīng)統(tǒng)一歸類分開放置,不與碳鋼類材料混放,并采取防止鐵銹、雨
水等腐蝕措施。
4.不銹鋼管應(yīng)使用砂輪機切割或等離子切割機切割,坡口加工使用角向磨光機。
5.不銹鋼管道在組對預(yù)制過程中,避免使用鐵制工具敲擊管段,盡量增大地面預(yù)制量,
減少固定焊口的數(shù)量。
6.不銹鋼管應(yīng)用機械或等離子方法切割。當用砂輪切割或修磨時,應(yīng)有專用砂輪片。
7.不銹鋼管不準直接與碳鋼支架接觸,應(yīng)在支架與管道之間墊入不銹鋼片、或不含氯離
子的塑料、橡膠墊片。
8.不銹鋼管道法蘭用的墊片應(yīng)用氯離子含量不超過50ppm的非金屬墊片。
9.管道連接時應(yīng)避免臟物的影響和氧化膜的破壞。
10.管道安裝時,應(yīng)檢查法蘭密封面及密封墊片,不得有影響密封性能的劃痕、斑點等缺
陷。
22
11.法蘭連接應(yīng)與管道同心,并應(yīng)保證螺栓自由穿入。法蘭間應(yīng)保持平行,其偏差不得大
于法蘭外徑的1.5%,且不得大于2mm。不得用強緊螺栓的方法消除歪斜。螺栓的安裝方向
應(yīng)一致。螺栓緊固應(yīng)對稱均勻操作。緊固后應(yīng)與法蘭緊貼,需加墊片時,每個螺栓不應(yīng)超過
一個。法蘭連接時應(yīng)對接平行、緊密,與管道中心線垂直,墊片不應(yīng)使用雙層,螺母應(yīng)在同
一側(cè),螺桿露出的長度不應(yīng)大于螺栓直徑的1/2。
12.管子安裝平直度應(yīng)在距接口中心200mm處測量,當管徑小于100mm時,允許偏差
為1mm,當管徑大于或等于100mm時,允許偏差為2mm;但全長允許偏差均為10mm。
13.穿墻套管規(guī)格比管道的規(guī)格高兩檔。管道與套管之間的空隙應(yīng)采用不燃材料填充。
當管道安裝工作有間斷時,應(yīng)及時封閉敞開的管口。
15.與設(shè)備連接符合設(shè)計或工藝設(shè)備技術(shù)文件規(guī)定(如采用金屬軟管連接方式)。
16.管道安裝的允許偏差見下表規(guī)定:
項目允許偏差(mm)
室內(nèi)15
坐標
室外25
室內(nèi)±15
標高
室外±20
DN≤1002L‰最大50
水平管道平直度
DN>1003L‰最大80
立管鉛垂度5L‰最大50
成排管道間距15
交叉管的外壁或絕緣層間間距20
(注:L為管子有效長度)
摘自《工業(yè)金屬管道工程施工及驗收規(guī)范》GB50235-97
6.7閥門安裝
1.按設(shè)計文件核對其型號,并按介質(zhì)流向確定其安裝方向。在安裝前,均應(yīng)檢查閘板與
密封面是否清潔。安裝后,在無水條件下按照操作程序啟閉三次,以保證開啟靈活。對于電
23
動閥門、閘門的安裝,首先要弄清其工作原理,同時在安裝時請電氣專業(yè)的技術(shù)人員配合進
行。
2.閥門安裝應(yīng)牢固、嚴密,與管道中心線同心,操作機構(gòu)靈活、準確。各種閥門的性能、
結(jié)構(gòu)、材質(zhì)、防腐蝕以及各種技術(shù)參數(shù)均應(yīng)符合設(shè)計要求。
3.閥門應(yīng)在關(guān)閉狀態(tài)下安裝。安裝方位應(yīng)符合設(shè)計要求,操作方便,開關(guān)靈活。
4.閥門安裝前,應(yīng)作強度和嚴密性試驗。試驗應(yīng)在每批(同牌號、同型號、同規(guī)格)數(shù)量中
抽查10%,且不少于一個。對于安裝在主干管上起切斷作用的閉路閥門,應(yīng)逐個作強度和嚴
密性試驗。閥門的強度和嚴密性試驗,應(yīng)符合下列規(guī)定:閥門的強度試驗壓力為公稱壓力的
1.5倍;嚴密性試驗壓力為公稱壓力的1.1倍;試驗壓力在試驗持續(xù)時間內(nèi)應(yīng)保持不變,且殼
體填料及閥瓣密封面無滲漏。
5.在安裝波紋補償器前,必須充分了解產(chǎn)品參數(shù)如伸縮量,是否在產(chǎn)地進行了水壓試驗
及預(yù)拉伸等后,再確定其具體的安裝方法。
6.管道上大型閥門或部件均應(yīng)加上獨立支撐,以免大型閥門及部件的重力對管道造成壓
力。
24
第7章管道焊接
7.1施工一般要求
1.所有焊工合格證應(yīng)為有效證件,合格項目應(yīng)與從事項目相同。上崗前必須進行現(xiàn)場模
擬考試,合格者方可以上崗。
2.施工現(xiàn)場應(yīng)備有符合規(guī)范要求的焊接材料貯存場所,烘干設(shè)備。并建立嚴格的保管、
烘干、發(fā)放制度,以防止錯用和浪費。
3.焊接設(shè)備的電流表、電壓表、氣體流量計等儀表儀器以及規(guī)范參數(shù)調(diào)節(jié)裝置應(yīng)定期檢
查。
4.電焊條(碳鋼焊條)應(yīng)在350℃溫度下,烘干1小時,并放入保溫桶內(nèi)隨用隨取,保
證焊條溫度始終為120℃,且焊條不允許重復(fù)烘干,焊工應(yīng)使用小保溫桶將焊條運到工地,
一次領(lǐng)用數(shù)量不宜超過2小時的使用量,并且要做到隨用隨取。
5.不銹鋼管的焊接采用氬弧焊,管內(nèi)充氬保護,避免產(chǎn)生氧化腐蝕物,焊接前,將坡口
及其兩側(cè)20~30mm范圍內(nèi),清理干凈,然后再焊接。
6.不銹鋼管道安裝焊接前,在坡口端150mm范圍內(nèi)涂上白堊粉,防止在焊接時焊渣和飛
濺損傷管表面。
7.不銹鋼管的焊縫用涂刷法對焊縫及兩側(cè)部位酸洗。
7.2一般焊接程序
1.對管道質(zhì)量進行檢查,焊縫坡口、間隙、錯邊是否符合GB50236-98的三級焊縫標準。
2.按照焊接工藝卡所規(guī)定的焊接參數(shù)進行施焊,若由于特殊原因需改變焊接工藝中某個
參數(shù),需報告工藝制訂人經(jīng)同意后方可改變。
3.焊接外觀質(zhì)量自檢:焊接缺陷(如飛濺、氣孔、焊渣)由焊工自己處理,做到誰焊、
誰負責、誰處理。
4.焊縫質(zhì)量專檢:由焊接質(zhì)量檢查員或焊接工程師檢查并標識。
25
7.3焊接工藝
本工程不銹鋼管采用氬弧焊接,無縫鋼管采用手工電弧焊。氬弧焊絲宜采用BOEAS2-1G
或BOEAS4-1G型號的焊絲。
1.氬弧焊工藝
1)焊槍噴嘴直徑為8mm,鎢極直徑為2.5mm,電極伸出長度為6mm。
2)管道焊接時管內(nèi)應(yīng)防止穿堂風。
3)焊接時應(yīng)保持焊槍、焊絲與管口之間的相對位置,送絲可以采用斷續(xù)送進和連續(xù)送進
兩種方法,但要防止焊絲與高溫的鎢極接觸。噴嘴與工件的距離一般為10~15mm,焊槍可
作一點橫向擺動,焊絲應(yīng)均勻送入熔池,不要擾亂氣流,焊絲頭部應(yīng)始終放在氬氣保護區(qū)內(nèi)。
焊接終了時,應(yīng)多加焊絲,然后慢慢拉開。
2.焊接前的準備要求
1)焊條使用前應(yīng)進行烘烤,現(xiàn)場應(yīng)指定專人負責烘烤焊條,并做好領(lǐng)用記錄。
2)焊條應(yīng)裝入保溫筒,隨用隨取。焊條隔夜必須收回保溫箱(并做好記錄),防止受潮
變質(zhì)。堿性焊條次日使用,還要重新烘烤,一般烘烤不得超過三次。
3)坡口加工必須按照規(guī)范要求進行,保證其型式正確、尺寸準確,且宜采用機械方法。
如采用氣割時,坡口面上的氧化熔渣、飛濺等物體必須清理干凈,并將凹凸不平處修理平整。
4)接頭組對時一定要做到內(nèi)壁齊平,不得強力進行,組對時錯邊量不得超過壁厚的
10%,且不得超過1毫米。組對完成后的接頭應(yīng)及時進行點固焊,所用焊接方法和材料與正
式施焊時相同。
3.焊接過程
1)本工程不銹鋼管采用氬弧焊接,無縫鋼管采用手工電弧焊。
26
2)根據(jù)管道的材質(zhì)、規(guī)格、工作介質(zhì)及焊接時的環(huán)境溫度等情況,必要時在焊前對接頭
進行預(yù)熱,其預(yù)熱溫度為100-200℃,預(yù)熱區(qū)域應(yīng)不小于距接頭150毫米的范圍,焊接完成
后,立即對接頭進行熱處理。在熱處理時,應(yīng)嚴格按照規(guī)范要求執(zhí)行,并及時作好記錄。
3)在正式焊接時必須按焊接工藝卡或焊接指導(dǎo)書執(zhí)行,不得任意變更。焊接時應(yīng)認真操
作,仔細檢查,及時處理焊接缺陷。
4)多層多道焊時,接頭應(yīng)錯開,且應(yīng)逐層進行檢查,經(jīng)自檢合格后,方可焊接次層,直
至完成。同時還應(yīng)特別注意接頭和收弧的質(zhì)量,收弧時應(yīng)將熔池填滿。
5)經(jīng)檢查需返修或補焊時,應(yīng)有具體的返修或補焊工藝措施,需作熱處理的,在返修或
補焊后應(yīng)重做熱處理。
6)焊接過程中,還應(yīng)注意周圍環(huán)境的影響。不能有妨礙焊接工作的環(huán)境因素產(chǎn)生,否則,
應(yīng)采取有效措施予以防護。
7.4焊接檢驗
1.焊接過程中應(yīng)時時對焊接質(zhì)量進行檢查和檢驗,做好焊接質(zhì)量三級檢查驗收工作。
2.焊接完成后對焊縫進行外觀檢查,外觀檢查不合格的焊縫,不得進入下一道工序,外
觀質(zhì)量合格標準為:
1)焊縫加強高為0-3毫米,寬度為坡口每側(cè)增寬約2毫米。
2)不允許有裂紋、未熔合、氣孔、夾渣。
3)根部未焊透的深度不大于厚度的10%且不大于1.5毫米,總長度不大于焊縫全長的
10%。
4)咬邊深度不大于0.5毫米,焊縫兩側(cè)總長不大于焊縫全長的20%。
5)內(nèi)凹不大于2毫米。
6)外觀檢查合格后及時作好記錄。
27
3.焊縫坡口的基本型式與尺寸如下表所示:
坡口形式間隙鈍邊
坡口角度
圖示壁厚t(mm)(mm)(mm)
3-90-20-2650—750
bt
α9-260-30-3550—650
摘自《埋弧焊焊縫坡口的基本形式和尺寸》GB986-88
4.焊縫外觀質(zhì)量檢查:焊縫邊緣應(yīng)圓滑過渡到基本金屬表面,焊縫表面外觀質(zhì)量應(yīng)符合
下表要求。
接頭類別質(zhì)量要求
缺陷名稱Ⅰ級Ⅱ級
裂紋不允許
每50mm焊縫長度內(nèi)允許直徑≤0.3δ,
表面氣孔
且≤2mm≥氣孔2個
表面夾渣深≤0.1δ長≤0.3δ,且≤10mm
不加墊單面焊≤0.15δ,且≤1.5mm
未焊透
不允許缺陷總長在6δ焊縫長度內(nèi)不超過δ
深度≤0.5mm,焊縫兩側(cè)咬邊總長≤焊
咬邊
縫全長的10%
≤0.3+0.05δ,且≤1mm;每100mm焊
角焊縫厚度不足
縫長度內(nèi)缺陷總長度≤25mm
≤0.2+0.02δ,且≤0.5mm,長
根部收縮≤0.2+0.02δ,且≤1mm,長度不限
度不限
角焊縫焊腳不對稱差值≤1+0.1a差值≤2+0.15a
余高≤1+0.1b,且最大為3mm≤1+0.2b,且最大為5mm
表中a—設(shè)計焊縫厚度b—焊縫寬度δ—母材厚度
摘自《現(xiàn)場設(shè)備、工業(yè)管道焊接工程施工及驗收規(guī)范》GB50236-98
28
第8章管道試壓與清洗
8.1管道系統(tǒng)試驗前應(yīng)具備下列條件
1.管道系統(tǒng)施工完畢,符合設(shè)計要求和規(guī)范規(guī)定。
2.焊接完畢并經(jīng)檢驗合格,焊縫及其他在試驗中應(yīng)檢查的部位未涂漆。
3.支、吊架安裝完畢。
4.管道上的膨脹節(jié)已設(shè)置了
溫馨提示
- 1. 本站所有資源如無特殊說明,都需要本地電腦安裝OFFICE2007和PDF閱讀器。圖紙軟件為CAD,CAXA,PROE,UG,SolidWorks等.壓縮文件請下載最新的WinRAR軟件解壓。
- 2. 本站的文檔不包含任何第三方提供的附件圖紙等,如果需要附件,請聯(lián)系上傳者。文件的所有權(quán)益歸上傳用戶所有。
- 3. 本站RAR壓縮包中若帶圖紙,網(wǎng)頁內(nèi)容里面會有圖紙預(yù)覽,若沒有圖紙預(yù)覽就沒有圖紙。
- 4. 未經(jīng)權(quán)益所有人同意不得將文件中的內(nèi)容挪作商業(yè)或盈利用途。
- 5. 人人文庫網(wǎng)僅提供信息存儲空間,僅對用戶上傳內(nèi)容的表現(xiàn)方式做保護處理,對用戶上傳分享的文檔內(nèi)容本身不做任何修改或編輯,并不能對任何下載內(nèi)容負責。
- 6. 下載文件中如有侵權(quán)或不適當內(nèi)容,請與我們聯(lián)系,我們立即糾正。
- 7. 本站不保證下載資源的準確性、安全性和完整性, 同時也不承擔用戶因使用這些下載資源對自己和他人造成任何形式的傷害或損失。
最新文檔
- 2025河南平煤神馬平綠置業(yè)有限責任公司招聘3人參考筆試題庫附答案解析
- 2025四川成都市青羊區(qū)新華少城社區(qū)衛(wèi)生服務(wù)中心招聘3人參考筆試題庫附答案解析
- 2025恒豐銀行南京分行社會招聘29人參考筆試題庫附答案解析
- 2025廣西北海市中日友誼中學秋季學期教師招聘1人備考考試試題及答案解析
- 2025年哈爾濱市南崗區(qū)殘疾人聯(lián)合會補充招聘殘疾人專職委員2人模擬筆試試題及答案解析
- 2025江蘇蘇州大學科研助理崗位招聘10人備考筆試試題及答案解析
- 網(wǎng)咖投資合同范本
- 網(wǎng)格員用工協(xié)議書
- 職場綠化合同協(xié)議
- 聯(lián)保勞動合同范本
- 教師資格認定申請表
- 中山大學二外法語考研真題及詳解(2012~2014)【圣才出品】
- 鋪路鋼板租賃合同路基箱鋼板租賃2024年
- 《直播運營實務(wù)》中職全套教學課件
- 隧道內(nèi)棧橋設(shè)計計算書
- 2022年下半年教師資格證考試《高中生物》題(題目及答案解析)
- 北京市豐臺區(qū)2023-2024學年六年級上學期期末英語試題
- 中孕期產(chǎn)前超聲檢查
- 超星爾雅學習通《從愛因斯坦到霍金的宇宙(北京師范大學)》2024章節(jié)測試含答案
- 二年級勞動教案整理書包
- 上海華東師大二附中2024屆招生全國統(tǒng)一考試(模擬卷)物理試題
評論
0/150
提交評論