文檔簡介
目錄
1、施工組織設(shè)計總說明..................................................14
1.1編制依據(jù)及編制原則.............................................14
1.1.1編制依據(jù)...................................................14
1.1.2編制原則...................................................15
1.1.3編制范圍...................................................16
1.2工程概況........................................................16
1.2.1工程位置和結(jié)構(gòu)形式........................................16
1.2.2工程范圍和數(shù)量............................................17
1.2.2.1工程范圍..............................................18
1.2.2.2主要工程數(shù)量.........................................18
1.2.3工程地質(zhì)和水文地質(zhì)........................................19
1.2.3.1工程地質(zhì)..............................................19
1.232地震烈度..............................................22
1.2.3.3水文地質(zhì)..............................................23
124站址周圍環(huán)境...............................................24
1.2.4.1地面交通及建筑物......................................24
124.2地下構(gòu)筑物及管線......................................25
1.3工程特點、重點、難點分析........................................26
1.3.1工程特點...................................................26
1.3.2工程重點難點..............................................26
2、施工總體部署....................................................28
2.1組織機構(gòu)與現(xiàn)場管理..........................................28
2.1.1組織機構(gòu)...............................................28
2.1.2現(xiàn)場管理..............................................28
2.2施工總體目標(biāo)...............................................30
2.2.1工期目標(biāo)...............................................30
2.2.2工程質(zhì)量目標(biāo)...........................................30
2.2.3安全目標(biāo)...............................................30
2.2.4文明施工及環(huán)境衛(wèi)生目標(biāo)................................30
2.2.5環(huán)境保護目標(biāo)...........................................30
2.3總體施工組織................................................31
2.4施工區(qū)段劃分及施工順序.....................................32
2.5施工總平面布置圖............................................33
2.5.1施工場地布置的原則.....................................33
2.5.2臨時設(shè)施布置及說明....................................39
2.5.3供電系統(tǒng)..............................................40
2.5.4給水系統(tǒng)..............................................46
255現(xiàn)場消防...............................................47
2.5.6施工期間排水防洪措施...................................47
3、交通疏解實施方案...............................................49
3.1施工期間的交通疏解及場內(nèi)交通組織...........................49
3.2場內(nèi)交通組織...............................................50
4、地下管線改移及保護方案..........................................50
4.1地下管線分布情況............................................50
4.2地下管線遷移及保護方案.....................................50
4.3施工期間與管線部門的協(xié)調(diào)....................................55
4.4地下管線遷移及保護措施.....................................56
5、施工方案和方法..................................................60
5.1車站施工方案綜述............................................60
5.1.1設(shè)計概況...............................................60
5.1.2車站主體結(jié)構(gòu)施工方案概述..............................61
5.2施工降水...................................................63
5.2.1車站水文地質(zhì)及降水方案設(shè)計.............................63
5.2.2降水井構(gòu)造............................................64
5.2.3降水井施工............................................65
5.2.3.1計算基坑出水量Q..........................................................................66
523.2水位降深計算.....................................66
5.233受降水漏斗影響高差計算...........................67
5.2.3.4降水井計算....................................67
5.2.3.5降水井布設(shè)方案................................69
5.2.3.6降水井成井施工工藝方法.........................71
5.2.4降水井檢測與運行管理....................................73
5.3圍護結(jié)構(gòu)及地基加固施工......................................74
5.3.1鉆孔灌注樁施工........................................74
5.3.1.1場地整平、基礎(chǔ)處理................................74
531.2樁位測放.........................................74
5.3.1.3埋設(shè)護筒..........................................74
5.3.1.4鉆機移位定位......................................75
5.3.1.5護壁泥漿的拌制....................................75
5.3.1.6鉆孔..............................................75
5.3.1.7成孔檢測及清孔....................................75
5.3.1.8鋼筋籠制作及吊裝..................................76
5.3.1.9水下硅灌注.......................................78
531.10樁頭清理........................................79
532人工挖孔樁施工.........................................79
5.3.2.1施工工藝流程.......................................80
5.322施工方法及要求....................................80
5.323硅灌注............................................85
532.4施工注意事項.......................................88
5.325起重安全措施.......................................89
5.326旋挖鉆機安全措施...................................90
5.3.2.7機械安全措施.......................................90
5.328應(yīng)急措施...........................................91
533地基加固施工...........................................93
5.3.3.1工藝原理...........................................93
533.2施工工藝流程圖....................................95
5.333袖閥管注漿施工方法................................95
533.4待凝...............................................99
5.335開環(huán)灌漿...........................................99
533.6終灌標(biāo)準(zhǔn):........................................100
5.3.3.7后備注漿措施......................................100
5.338壓力注漿時的監(jiān)測措施.............................100
5.3.3.9灌注材料及配比....................................100
5.3.3.10質(zhì)量控制.........................................101
5.4基坑開挖..................................................102
5.4.1基坑開挖順序..........................................102
5.4.2基坑開挖方法..........................................102
5.4.3開挖施工要求..........................................104
5.4.4開挖準(zhǔn)備工作..........................................105
5.4.6開挖設(shè)備與勞動組織....................................106
5.4.7土石方外運...........................................107
5.4.8應(yīng)急措施..............................................107
5.5基坑支護...................................................109
5.5.1樁間網(wǎng)噴施工工藝......................................109
552鋼支撐體系施工工藝、方法..............................112
5.6主體結(jié)構(gòu)施工...............................................114
5.6.1冠梁、擋土墻施工......................................114
5.6.1.1冠梁施工.........................................114
5.6.1.2擋墻施工.........................................115
5.6.2墊層施工..............................................116
5.6.3底板(底梁)施工......................................117
564側(cè)墻及中柱施工........................................117
5.6.5中板、頂板施工........................................118
5.6.6內(nèi)部結(jié)構(gòu)施工..........................................118
5.6.7預(yù)留、預(yù)埋件施工......................................119
5.6.8結(jié)構(gòu)施工技術(shù)措施......................................120
5.6.8.1鋼筋施工.........................................120
568.2模板施工........................................125
5.6.8.3混凝土施工....................................133
5.6.8.4預(yù)埋件及預(yù)留孔................................140
5.6.9主體結(jié)構(gòu)校施工質(zhì)量技術(shù)保證措施........................141
5.6.9.1混凝土裂縫控制..................................141
5.692大體積、大面積碎施工控制.........................143
5.6.10防雜散電流措施.......................................146
5.7車站防水施工...............................................147
5.7.1防水原則及標(biāo)準(zhǔn)........................................147
5.7.2結(jié)構(gòu)防水體系..........................................148
5.7.3結(jié)構(gòu)自防水...........................................149
5.7.4底板外防水施工......................................151
5.7.4.1施工方法........................................151
5.7.4.2施工工藝........................................151
5.7.5頂板防水施工..........................................152
5.7.5.1施工方法.........................................152
5.752施工工藝..........................................153
576側(cè)墻防水施工...........................................155
5.7.6.1防水設(shè)計.........................................155
5.7.6.2施工方法.........................................155
5.7.6.3施工工藝.........................................156
5.7.7特殊部位防水施工.....................................156
5.7.7.1施工縫防水施工..................................156
5.7.7.2變形縫防水施工..................................159
5.7.7.3主體與出入口、風(fēng)道接口處防水施工..............160
5.774穿墻管、后補孔防水施工........................160
5.8附屬結(jié)構(gòu)工程施工............................................161
5.8.1施工工藝..............................................162
6、施工測量與監(jiān)控量測.............................................166
6.1施工監(jiān)測...................................................166
6.1.1監(jiān)測目的..............................................166
6.1.2監(jiān)測項目..............................................166
6.1.3監(jiān)測方法..............................................167
6.2施工測量...................................................168
6.2.1測量控制樁點交接及復(fù)核測量............................168
6.2.2測量管理..............................................168
623平面控制測量與高程控制測量.............................169
6.2.7施工控制測量成果的檢查和檢測.........................171
6.2.8施工測量精度的保障措施................................172
7、施工進度計劃及措施.............................................173
7.1計劃工期...................................................173
7.2主要進度指標(biāo)...............................................173
7.3施工進度橫道圖............................................173
7.4施工進度網(wǎng)絡(luò)計劃圖........................................173
7.5工期保證措施...............................................173
7.5.1組織保證措施..........................................173
7.5.2管理保證措施..........................................174
7.5.3資金保證措施..........................................174
755技術(shù)保證措施...........................................176
8、資源配置......................................................177
8.1勞動力配置計劃及保障.......................................177
8.2主要材料供應(yīng)計劃及保障.....................................178
8.2.1鋼筋供應(yīng)計劃..........................................178
8.3機械設(shè)備配置計劃及保障....................................179
8.4工程用款計劃及保障措施....................................180
9、質(zhì)量保證體系及措施............................................180
9.1質(zhì)量管理目標(biāo)...............................................180
9.2質(zhì)量管理體系...............................................180
9.3質(zhì)量管理制度..............................................181
9.3.1樣板先行制度..........................................181
932質(zhì)量檢查制度...........................................182
933質(zhì)量否決制度...........................................184
934材料進場檢驗制度.......................................185
935試驗把關(guān)制度...........................................185
936質(zhì)量文件記錄制度.......................................185
9.3.7工程質(zhì)量驗收制度......................................186
938成品保護制度...........................................186
939質(zhì)量事故處理辦法.......................................187
9310質(zhì)量優(yōu)劣獎罰制度......................................189
9.4過程控制措施...............................................189
9.4.1基坑降水施工質(zhì)量保證措施..............................189
9.4.2基坑開挖質(zhì)量保證措施..................................190
9.4.3鋼筋工程質(zhì)量保證措施..................................191
944支架、模板工程質(zhì)量保證措施.............................194
9.4.5結(jié)構(gòu)混凝土質(zhì)量保證措施................................195
9.4.6大體積校施工的特殊控制措施............................198
9.4.7結(jié)構(gòu)防水質(zhì)量保證措施..................................201
9.4.8隱蔽工程質(zhì)量保證措施..................................204
9.4.9與通道及區(qū)間接頭處施工質(zhì)量保證措施....................206
9.4.10基坑回填質(zhì)量保證措施................................207
9.5檢驗檢測控制...............................................207
9.5.1隱蔽工程檢查驗收......................................207
9.5.2材料檢驗檢測..........................................208
9.5.2.1主要檢測試驗項目及手段...........................208
9.5.2.2主要檢測試驗措施.................................209
10、安全管理體系及安全管理措施...................................212
10.1安全生產(chǎn)目標(biāo)及保證措施....................................212
10.1.1安全生產(chǎn)目標(biāo).........................................212
10.1.2安全管理機構(gòu)及安全監(jiān)控網(wǎng)絡(luò)...........................212
10.1.3安全保證體系.........................................215
1014安全生產(chǎn)責(zé)任制.......................................216
10.1.5安全基礎(chǔ)工作.........................................225
10.2安全防范重點與措施.......................................228
10.2.1安全防范重點.........................................228
10.2.2用電安全防范措施.....................................228
1023起重作業(yè)安全防范措施.................................229
10.2.4機械安全防范措施.....................................229
10.2.5深基坑開挖安全防范措施...............................230
10.2.6車站主體結(jié)構(gòu)施工安全保證措施.........................230
10.3安全應(yīng)急預(yù)案...............................................231
10.3.1深基坑施工突發(fā)事故應(yīng)急預(yù)案...........................231
1032突發(fā)事故防范..........................................234
11、文明施工、環(huán)境保護體系及措施.................................235
11.1文明施工管理體系及措施....................................235
11.1.1文明施工目標(biāo).........................................235
11.1.2文明施工管理體系.....................................235
11.1.3文明施工管理制度.....................................236
11.1.4文明施工措施.........................................236
11.2環(huán)境保護體系及措施.......................................240
11.2.1環(huán)境保護體系.........................................240
11.2.2主要環(huán)境影響的控制保護措施...........................241
12、消防、保衛(wèi)、健康體系及措施....................................246
12.1消防、保衛(wèi)、健康保證體系.................................246
12.2消防工作重點及措施.......................................247
12.3保衛(wèi)工作重點及措施.......................................248
13、雨季、節(jié)假日施工措施..........................................249
13.1雨期施工準(zhǔn)備...............................................249
13.2雨期施工技術(shù)措施..........................................249
13.2.1土方開挖.............................................249
13.2.2鋼筋工程.............................................250
13.2.3鋼管支撐架設(shè).........................................250
13.2.4硅工程......................................................................................................250
13.3雨季施工應(yīng)急預(yù)案..........................................251
13.4節(jié)假日施工措施...........................................252
14、施工接口界面處理與協(xié)調(diào)........................................252
14.1施工接口界面管理組織機構(gòu).................................252
14.2與業(yè)主的配合協(xié)調(diào)..........................................254
14.3與地方聯(lián)系與協(xié)調(diào)..........................................254
14.2.1按照相關(guān)部門的要求辦理各種手續(xù)和證件.................254
14.3.2積極與市政主管部門溝通和聯(lián)系.........................255
14.3.3搞好安全文明施工,確保場地周圍環(huán)境衛(wèi)生符合要求......255
14.3.4處理好與臨近市民的關(guān)系..............................255
14.4與監(jiān)理的配合與協(xié)調(diào)........................................256
14.4.1尊重監(jiān)理的工作.......................................256
14.4.2建立良好的溝通渠道,密切配合監(jiān)理工作................256
14.4.3給監(jiān)理創(chuàng)造一個良好的工作環(huán)境........................257
14.4.4服從監(jiān)理的指令.......................................257
14.4.5按時參加監(jiān)理召開的各種工程例會......................257
14.4.6按時上報各種報表及資料..............................257
14.5與設(shè)計單位的配合與協(xié)調(diào)....................................257
14.5.1認真審圖,領(lǐng)會設(shè)計意圖..............................258
14.5.2參加圖紙會審及設(shè)計交底,提出相關(guān)問題................258
14.5.3及時反饋施工信息,優(yōu)化設(shè)計方案......................258
14.6與相鄰工區(qū)經(jīng)理部接口單位的配合協(xié)調(diào)........................259
15、其他管理措施..................................................259
15.1合同管理..................................................259
15.2風(fēng)險管理.................................................259
15.3工程分包與分包管理措施...................................260
15.3.1對分包的管理要求.....................................260
15.3.2質(zhì)量方面的管理措施..................................261
15.3.3確保工程工期的管理措施...............................262
15.3.4安全保證措施.........................................262
15.3.5文明施工措施.........................................262
15.3.6健康管理.............................................263
15.3.7成品保護管理.........................................264
15.4成本控制措施.............................................265
附表及附圖:......................................................267
地質(zhì)縱剖面圖..................................................267
施工總平面圖..................................................267
交通疏解圖....................................................267
施工進度計劃橫道圖267
0站實施性施工組織設(shè)計
1、施工組織設(shè)計總說明
1.1編制依據(jù)及編制原則
1.1.1編制依據(jù)
1)、。地鐵。土建9標(biāo)0站土建工程相關(guān)設(shè)計資料、合同文
件、招標(biāo)文件及投標(biāo)文件;
2)、。地鐵00站初步設(shè)計圖;
3)、《0地鐵00站工程詳勘巖土工程勘察報告》;
4)、《中華人民共和國安全生產(chǎn)法》、《建筑基坑工程技術(shù)規(guī)
范》(YB9258-97)、《建筑基坑支護技術(shù)規(guī)程》(JGJ120-99)、《建設(shè)
工程安全生產(chǎn)管理條理》、《混凝土結(jié)構(gòu)工程施工質(zhì)量驗收規(guī)范》
(GB50204-2002),《危險性較大工程安全專項施工方案編制及專
家論證審查辦法》(建質(zhì)〔2004〕213號)、《危險性較大的分部分
項工程安全管理辦法》(建質(zhì)[2009]87號)、《地下鐵道工程施工及
驗收規(guī)范》(GB50299-1999,2003版)、《軌道交通工程技術(shù)規(guī)范》
(GB50490-2009)>《建筑結(jié)構(gòu)可靠度設(shè)計統(tǒng)一標(biāo)準(zhǔn)》(GB
50068-2001)>《地下鐵道工程施工及驗收規(guī)范》(GB50299-1999)
(2003年版);《地下防水工程質(zhì)量驗收規(guī)范》(GB50208-2011)>
《建筑工程質(zhì)量檢驗評定標(biāo)準(zhǔn)》(GB50210-2001)、《建筑施工場
界環(huán)境噪聲排放標(biāo)準(zhǔn)》(GB12523-2011)、《建筑施工場界噪聲測
量方法》(GBJ12524—2011)、《城市軌道交通工程測量規(guī)范》
(GB50308-2008)、《鋼筋焊接及驗收規(guī)程》(JGJ18-2012)>《鋼筋
機械連接通用技術(shù)規(guī)程》(JGJ107-2010)、《建筑施工安全檢查標(biāo)
準(zhǔn)》(JGJ59-2011).《混凝土質(zhì)量控制標(biāo)準(zhǔn)》(GB50164-2011)、《建
筑機械使用安全技術(shù)規(guī)程》(JGJ33-2012)、《施工現(xiàn)場臨時用電安
全技術(shù)規(guī)程》(JGJ46-2005)、?0地區(qū)基坑工程安全技術(shù)規(guī)范》
(DB51/T5072-2011)、《人防工程施工及驗收規(guī)范》
(GBJ134-2004),其他國家及四川省、0市有關(guān)規(guī)范、規(guī)程和規(guī)
定。
5)、我公司在地鐵施工方面的研究成果及現(xiàn)有的施工管理水
平、技術(shù)水平、機械設(shè)備配套能力以及資金投入能力;
6)、國家、地方及行業(yè)相關(guān)法規(guī)。
1.1.2編制原則
1)、在充分理解招標(biāo)文件與施工設(shè)計圖紙及認真踏勘現(xiàn)場的
基礎(chǔ)上采用安全、合理、可行、經(jīng)濟的施工方案。
2)、組織管理:采用先進的組織管理技術(shù),統(tǒng)籌計劃,合理安
排,組織分段、分工序平行流水作業(yè),施工進度安排均衡、高效,
保證業(yè)主要求的工期。
3)、機械設(shè)備:采用先進的機械設(shè)備,科學(xué)配置生產(chǎn)要素,
組建功能匹配、良性運作的施工程序,充分發(fā)揮機械設(shè)備的生產(chǎn)
能力。
4)、施工工藝:根據(jù)工程特點,采用先進的、成熟的施工工
藝,實行樣板引路、試驗先行、全過程監(jiān)控信息化施工。
5)、質(zhì)量控制:進一步推進全面質(zhì)量管理,嚴(yán)格按照IS09000
標(biāo)準(zhǔn)質(zhì)量體系進行質(zhì)量程序控制,對施工現(xiàn)場實施動態(tài)管理和嚴(yán)
密監(jiān)控,上道工序必須為下道工序服務(wù),質(zhì)量具有優(yōu)先否決權(quán)。
6)、安全控制:強化安全體系,細化安全措施,加大投入,
有針對性地狠抓各施工環(huán)節(jié)的安全落實,杜絕安全事故的發(fā)生。
7)、環(huán)境保護:采用先進、經(jīng)濟、合理、可行的施工措施,
貫穿施工全過程,對環(huán)境影響最小、占用場地最少,有效保護周
圍環(huán)境。
8)、嚴(yán)格貫徹“安全第一”的原則。加強施工管理,提高生
產(chǎn)效率,降低工程造價。
1.1.3編制范圍
本施工組織設(shè)計適用于0地鐵00站土建工程。主要包括內(nèi)
容:車站主體結(jié)構(gòu);A、B、C出入口;1、2號風(fēng)亭;降水工程。
L2工程概況
1.2.1工程位置和結(jié)構(gòu)形式
。站是。地鐵。的一個中間站,車站主體沿東、西方向布置
在。東街下方,為地下二層三跨12m島式車站,無換乘。車站
東西兩端均為盾構(gòu)區(qū)間。地面交通車流量一般,主要為附近小區(qū)
的車輛。A、C出入口位于0東街北側(cè);B號出入口位于0東街
南側(cè)。1號風(fēng)亭組設(shè)在車站西端,2號風(fēng)亭組及疏散出入口設(shè)在
車站東端,附屬結(jié)構(gòu)均外掛在車站主體之外。
車站全長206.600m,標(biāo)準(zhǔn)段寬21.1m,頂板覆土厚約3.5m,。
車站起始里程為YCK35+911.750,終點里程為YCK36+118.350,
車站有效站臺中心里程為YCK35+999.000,地面高程約508.700?
509.400mo
本站的主體結(jié)構(gòu)和附屬結(jié)構(gòu)均采用明挖順筑法施工,其中1
號風(fēng)亭組和A出入口施工期間局部采用鋼便橋。施工期間基坑外
管井降水。
車站基坑周邊的主要構(gòu)(建)筑物有:車站北側(cè)側(cè)墻距離銀
沙新居的兩棟7層住宅為7.97m,其中C出入口側(cè)墻距離銀沙新
居小區(qū)最近為3.00mo車站南側(cè)主要有鳳凰棲小區(qū)的1棟、2棟、
3棟住宅,距離車站附屬側(cè)墻最近處約2.14m。車站南側(cè)有一條
蓋板渠名茅草堰,該水渠上口寬約4.5米,下口寬約3.3米,深
度約1.6?2.0米,流向為東西流向,與車站平行。該水渠距離車
站盾構(gòu)擴大端側(cè)墻最近約0.43米。
122工程范圍和數(shù)量
1.2.2.1工程范圍
。站土建工程承包范圍:
工程范圍表表1」
工程名稱工程范圍
1、前期準(zhǔn)備工作、輔助設(shè)施及其
他;
2、主體結(jié)構(gòu)圍護工程;
0站土建范圍
3、主體結(jié)構(gòu)土石方工程;
4、車站主體結(jié)構(gòu)工程;
5、車站附屬結(jié)構(gòu)工程
122.2主要工程數(shù)量
主要工程數(shù)量表表1-2
項目材料單位數(shù)量備注
主體圍護樁鋼筋混凝土壇工方6655.4240根
主體土方挖填土方m398752.6
3
主體混凝土結(jié)構(gòu)鋼筋混凝土m17900.4
出入口圍護樁鋼筋混凝土m33055.9129根
出入口土方挖填土方m319710
3
出入口碎結(jié)構(gòu)鋼筋混凝土m2438.9
3
風(fēng)亭圍護樁鋼筋混凝土m3209.6182根
一3
風(fēng)亭土方挖填土方m17035.5
3
風(fēng)亭碎結(jié)構(gòu)鋼筋混凝土m2362.1
1.2.3工程地質(zhì)和水文地質(zhì)
1.2.3.1工程地質(zhì)
1)、地形地貌
本車站所在位置地形平坦,交通便利,地面高程變化為
508.750-509.043m,絕對高差為0.29mo地面交通車流量一般,
民房密集。
2)、巖土特性
根據(jù)本次鉆孔揭示,場地范圍內(nèi)上覆第四系人工填土層
ml
(Q4);下伏基巖為白堊系上統(tǒng)紫紅色泥巖(勘探中未揭示出該
巖土層)。按分層依據(jù),結(jié)合本站地質(zhì)斷面,劃分巖土層。巖土
層分層描述如下:
⑴第四系全新統(tǒng)人工填土(Q4ml)
<1-1>素填土:灰色、土黃色、雜色,稍濕,松散。成份以
混凝土、粉土、粉質(zhì)粘土為主。人工開挖3m,巖芯采取率100%。
人工開挖較易。局部缺失,為欠壓密土。層厚0.5?3m,場地內(nèi)
均有分布。
⑵第四系全新統(tǒng)沖積層(Q4al)
<2-3>粉質(zhì)粘土(Q4al):灰黃色,可塑。含鐵鎰質(zhì)礦物。層
厚約1.9?2.2m,埋深約0.5?0.8m。根據(jù)鉆孔巖芯揭示,該巖土層
在本站范圍內(nèi)廣泛分布,局部地方缺失。
<2-4>粉土(Q4al):灰黑、黑色,稍濕,松散。分選性較好,
粘粒含量約15%。層厚約1.5m?2.7左右,埋深約0.7?3m左右。
根據(jù)鉆孔巖芯揭示,該巖土層在里程YCK36+036m附近均有分
布。
<2-6-1>中砂(Q4al):青灰色、灰黑色,稍密,潮濕。黏
粒含量約15%o層厚約1.8m左右,埋深約3m左右。根據(jù)取樣顆
分試驗,粒徑>0.25mm的顆粒占50.7%。根據(jù)鉆孔巖芯揭示,該
巖土層呈透鏡體分布于本車站。
⑵第四系上更新統(tǒng)冰水沉積(Q3fgl+al)
中砂:青灰色,飽和,稍密。分選性好,質(zhì)純。根
據(jù)M7Z2-HZB-03鉆孔巖芯揭示,該巖土層厚約0.5?1.7m,呈透
鏡體狀分布于巖土層<3-8>中。
<3-8>卵石(Q3fgl+al):灰、灰黃色、灰白、青灰色,潮濕?
飽和,稍密?密實。石質(zhì)以灰?guī)r、花崗巖為、石英砂巖主。卵石
粒徑6~20cm,含量60?80%,磨圓度良好,呈亞圓狀?渾圓狀,
分選性較差。圓礫含量約10?15%。余為細砂、中砂充填。局部
含漂石。根據(jù)顆分顯示,該卵石的均勻性極差,不均勻系數(shù)Cu
為100?200,但石質(zhì)堅硬;根據(jù)點荷載試驗,其換算巖石單軸抗
壓強度R=80?90MPa。
根據(jù)重型動力觸成果和鉆探巖芯鑒定,按照《0地區(qū)建筑地
基基礎(chǔ)設(shè)計規(guī)范》(DB51/T5026-2001)表423-2,該層卵石分為稍
密卵石<3-8-1>、中密卵石<3-8-2>和密實卵石<3-8-3>,共3個亞
層。
3)不良地質(zhì)及特殊性巖土
車站內(nèi)無不良地質(zhì)作用,但地層中有可能含有害氣體,特殊
巖土為人工填土。
4)土層可挖性分級
根據(jù)《城市軌道交通巖土工程勘察規(guī)范》(GB50307-2012)附
錄F表F,本段土石可挖性分級如下:
I級松土:包括沖積的砂類土。即巖土層<2-6-1>、<3-5-1>
機械能全部直接鏟挖滿載。
n級普通土:包括素填土、粉土、粉質(zhì)黏土,即巖土層<i-i>、
<2-3>、<2-4>o機械需部分刨松方能鏟挖滿載,或可直接鏟挖但
不能滿載。
田級硬土:包括沖積、冰水沉積成因的稍密、中密卵石層。
巖土分層代號為<3-8-1>、<3-8-2>o機械須普遍刨松方能鏟挖滿
載。
W軟質(zhì)巖:主要為冰水沉積成因的密實卵石層。即巖土層
<3-8-3>o部分用爆破法開挖。
土層可挖性分級表表1-3
地層巖土開挖后的穩(wěn)定土石可
代成巖土特征
代號名稱狀態(tài)挖性分級
因
Q<1-1素填松散?稍密自穩(wěn)性差I(lǐng)I
Q<2-3粉質(zhì)軟塑?可塑不能自穩(wěn),易塌II
al
4<2-4粉土松散、潮濕不能自穩(wěn),易塌II
<2-6中砂稍密不能自穩(wěn),易塌I
<3-5中砂稍密不能自穩(wěn),易塌I
Q<3-8卵石稍密、飽和自穩(wěn)性差I(lǐng)II
fgl+al
4<3-8卵石中密、飽和自穩(wěn)性差I(lǐng)II
<3-8卵石密實、飽和自穩(wěn)性較差I(lǐng)V
1.232地震烈度
1)、地震參數(shù)
根據(jù)《中國地震動參數(shù)區(qū)劃圖》(GB18306-2001)和《中國
地震動參數(shù)區(qū)劃圖》(GB18306-2001)國家標(biāo)準(zhǔn)第1號修改單要
求,根據(jù)《中國地震動參數(shù)區(qū)劃圖》(GB18306-2001)和《中國
地震動參數(shù)區(qū)劃圖》(GB18306-2001)國家標(biāo)準(zhǔn)第1號修改單要
求,0市地鐵。工程通過地區(qū)設(shè)計地震分組為第三組,地震動峰
值加速度為0.10g,地震動反應(yīng)譜特征周期為0.45so0市抗震設(shè)
防烈度為7度。
據(jù)《建筑工程抗震設(shè)防分類標(biāo)準(zhǔn)》(GB50223-2008)中第302
條規(guī)定,本工程屬重點設(shè)防類。
2)、建筑當(dāng)?shù)仡悇e
綜合分析判定,本站場地類別為H類。
1.2.3.3水文地質(zhì)
1)、地表水
擬建車站范圍內(nèi)有一條梯形的排洪溝,排洪溝上寬5m,下
寬3.5m,深約2m,車站主體盾構(gòu)擴大端已侵入茅草堰水渠。對
工程有一定的影響。
擬建車站工程范圍內(nèi)地下水主要為松散土層孔隙水?;径?/p>
賦存于全新統(tǒng)(Q4)、上更新統(tǒng)(Q3)砂、卵石中,砂卵石層含
水極其豐富,形成一個整體含水層,為孔隙潛水。地下車站主體
結(jié)構(gòu)基本位于該層砂、卵石中,受地下水影響較大。根據(jù)本次鉆
探揭示,勘察期間測得地下水位為3.5?5m。
本車站巖土層素填土及粉土、粉質(zhì)粘土中,地下水含量甚微,
對工程影響較小。
2)、地下水
。市充沛的降雨量(多年平均降雨量947mm,年降雨日達140
天),構(gòu)成了地下水的主要補給源。同時,雨洪期河水及附近溝
渠也為其補給源。此外,區(qū)內(nèi)地下水還接受NW方向的側(cè)向徑流
補給。區(qū)內(nèi)地下水徑流方向為NW方向至SE方向。區(qū)內(nèi)地下水
排泄主要為大氣蒸發(fā)和向下游徑流。
3)、水、土的腐蝕性評價
根據(jù)《巖土工程勘察規(guī)范》(GB50021-2001)(2009年版),
按n類環(huán)境類型及A類地層滲透性判定,溝水對混凝土結(jié)構(gòu)及鋼
筋混凝土結(jié)構(gòu)中鋼筋均為微腐蝕。
根據(jù)《巖土工程勘察規(guī)范》(GB50021-2001)(2009年版),
按□類環(huán)境類型評價,場地粉土層對混凝土結(jié)構(gòu)的腐蝕性等級為
弱腐蝕;卵石土為微腐蝕。按A類地層滲透性判定,場地粉土層
和卵石土層對鋼筋混凝土結(jié)構(gòu)中鋼筋的腐蝕性為微腐蝕。
4)、抗浮水位確定
根據(jù)0地區(qū)水文地質(zhì)資料,結(jié)合。地區(qū)其它地鐵項目及建筑
施工經(jīng)驗,建議抗浮水位埋深采用3m,地下水位年變幅約為1?
3mo建議抗浮水位采用絕對高程506.39m。即地面下3.0m
124站址周圍環(huán)境
1.2.4.1地面交通及建筑物
車站位于0東街下方,二期(主體結(jié)構(gòu))施工時,保證北側(cè)
4.5m道路,以便和睦新天地和銀沙小區(qū)的車輛出行,南側(cè)鳳凰棲
小區(qū)車庫出口設(shè)置鋼便橋倒邊施工,確保小區(qū)車輛出行。三期圍
擋南側(cè)附屬施工時,A出入口設(shè)置鋼便橋,保證銀沙新居小區(qū)車
輛出行。
車站西端與銀沙街、金房苑橫街、0中橫街相連,東端與銀
沙北街、金房苑
溫馨提示
- 1. 本站所有資源如無特殊說明,都需要本地電腦安裝OFFICE2007和PDF閱讀器。圖紙軟件為CAD,CAXA,PROE,UG,SolidWorks等.壓縮文件請下載最新的WinRAR軟件解壓。
- 2. 本站的文檔不包含任何第三方提供的附件圖紙等,如果需要附件,請聯(lián)系上傳者。文件的所有權(quán)益歸上傳用戶所有。
- 3. 本站RAR壓縮包中若帶圖紙,網(wǎng)頁內(nèi)容里面會有圖紙預(yù)覽,若沒有圖紙預(yù)覽就沒有圖紙。
- 4. 未經(jīng)權(quán)益所有人同意不得將文件中的內(nèi)容挪作商業(yè)或盈利用途。
- 5. 人人文庫網(wǎng)僅提供信息存儲空間,僅對用戶上傳內(nèi)容的表現(xiàn)方式做保護處理,對用戶上傳分享的文檔內(nèi)容本身不做任何修改或編輯,并不能對任何下載內(nèi)容負責(zé)。
- 6. 下載文件中如有侵權(quán)或不適當(dāng)內(nèi)容,請與我們聯(lián)系,我們立即糾正。
- 7. 本站不保證下載資源的準(zhǔn)確性、安全性和完整性, 同時也不承擔(dān)用戶因使用這些下載資源對自己和他人造成任何形式的傷害或損失。
最新文檔
- 2025河南商丘梁園區(qū)招聘安全服務(wù)人員50人備考筆試題庫及答案解析
- 2025昆明市團結(jié)街道辦事處招聘公益性崗位人員(2人)參考考試題庫及答案解析
- 2025年12月深圳市公辦中小學(xué)面向2026年應(yīng)屆畢業(yè)生招聘教師888人參考考試題庫及答案解析
- 2025北京大學(xué)材料科學(xué)與工程學(xué)院招聘勞動合同制工作人員1人模擬筆試試題及答案解析
- 河北省行唐縣第三中學(xué)2026屆英語高三上期末考試模擬試題含解析
- 上海市十校2026屆生物高三第一學(xué)期期末質(zhì)量跟蹤監(jiān)視試題含解析
- 杠桿交易知識測試題及答案
- 2025年小熊汽車試講真題及答案
- 黑龍江齊齊哈爾市第八中學(xué)2026屆高二上生物期末綜合測試模擬試題含解析
- 64紅色卡通風(fēng)格的中小學(xué)315消費者權(quán)益主題班會模板
- 人工智能+跨學(xué)科人才培養(yǎng)模式創(chuàng)新分析報告
- 培訓(xùn)師演示直播帶貨操作流程
- 浙江寧波市江北區(qū)面向2025屆高校畢業(yè)生招聘高層次緊缺人才25人筆試備考題庫附答案詳解
- 產(chǎn)業(yè)生態(tài)構(gòu)建-洞察及研究
- 【《某地區(qū)綜合給水工程的取水工程設(shè)計計算案例》2200字】
- 立體邏輯架構(gòu)圖模板
- 2025年江蘇知識產(chǎn)權(quán)題庫及答案
- 職業(yè)教育專業(yè)布局體系清單
- 2025年水產(chǎn)養(yǎng)殖技術(shù)員資格考試試題及答案解析
- 2025年事業(yè)單位聯(lián)考A類《綜合應(yīng)用能力》真題(含答案)
- 意識形態(tài)工作培訓(xùn)課件
評論
0/150
提交評論