文檔簡介
目錄
1編制依據(jù)、范圍及原則....................................................1
1.1編制依據(jù)............................................................1
1.2編制范圍............................................................1
1.3編制原則............................................................1
2工程概況................................................................3
2.1項目簡介............................................................3
2.3橋梁結(jié)構(gòu)............................................................4
2.3.1主橋結(jié)構(gòu).......................................................4
2.3.2引橋結(jié)構(gòu)......................................................11
2.4工程數(shù)量...........................................................14
2.5技術(shù)標準...........................................................15
2.6工程特點、重點及難點...............................................16
2.6.1工程特點.......................................................16
2.6.2工程重點及難點................................................16
2.6.3對策分析及措施................................................17
3環(huán)境及資源條件.........................................................19
3.1自然條件...........................................................19
3.1.1水文條件.......................................................19
3.1.2通航條件.......................................................19
3.1.3地質(zhì)條件......................................................20
3.1.4氣候特點......................................................21
3.2交通運輸...........................................................21
3.3材料供應(yīng)..........................................................21
3.4水、電、燃料等資源................................................21
3.5通訊條件...........................................................22
4施工組織安排...........................................................22
4.1建設(shè)總體目標.......................................................22
4.1.1工期目標.......................................................22
4.1.2質(zhì)量目標.......................................................22
4.1.3安全目標.......................................................22
4.1.4成本目標.......................................................22
4.1.5環(huán)境保護目標...................................................22
4.1.6文明施工目標...................................................23
4.1.7職業(yè)健康安全目標...............................................23
4.2施工組織機構(gòu).......................................................23
4.2.1項目管理原則...................................................23
4.2.2項目管理方法...................................................23
4.2.3施工組織機構(gòu)及框圖........................................24
4.2.4施工隊伍部署及任務(wù)劃分.........................................25
4.3_L?-vi**JclJ27
4.3.1總工期及開竣工日期.............................................27
4.3.2各階段工期安排.................................................27
4.3.3總體工程施工進度計劃安排......................................29
5場地布置及大臨設(shè)施.....................................................30
5.1場地規(guī)劃布置.......................................................30
5.1.1場地布置原則...................................................30
5.1.2總體平面布置...................................................30
5.1.3生活區(qū)布置.....................................................30
5.1.4生產(chǎn)區(qū)布置.....................................................31
5.2大臨設(shè)施布置.......................................................34
5.2.1進場道路及施工便道.............................................34
5.2.2混凝土工廠.....................................................34
5.2.3生產(chǎn)、生活用水.................................................34
5.2.4生產(chǎn)、生活用電.................................................35
5.2.5施工棧橋.......................................................35
5.2.6起重碼頭.......................................................38
6控制及重難點工程施工方案..............................................40
6.1主墩基礎(chǔ)施工方案..................................................40
6.1.1施工總體方案...................................................40
6.1.2雙壁鋼套箱圍堰基坑清理.........................................44
6.1.3圍堰設(shè)計與制造.................................................47
6.1.4圍堰浮運、定位.................................................52
6.1.5鉆孔樁施工.....................................................56
6.1.6?—?-1*66
6.2主橋邊墩及輔助墩基礎(chǔ)施工方案......................................68
6.2.11#墩施工方案...................................................68
6.2.22#墩施工方案...................................................72
6.2.36#墩施工方案...................................................75
6.2.47#、8#墩施工方案...............................................75
6.3主塔施工方案.......................................................78
6.3.1總體施工方案...................................................78
6.3.2總體施工步驟..................................................82
6.3.3總體施工布置..................................................84
6.3.4施工測量控制..................................................84
6.3.5下塔柱施工....................................................84
6.3.6下橫梁施工....................................................87
6.3.7中塔柱施工.....................................................90
6.3.8上塔柱施工.....................................................93
6.4鋼梁架設(shè)方案.......................................................96
6.4.1總體架設(shè)方案...................................................96
6.4.2總體架設(shè)步驟...................................................96
6.4.3主要臨時設(shè)施及機械.............................................99
6.4.4鋼梁制造、運輸................................................107
6.4.5鋼梁進場、存放及預(yù)拼..........................................107
6.4.6鋼箱梁架設(shè)....................................................109
6.4.7鋼桁梁架設(shè)....................................................114
6.4.8鋼梁合龍......................................................115
6.4.9高強螺栓施工..................................................118
6.4.10鋼梁涂裝.....................................................122
6.4.11支座安裝.....................................................123
6.4.12斜拉索掛設(shè)..................................................124
6.4.13監(jiān)控監(jiān)測....................................................128
7主要項目施工方案......................................................130
7.1施工準備..........................................................130
7.1.1技術(shù)準備......................................................130
7.1.2施工現(xiàn)場準備..................................................130
7.1.3勞動力準備....................................................131
7.1.4機械設(shè)備準備.................................................132
7.1.5物資材料準備.................................................132
7.1.6醫(yī)療、衛(wèi)生準備...............................................132
7.1.7生活后勤準備.................................................132
7.1.8環(huán)保準備......................................................133
7.1.9宣傳教育準備..................................................133
7.1.10其它準備.....................................................133
7.2試驗和測量控制....................................................133
7.2.1試驗控制......................................................133
7.2.2測量控制......................................................136
7.3主橋施工方案......................................................138
7.4引橋施工方案......................................................138
7.4.1引橋總體施工方案概述..........................................138
7.4.2引橋下部結(jié)構(gòu)施工..............................................138
7.4.384nl鋼桁梁施工方案.............................................145
7.4.492nl鋼管混凝土拱橋施工方案....................................146
7.4.5120nl預(yù)應(yīng)力混凝土連續(xù)梁施工方案...............................151
7.4.652nl預(yù)應(yīng)力混凝土簡支梁施工方案............................158
7.5鐵路橋面系及附屬工程施工..........................................160
7.5.1擋磴墻及電纜槽施工............................................160
7.5.2綜合接地施工..................................................160
7.5.3防水層鋪裝和橋上排水系統(tǒng)施工.................................160
7.5.4橋梁伸縮縫施工...............................................161
8資源配置方案..........................................................162
8.1勞動力配置........................................................162
8.2機械、儀器設(shè)備配置................................................162
8.3材料供應(yīng)..........................................................163
9管理措施..............................................................164
9.1質(zhì)量管理措施......................................................164
9.1.1質(zhì)量保證體系..................................................164
9.1.2質(zhì)量保證措施..................................................168
9.2安全管理措施......................................................180
9.2.1安全保證體系..................................................180
9.2.2安全保證措施..................................................183
9.2.3安全應(yīng)急預(yù)案..................................................197
9.3工期保證措施......................................................203
9.3.1工期保證體系..................................................203
9.3.2工期保證措施..................................................204
9.4環(huán)保及水保措施....................................................208
9.4.1環(huán)保、水保保證體系............................................208
9.4.2環(huán)境保護措施..................................................209
9.4.3水土保持措施..................................................213
9.4.4臨時用地復墾方案..............................................214
9.5冬季、夏季和雨季施工措施..........................................215
9.5.1冬季施工措施..................................................215
9.5.2雨季施工措施..................................................217
9.5.3夏季施工措施..................................................220
9.6文明施工及文物保護................................................222
9.6.1文明施工保證體系..............................................222
9.6.2文明施工措施..................................................223
9.6.3文物保護措施..................................................227
9.7職業(yè)健康安全保障措施..............................................228
9.7.1保證體系......................................................228
9.7.2保障措施......................................................229
9.7.3應(yīng)急處理預(yù)案.................................................232
10引用的設(shè)計文件與施工規(guī)范............................................234
10.1引用的設(shè)計文件..................................................234
10.2引用的施工規(guī)范..................................................234
11施工組織圖表.........................................................235
附圖1:總體施工進度計劃橫道圖........................................236
附圖2:總體施工進度計劃網(wǎng)絡(luò)圖........................................237
附圖3:施工總平面布置圖..............................................238
附表1:勞動力資源配置表..............................................240
附表2主要機械設(shè)備表.................................................241
附表3:主要儀器設(shè)備表................................................245
附表4:主要材料計劃供應(yīng)表............................................248
附表5:大臨設(shè)施匯總表................................................249
1編制依據(jù)、范圍及原則
1.1編制依據(jù)
1、新建蒙西至華中鐵路荊州至岳陽段洞庭湖特大橋施工圖及其說明書等。
2、新建蒙西至華中鐵路荊州至岳陽段公安長江公鐵兩用特大橋和洞庭湖特大橋
工程MHQS-01標段投標文件及施工合同文件。
3、新建蒙西至華中鐵路荊州至岳陽段指導性施工組織設(shè)計。
4、我公司依據(jù)GB/T19001-2008質(zhì)量標準體系、GB/T24001-2004環(huán)境管理體系和
GB/T28001-2001職業(yè)健康安全標準建立的質(zhì)量、環(huán)境、職業(yè)健康管理體系和程序文件。
5、工程現(xiàn)場調(diào)查、采集、咨詢所獲取的資料。
6、我公司擁有的科學技術(shù)成果、工法成果、機具設(shè)備裝備情況、施工技術(shù)與管
理水平以及武漢天興洲長江大橋、南京大勝關(guān)長江大橋以及在建的寧安城際鐵路安慶
長江大橋等過江鐵路工程積累的施工經(jīng)驗。為完成本工程工程擬投入的施工管理、專
業(yè)技術(shù)人員、機械設(shè)備等資源。
7、根據(jù)鐵道部下發(fā)的《關(guān)于積極倡導架子隊管理模式的指導意見》(鐵建設(shè)
[2008]51號)的規(guī)定以及建設(shè)單位、我公司的有關(guān)規(guī)定。
8、國家及相關(guān)部委頒布的法律、法規(guī)和鐵道部頒布的現(xiàn)行設(shè)計規(guī)范、施工規(guī)范、
鐵路工程質(zhì)量驗收標準、客運專線鐵路標準規(guī)范及其它有關(guān)文件資料。
1.2編制范圍
本施工組織設(shè)計編制的范圍為新建蒙西至華中鐵路荊州至岳陽段公安長江公鐵
兩用特大橋和洞庭湖特大橋工程MHQS-01標段中洞庭湖特大橋工程部分,其設(shè)計里程
為DK152+693.848?DK163+122.158,全長10444.66m。主要工程內(nèi)容:除鐵路T梁預(yù)
制、運輸、架設(shè)及相關(guān)工程外的全部橋涵工程(含綜合接地、防雷、接觸網(wǎng)立柱基礎(chǔ)
及預(yù)埋件、電纜槽道、人行步道板、蓋板、防護網(wǎng)、圍欄、檢查梯及取棄土場綠化等)
及通信、電力等三電管線遷改工程。
1.3編制原則
1、積極響應(yīng)和遵守招標文件中的工期、質(zhì)量、安全、環(huán)境保護、文明施工等規(guī)
定及鐵路建設(shè)工程施工合同、施工合同協(xié)議條款內(nèi)容。
2、保證重點,突出難點,做到總體部署和分項工程相結(jié)合、重點工程和一般工
程相結(jié)合、高新技術(shù)與既有技術(shù)相結(jié)合。
3、堅持按項目法管理的原則。通過與建設(shè)單位、監(jiān)理單位和設(shè)計單位協(xié)作,綜
合運用人員、機械、物資、資金和信息,實現(xiàn)質(zhì)量和造價在保證安全和工期前提下的
最佳組合。在每道工序施工中,加大自檢自查力度,嚴格執(zhí)行監(jiān)理工程師的指令,尊
重并服從監(jiān)理的意見,嚴格管理。
4、遵循“重視環(huán)境、保護環(huán)境”的原則,做到不擾民,重視生態(tài)環(huán)境,不污染
環(huán)境。在施工期間及竣工通車后保證不發(fā)生水土流失,保證不破壞環(huán)境。貫徹執(zhí)行國
家和當?shù)卣姆结樥?,遵守法律法?guī),尊重和保護工程施工所在地的民俗風情。
5、堅持用工制度的動態(tài)管理。根據(jù)工作的需要,合理配置勞動力資源。
6、按照要求編制質(zhì)量管理體系程序文件,按照投標文件對安全、質(zhì)量目標的承
諾進行嚴格的管理和有效的實施。
7、安全第一、質(zhì)量至上原則。精心組織施工,合理安排工期。堅持技術(shù)先進、
方案優(yōu)化、重合同守信譽、施工組織、科學合理、按期優(yōu)質(zhì)安全高效、不留后患。
8、遵循與設(shè)計、規(guī)范和驗標保持一致的原則。在編寫施工工藝時,嚴格按設(shè)計
要求,認真執(zhí)行現(xiàn)行本工程專用條款及施工技術(shù)規(guī)范和驗收標準,確保工程質(zhì)量優(yōu)良。
9、堅持實事求是的原則。在制定本施工組織設(shè)計時,根據(jù)我方施工經(jīng)驗和管理
水平,堅持科學組織,合理安排,均衡生產(chǎn),確保優(yōu)質(zhì)、高效地完成本工程工程建設(shè)。
10、木著先進性與適用性相結(jié)合的原則,采用成熟可靠的技術(shù),加強工序控制,
確保優(yōu)質(zhì)、安全、快速、高效建成該工程;并以先進可靠的施工方法和工藝控制投資,
降低成本。
11、堅持“高標準、高質(zhì)量、科研先行”的原則,以“高、精、尖”為要求,選
擇配置施工設(shè)備、施工技術(shù)、施工工藝,關(guān)鍵特殊工序遵循先試驗、后實施,做到安
全可靠。
2工程概況
2.1項目簡介
新建蒙西至華中鐵路荊州至岳陽段工程位于鄂中南和湘東地區(qū),線路起自湖北省
荊州市,向南經(jīng)湖北省的江陵、公安、石首等市縣,以及湖南省的華容縣至岳陽市,
洞庭湖特大橋是線路跨越湘江洞庭湖口的特大鐵路橋梁。
洞庭湖特大橋位于湖南省岳陽市,大橋由君山區(qū)向東南方向跨越洞庭湖與長江相
連接的出口處,距上游混庭湖公路橋約4.2km,距下游蓮花塘水位站約2.2km,河道
兩岸均為湘江漫灘區(qū)。君山岸地處湘江與長江之間,為湘江泄洪區(qū),地面多被蘆葦?shù)?/p>
植被覆蓋,屬岳陽紙業(yè)蘆葦農(nóng)場,地勢平坦,地勢開闊,地面高程一般+27.0?+31.0小,
湘江與長江之間的防洪大堤堤頂高程+35.9?+36.2m;岳陽岸為吉家湖魚場,堤內(nèi)主
要為魚塘及菜地,地形平坦,地面高程一般為+26.0?+28.0m。橋址里程DK158+500
以東為剝蝕殘丘區(qū),地面起伏較大,地面高程為+23.0?+44.0m。沿湖路筑有防洪大
堤,堤面高程+34.9?+35.8mo
洞庭湖特大橋設(shè)計里程為DK152+693.848?DK163+122.158,全長10444.66m。
2.2橋跨布置
洞庭湖特大橋橋跨布置為2X32m預(yù)應(yīng)力混凝土簡支T梁(君山岸陸地引橋)+92m
鋼管混凝土拱橋(跨君山岸大堤)+U0X32m預(yù)應(yīng)力混凝土簡支T梁(君山岸灘地引
橋)+4X52m預(yù)應(yīng)力混凝土簡支箱梁(君山岸灘地引橋預(yù)留建閘條件)+83X32m預(yù)應(yīng)
力混凝土簡支T梁(君山岸灘地引橋)+(75+3X120+75)m預(yù)應(yīng)力混凝土連續(xù)梁(預(yù)
留邊灘河道疏浚規(guī)劃條件)+(98+140+406+406+140+98)m三塔鋼箱鋼桁結(jié)合梁斜拉
橋(主橋)+84m簡支鋼桁梁(跨沿湖路橋)+57X32m預(yù)應(yīng)力混凝土簡支T梁(岳陽
岸引橋)。橋跨布置見“圖2-1”。
君山<=)=岳陽
圖2-1洞庭湖特大橋橋跨布置示意圖
2.3橋梁結(jié)構(gòu)
2.3.1主橋結(jié)構(gòu)
1、結(jié)構(gòu)體系
洞庭湖特大橋主橋為(98+140+406+406+140+98)m三塔雙索面鋼箱鋼桁結(jié)合梁
4#主塔與主梁間順橋向設(shè)置固定支座,限制主梁順橋向位移。3#及5#主塔與主梁
間使用帶限位功能的粘滯阻尼器。塔、梁間設(shè)置豎向約束,邊墩及輔助墩頂設(shè)置縱向
滑動支座提供豎向約束。
2、主梁
(D桁式布置
主梁為鋼箱鋼桁結(jié)合梁結(jié)構(gòu),主桁采用內(nèi)傾布置,上弦中心距12.0m,下弦中心
間距14.0m。全聯(lián)桁架為不帶豎桿的華倫式桁架,桁高12.0m,節(jié)間長14.0m,斜桿立
面傾角59.744°,全橋共92個節(jié)間,全橋以4號塔對稱布置,詳細布置見“圖2-3”。
⑵主桁構(gòu)件
主桁為空間兩片桁架結(jié)構(gòu),采用焊接的整體節(jié)點,在工廠內(nèi)將桿件和節(jié)點板、各
連接件的接頭板焊成一體,運到工地架設(shè)時,在節(jié)點之外用高強度螺栓拼接。主桁結(jié)
構(gòu)和橋面系構(gòu)件采用Q370qE材質(zhì)的鋼板,桿件最大板厚50mnb節(jié)點板最大厚度50mm0
主桁上弦桿為箱型截面,上弦桿件內(nèi)高lOOOnmi,內(nèi)寬為800nm1,板厚20?50mm。
下弦箱桿件內(nèi)高2432mm,頂板寬2400mm,底板寬1950nlm,斜腹板凈距1600mm,
鋼箱腹板與頂?shù)装鍔A角85.2364°,板厚24?36mm。在下弦鋼箱外側(cè),為提高結(jié)構(gòu)的
抗風性能,設(shè)有風嘴,寬2200mm。
上、下弦桿均采用高強度螺栓連接,最大單根桿件重約57.3t。
腹桿有箱形和H型兩種截面形式。箱型截面外高800mm,板厚24?40nlm。H型為
腹板帶肋截面,高600mm,板厚16?32mm。
⑶預(yù)拱度
主橋鋼桁梁設(shè)置了拱度,由調(diào)整斜拉索的索力和桁梁起拱兩部分共同實現(xiàn)的。主
跨鋼梁僅通過調(diào)整斜拉索的索力來實現(xiàn)橋面的拱度;其余各邊跨通過桁梁起拱和調(diào)整
斜拉索的索力共同實現(xiàn)。鋼桁梁結(jié)構(gòu)的起拱,采用二弦節(jié)間長度不變,調(diào)整下弦系統(tǒng)
線轉(zhuǎn)角,相應(yīng)加長或縮短上弦節(jié)間長度的方法。
⑷索梁錨固結(jié)構(gòu)
本橋的索梁錨固結(jié)構(gòu)為設(shè)計在下弦鋼箱節(jié)點邊腹板上的鋼錨箱。鋼錨箱在工廠焊
接于下弦鋼箱腹板外側(cè),并在內(nèi)側(cè)增設(shè)豎向及縱向加勁板。
⑸聯(lián)結(jié)系
上平面縱向聯(lián)結(jié)系設(shè)置交叉式斜桿和橫向撐桿。斜桿及橫撐桿均為工字形截面。
每個節(jié)間均設(shè)橫向聯(lián)結(jié)系,以增強結(jié)構(gòu)的橫向剛度。橫向聯(lián)結(jié)系分三種形式:板
式橋門架、板式橫聯(lián)及隅撐。橋門架布置在橋墩及橋塔等支點處的斜桿上,橫聯(lián)在橋
跨中間每兩個節(jié)間設(shè)置一處,隅撐在未設(shè)橫聯(lián)與橋門架的節(jié)點上設(shè)置。
(6)鐵路橋面結(jié)構(gòu)
本橋采用整體性好、剛度大的正交異性板整體道作橋面結(jié)構(gòu),由縱肋、橫梁及其
加勁的鋼橋面板組成。
橋面板分塊制造和安裝,每節(jié)間的橋面板橫橋向分為三塊,由主桁的下弦箱焊連
橋面板端頭,以及在其間的一塊橋面板組成。
橋面板厚16mm,其下部設(shè)置間距600mm的U型縱肋。在每條線路的軌道之下設(shè)置
高500mm的倒T形縱梁。順橋向每隔3.5m設(shè)一道倒T形橫梁,橫梁的跨中高度為2.5m,
腹板上緣與橋面板焊連,橫梁下緣與下弦鋼箱底面平齊,二者采用高強螺栓栓接。
⑺斜拉橋壓重段鋼箱
在鋼梁E5?E9節(jié)間范圍設(shè)壓重段,壓重荷載500kN/ni,采用在鋼箱內(nèi)灌注高容重
混凝土的方法。
(8)支座及阻尼器
主橋在邊墩(1#、7訝)、輔助墩(2#、6#)、邊塔(3#-.5#)及中塔(4#)處均
設(shè)置有豎向支承和橫向支承,在中塔處還設(shè)有縱向支承。主橋鋼梁的豎向支座采用球
形鑄鋼支座,橫向抗風支座采用盆式支座。
本橋在兩個邊塔位置設(shè)置阻尼器,一個塔處設(shè)置四個阻尼器,全橋共8個縱向阻
尼器。
3、主塔
主塔采用鋼筋混凝土結(jié)構(gòu),橋面以上為倒Y形,橋面以下塔柱內(nèi)收為鉆石形。塔
頂高程+170.0m,塔根(承臺頂)高程+13.0m,承臺以上塔高157mo
塔柱順橋向尺寸6?12.8m,上塔柱標準段橫橋向尺寸為13m,中塔柱和下塔柱
橫向尺寸為4?8n】。
下塔柱高36m,采用空心矩形截面,順橋向邊長9.13?12.8m,壁厚1.5m,橫
橋向邊長5.94?8m,壁厚1.0m。底部設(shè)基座,下塔柱與中塔柱交界處設(shè)橫梁。
橫梁為預(yù)應(yīng)力混凝土結(jié)構(gòu),采用雙室空心矩形結(jié)構(gòu),高6.0m,寬7.8m,頂、底
板厚0.8m,腹板厚1.0m,支座處設(shè)有橫隔板。每塔布置60束15中S15.2預(yù)應(yīng)力鋼
絞線。
橫梁以上至塔柱合并段為中塔柱,高73.04m,采用空心矩形截面,順橋向邊長
7.42-8.87m,壁厚1.5m,橫橋向邊長4?5m,壁厚1.0m。
上塔柱高47.96m,為單箱三室截面,順橋向邊長6?7.42m,壁厚1.5m,橫橋
向邊長13m,壁厚0.8m,隔板厚0.8m,塔柱內(nèi)壁設(shè)外凸的鋸齒塊作為斜拉索的錨點。
上塔柱斜拉索錨固區(qū)設(shè)計為預(yù)應(yīng)力混凝土構(gòu)件,錨固塔壁內(nèi)采用井字型布置032預(yù)
應(yīng)力粗鋼筋。
主塔結(jié)構(gòu)詳細布置見“圖2-4”。
畫
蒯
始
螂
T和
z
畫
<??叩X就
4、斜拉索
斜拉索為空間雙索面,立面上每塔兩側(cè)共13對索,在中塔塔頂與邊塔橋面橫梁
上方布置一對長索,全橋164根斜拉索。斜拉索采用①7mm平行鋼絲索,外包雙層
PE護套,兩層PE護套間設(shè)置隔離層,ob=1670Mp2,分199中7、223①7、24107.
265①7、301①7、33707.349①7、379①7五種規(guī)格。斜拉索錨具為冷鑄錨。
本橋斜拉索除在預(yù)埋鋼管內(nèi)設(shè)置體內(nèi)減振器外,將設(shè)置體外液壓減振裝置。
5、基礎(chǔ)
3、4、5#主塔墩采用22根①3,0m鉆孔樁基礎(chǔ),按摩擦樁設(shè)計,持力層為微風化
板巖或破碎板巖。基樁采用梅花形布置,樁間距7.5m,3#墩樁長36nl,4#墩樁長40m,
5#墩樁長32m。
主塔墩承臺采用圓端形布置,平面尺寸44.51X25.5m,厚度為6.5m,承臺頂高
程為+13.0m。詳細布置見“圖2-5”。
1-1
參數(shù)表
?號L(ca)hW
336W-N.5
44喊-33.5
$3210-J5.5
圖2-5主塔墩基礎(chǔ)布置圖
1#、7#墩身為圓端形門式墩,寬20nb厚5nb墩頂設(shè)置1.5m厚墩帽?;A(chǔ)采用
梅花形布置10根①L8m鉆孔樁基礎(chǔ),按摩擦樁設(shè)計,持力層為弱風化、微風化板巖,
或破碎板巖,1#墩樁長33m,7#墩樁長32唳承臺采用矩形承臺,平面尺寸直徑24X
9.2m,厚度為3.5m。詳細布置見“圖2-6”。
將
雯
雯
累
22
中S
密C
心
線
-
——
-
138魄i孔杜
^
―
▽-17.50(7.5。)
面
雌:
1、本田尺寸除商程以米計外,其余均以厘米計.
圖2-61#(7#)墩基礎(chǔ)布置圖
2#、6#墩身為圓端形門式墩,寬20m,厚5nb墩頂設(shè)置1.5m厚墩帽。2#基礎(chǔ)采
用12根中2.0m鉆孔樁基礎(chǔ),樁長30m。6#基礎(chǔ)采用10根①L8m鉆孔樁基礎(chǔ),樁長
30mo承臺采用矩形承臺,2#墩平面尺寸直徑24X13.6m,厚度為4.5m,6#平面尺寸
直徑24X9.2m,厚度為3.5m。詳細布置見“圖2-7”°
側(cè)面
550
F口南.!}。
十
+
橋
費
堆
S泰
S中
S中
心
心
次
戔
及
?*16.00(*2100)0+16.00(+22.0。)
圖2-72#(6#)墩基礎(chǔ)布置圖
2.3.2引橋結(jié)構(gòu)
1、君山岸跨大堤引橋
君山岸跨大堤橋梁采用92nl系桿拱橋。主梁采月邊主梁形式。梁高2.5m,系梁標
準橋面全寬16m,拱座處橋面加寬至17.6m,拱局18.4m。
橋梁立面及橫斷面見“圖2-8”。
橋丈立于布置田橋式制面布置困
*注:
t.
工林看iWf?夕敢
房iAt?.
X央JtMM”量機*f>*
幻.
£4+上看才%入根(及欄桿與蝮JI
松奸行,”桂.既&觸
充不”.
圖2-892m系桿拱橋布置圖
2、君山岸灘地引橋
君山岸灘地引橋總長7041.727m,
溫馨提示
- 1. 本站所有資源如無特殊說明,都需要本地電腦安裝OFFICE2007和PDF閱讀器。圖紙軟件為CAD,CAXA,PROE,UG,SolidWorks等.壓縮文件請下載最新的WinRAR軟件解壓。
- 2. 本站的文檔不包含任何第三方提供的附件圖紙等,如果需要附件,請聯(lián)系上傳者。文件的所有權(quán)益歸上傳用戶所有。
- 3. 本站RAR壓縮包中若帶圖紙,網(wǎng)頁內(nèi)容里面會有圖紙預(yù)覽,若沒有圖紙預(yù)覽就沒有圖紙。
- 4. 未經(jīng)權(quán)益所有人同意不得將文件中的內(nèi)容挪作商業(yè)或盈利用途。
- 5. 人人文庫網(wǎng)僅提供信息存儲空間,僅對用戶上傳內(nèi)容的表現(xiàn)方式做保護處理,對用戶上傳分享的文檔內(nèi)容本身不做任何修改或編輯,并不能對任何下載內(nèi)容負責。
- 6. 下載文件中如有侵權(quán)或不適當內(nèi)容,請與我們聯(lián)系,我們立即糾正。
- 7. 本站不保證下載資源的準確性、安全性和完整性, 同時也不承擔用戶因使用這些下載資源對自己和他人造成任何形式的傷害或損失。
最新文檔
- 2025年鄭州龍湖一中招聘工作人員備考題庫及答案詳解1套
- 普洱市第一中學2026年度急需緊缺人才第二批招聘備考題庫及答案詳解一套
- 武安市市場監(jiān)督管理局2025年公開招聘食品檢測專業(yè)技術(shù)人員的備考題庫及答案詳解一套
- 2025年齊齊哈爾醫(yī)學院附屬第一醫(yī)院公開招聘編制外眼科醫(yī)師備考題庫及一套答案詳解
- 中國人民人壽保險股份有限公司2026年校園招聘備考題庫及答案詳解參考
- 云南省衛(wèi)生健康委所屬事業(yè)單位開展2026年校園招聘309名備考題庫及答案詳解1套
- 2025年區(qū)某企業(yè)招聘勞務(wù)派遣人員備考題庫含答案詳解
- 2025年嘉興市經(jīng)英人才發(fā)展服務(wù)有限公司城南分公司公開招聘勞務(wù)派遣人員備考題庫有答案詳解
- 成都市龍泉驛區(qū)青臺山中學校2025年秋季教師招聘備考題庫及參考答案詳解1套
- 2025年成都市花園國際小學招聘儲備教師備考題庫及答案詳解1套
- 2025年10月自考04184線性代數(shù)經(jīng)管類試題及答案含評分參考
- 路燈養(yǎng)護投標方案(技術(shù)標)
- 幼兒園防火安全檢查記錄表
- 南方科技大學校聘能力測評英語測評
- 2023高效制冷機房系統(tǒng)應(yīng)用技術(shù)規(guī)程
- 第十一章靈巧彈藥
- 電力工程公司積成績效考核管理體系制度規(guī)定
- 銀行IT服務(wù)管理事件管理流程概要設(shè)計
- 地圖文化第三講古代測繪課件
- LY/T 2230-2013人造板防霉性能評價
- GB/T 34891-2017滾動軸承高碳鉻軸承鋼零件熱處理技術(shù)條件
評論
0/150
提交評論