淤地壩除險(xiǎn)加固技術(shù)咨詢指南
Guidefortechnologyconsultingofremovingrisksand
strengtheningsiltDAMS
(征求意見稿)
20XX-XX-XX發(fā)布20XX-XX-XX實(shí)施
中國(guó)水利工程協(xié)會(huì)發(fā)布
T/CWEAXXX—20XX
目次
前言························································································II
引言·······················································································III
1范圍·························································································1
2規(guī)范性引用文件··········································································1
3術(shù)語(yǔ)·························································································1
4病險(xiǎn)評(píng)估···················································································1
4.1基本條件··············································································1
4.2評(píng)估要素··············································································2
4.3結(jié)論和建議···········································································2
5前期工作···················································································2
5.1初步設(shè)計(jì)準(zhǔn)備········································································2
5.2工程勘察與測(cè)量·····································································2
5.3信息化建設(shè)···········································································2
5.4除險(xiǎn)加固方案········································································3
6建設(shè)管理···················································································3
6.1工程設(shè)計(jì)··············································································3
6.2招標(biāo)采購(gòu)··············································································4
6.3工程監(jiān)理··············································································5
7驗(yàn)收·························································································9
7.1驗(yàn)收準(zhǔn)備··············································································9
7.2驗(yàn)收條件··············································································9
7.3驗(yàn)收成果··············································································9
8運(yùn)行維護(hù)··················································································10
8.1檢查···················································································10
8.2養(yǎng)護(hù)維修·············································································11
8.3安全監(jiān)測(cè)·············································································11
8.4項(xiàng)目后評(píng)價(jià)··········································································12
參考文獻(xiàn)·······················································································13
I
T/CWEAXXX—20XX
淤地壩除險(xiǎn)加固技術(shù)咨詢指南
1范圍
本文件規(guī)定了淤地壩除險(xiǎn)加固技術(shù)咨詢關(guān)于病險(xiǎn)評(píng)估、前期工作、建設(shè)管理、驗(yàn)
收、運(yùn)行管理等方面的內(nèi)容和要求。
本文件適用于病險(xiǎn)淤地壩除險(xiǎn)加固的技術(shù)咨詢工作。
2規(guī)范性引用文件
下列文件對(duì)于本文件的應(yīng)用是必不可少的。凡是注日期的引用文件,僅所注日期
的版本適用于本文件。凡是不注日期的引用文件,其最新版本(包括所有的修改單)
適用于本文件。
GB/T38357招標(biāo)代理服務(wù)規(guī)范
GB50500建設(shè)工程工程量清單計(jì)價(jià)規(guī)范
GB50501水利工程工程量清單計(jì)價(jià)規(guī)范
GB/T51212建筑信息模型應(yīng)用統(tǒng)一標(biāo)準(zhǔn)
GB/T51235建筑信息模型施工應(yīng)用標(biāo)準(zhǔn)
GB/T51301建筑信息模型設(shè)計(jì)交付標(biāo)準(zhǔn)
SL213水利對(duì)象分類與編碼總則
SL258水庫(kù)大壩安全評(píng)價(jià)導(dǎo)則
SL551土石壩安全監(jiān)測(cè)技術(shù)規(guī)范
SL/T619水利水電工程初步設(shè)計(jì)報(bào)告編制規(guī)程
SL725水利水電工程安全監(jiān)測(cè)設(shè)計(jì)規(guī)范
SL/T783水利數(shù)據(jù)交換規(guī)約
SL/T803水利網(wǎng)絡(luò)安全保護(hù)技術(shù)規(guī)范
SL/T804淤地壩技術(shù)規(guī)范
3術(shù)語(yǔ)
本文件沒(méi)有需要界定的術(shù)語(yǔ)和定義。
4病險(xiǎn)評(píng)估
4.1基本條件
4.1.1病險(xiǎn)淤地壩認(rèn)定應(yīng)由運(yùn)行管理部門編制病險(xiǎn)淤地壩認(rèn)定報(bào)告。認(rèn)定報(bào)告應(yīng)包括
基本情況、主要病險(xiǎn)問(wèn)題、安全影響評(píng)價(jià)、認(rèn)定結(jié)論等內(nèi)容。
4.1.2經(jīng)認(rèn)定的病險(xiǎn)淤地壩應(yīng)由運(yùn)行管理部門編制病險(xiǎn)淤地壩除險(xiǎn)加固設(shè)計(jì)報(bào)告,并
及時(shí)進(jìn)行除險(xiǎn)加固。
4.1.3已淤滿且缺少必需的排水設(shè)施,影響工程安全和壩地生產(chǎn)利用的大、中型淤地
壩可實(shí)施提升改造。
1
T/CWEAXXX—20XX
4.2評(píng)估要素
4.2.1符合下列條件之一的應(yīng)界定為病險(xiǎn)淤地壩:
a)下游影響范圍有村莊、學(xué)校、工礦、道路等基礎(chǔ)設(shè)施無(wú)配套泄洪建筑物的淤
地壩;
b)庫(kù)容100萬(wàn)立方米以上無(wú)溢洪道的大型淤地壩;
c)大型淤地壩控制區(qū)域外無(wú)溢洪道的中型淤地壩;
d)壩體、壩肩出現(xiàn)貫通性橫向裂縫或縱向滑動(dòng)性裂縫,壩坡發(fā)生破壞性滑坡、
塌陷、沖溝,壩體出現(xiàn)沖缺、管涌、流土的淤地壩;
e)放水建筑物或溢洪道出現(xiàn)損毀、斷裂、坍塌、基部掏刷懸空等破壞的淤地壩;
f)淤積面超過(guò)設(shè)計(jì)淤積高程,滯洪能力達(dá)不到原設(shè)計(jì)洪水標(biāo)準(zhǔn)的淤地壩;
g)其他影響淤地壩安全運(yùn)用的病險(xiǎn)情形。
4.2.2老舊淤地壩提升改造認(rèn)定工作,由淤地壩管理責(zé)任主體提出申請(qǐng),縣級(jí)水行政
主管部門負(fù)責(zé)認(rèn)定并出具書面意見,省級(jí)水行政主管部門組織核查。
4.3結(jié)論和建議
4.3.1淤地壩除險(xiǎn)加固措施應(yīng)包括下列內(nèi)容:
a)增設(shè)溢洪道;
b)壩體除險(xiǎn)加固;
c)放水建筑物除險(xiǎn)加固;
d)溢洪道除險(xiǎn)加固;
e)增設(shè)安全監(jiān)測(cè)設(shè)施。
4.3.2老舊淤地壩提升改造措施應(yīng)包括下列內(nèi)容:
a)布設(shè)排洪設(shè)施;
b)壩地鹽堿化防治;
c)壩體整修。
5前期工作
5.1初步設(shè)計(jì)準(zhǔn)備
5.1.1初步設(shè)計(jì)應(yīng)按照SL/T619的要求,宜達(dá)到施工圖深度。
5.1.2初步設(shè)計(jì)審查應(yīng)包括規(guī)劃(實(shí)施方案)依據(jù)、用地等條件是否落實(shí),審查前應(yīng)
組織現(xiàn)場(chǎng)查看。
5.2工程勘察與測(cè)量
5.2.1庫(kù)容大于等于50萬(wàn)m2的淤地壩除險(xiǎn)加固應(yīng)開展地質(zhì)勘察工作,庫(kù)容小于50
萬(wàn)m2的淤地壩宜根據(jù)需要開展地質(zhì)勘察工作。
5.2.2基礎(chǔ)圖件資料應(yīng)包括:工程地理位置圖,1:10000小流域地形圖及工程影響區(qū)
域交通、居民點(diǎn)、工礦、學(xué)校分布情況等。
5.2.3淤地壩除險(xiǎn)加固工程地質(zhì)勘察與地形測(cè)量應(yīng)滿足SL/T804的規(guī)定。
5.3信息化建設(shè)
5.3.1信息化建設(shè)應(yīng)貫穿項(xiàng)目全過(guò)程,可包括投資決策階段、設(shè)計(jì)階段、招標(biāo)采購(gòu)階
段、施工階段及運(yùn)行維護(hù)階段。
2
T/CWEAXXX—20XX
5.3.2信息化建設(shè)工作應(yīng)滿足GB/T51212、GB/T51235、GB/T51301、SL213、SL/T
783、SL/T803的相關(guān)規(guī)定。
5.3.3咨詢方應(yīng)以工程建模技術(shù)為核心,綜合利用先進(jìn)技術(shù),遵循水利信息化建設(shè)頂
層設(shè)計(jì),以需求和適用為基礎(chǔ),為委托方提供數(shù)字化、智慧化整體解決方案。
5.3.4信息化建設(shè)應(yīng)進(jìn)行充分調(diào)研和技術(shù)分析,形成數(shù)字化、智慧化建設(shè)咨詢文件,
宜包括總體方案和實(shí)施方案。
5.3.5信息化建設(shè)總體方案應(yīng)根據(jù)項(xiàng)目需求,結(jié)合信息技術(shù)發(fā)展趨勢(shì)和數(shù)字化實(shí)踐經(jīng)
驗(yàn)編制。信息化總體方案內(nèi)容應(yīng)包括:項(xiàng)目概況、項(xiàng)目信息化建設(shè)目標(biāo)、信息化建設(shè)
標(biāo)準(zhǔn)、信息化建設(shè)內(nèi)容、實(shí)施流程及進(jìn)度計(jì)劃等。
5.3.6信息化建設(shè)實(shí)施方案應(yīng)根據(jù)項(xiàng)目需求和信息化建設(shè)總體方案編制。信息化建設(shè)
實(shí)施方案內(nèi)容應(yīng)包括:項(xiàng)目概況、實(shí)施目標(biāo)、實(shí)施專業(yè)組建、實(shí)施軟硬件環(huán)境、實(shí)施
標(biāo)準(zhǔn)、實(shí)施方案及應(yīng)用價(jià)值點(diǎn)、實(shí)施保障措施等。
5.3.7宜采用BIM、GIS、物聯(lián)網(wǎng)、大數(shù)據(jù)、云計(jì)算、智能傳感技術(shù)、衛(wèi)星遙感、5G、
無(wú)人設(shè)備等現(xiàn)代信息技術(shù)增強(qiáng)信息化建設(shè)服務(wù)能力。
5.3.8針對(duì)不同需求,可提供數(shù)字孿生、工程造價(jià)、環(huán)保水保、征地移民、節(jié)能評(píng)估
等專項(xiàng)信息化建設(shè)。
5.3.9信息化建設(shè)應(yīng)滿足下列要求。
a)采用數(shù)字化、智能化技術(shù)時(shí),應(yīng)確保基礎(chǔ)數(shù)據(jù)等信息的真實(shí)性、準(zhǔn)確性、全
面性和安全性。
b)數(shù)據(jù)成果在項(xiàng)目全過(guò)程各階段間應(yīng)有效銜接,前一階段工作應(yīng)支持后續(xù)工作,
項(xiàng)目整體數(shù)字化管理數(shù)據(jù)成果應(yīng)完整、準(zhǔn)確、及時(shí)傳遞。
c)數(shù)字孿生項(xiàng)目設(shè)計(jì)應(yīng)結(jié)合工程類型、任務(wù)和規(guī)模,合理確定建設(shè)定位。
d)采用無(wú)人機(jī)技術(shù)應(yīng)根據(jù)環(huán)境、天氣等外部狀況及空域管理規(guī)定規(guī)劃飛行路線,
做好飛行記錄。
e)宜結(jié)合監(jiān)測(cè)技術(shù)、測(cè)繪技術(shù)、檢測(cè)技術(shù)、可視化技術(shù)等多種工程應(yīng)用技術(shù),
充分發(fā)揮數(shù)字化建設(shè)效用。
f)可根據(jù)實(shí)際需求利用先進(jìn)信息技術(shù),對(duì)工程信息化建設(shè)進(jìn)行擴(kuò)展和(或)升
級(jí)優(yōu)化。
5.4除險(xiǎn)加固方案
淤地壩除險(xiǎn)加固方案應(yīng)按照SL804的要求設(shè)計(jì)。
6建設(shè)管理
6.1施工準(zhǔn)備(土地預(yù)審、社會(huì)穩(wěn)定風(fēng)險(xiǎn)評(píng)估)
6.1工程設(shè)計(jì)
6.1.1工程設(shè)計(jì)服務(wù)可包括初步設(shè)計(jì)、招標(biāo)設(shè)計(jì)、施工圖設(shè)計(jì)、施工階段設(shè)計(jì)服務(wù)等。
6.1.2工程設(shè)計(jì)管理工作內(nèi)容應(yīng)包括:
a)有關(guān)設(shè)計(jì)審批、設(shè)計(jì)變更程序和設(shè)計(jì)資格管理;
b)技術(shù)質(zhì)量管理,包括審查審批意見落實(shí)、驗(yàn)收設(shè)計(jì)意見執(zhí)行、設(shè)計(jì)變更、施
工圖審查、設(shè)計(jì)交底、質(zhì)量缺陷與質(zhì)量事故處理等設(shè)計(jì)服務(wù)的技術(shù)質(zhì)量管理;
c)設(shè)計(jì)技術(shù)資料歸檔管理。
6.1.3設(shè)計(jì)階段設(shè)計(jì)服務(wù)應(yīng)符合下列要求:
3
T/CWEAXXX—20XX
a)初步設(shè)計(jì)應(yīng)依據(jù)批準(zhǔn)的可行性研究文件開展,其成果文件應(yīng)滿足政府部門或
項(xiàng)目業(yè)主組織的審查及設(shè)計(jì)概算編制和前期施工準(zhǔn)備需要;
b)招標(biāo)設(shè)計(jì)應(yīng)依據(jù)批準(zhǔn)的初步設(shè)計(jì)文件開展,其成果文件應(yīng)滿足施工招標(biāo)及編
制招標(biāo)工程量清單的要求;
c)施工圖設(shè)計(jì)應(yīng)依據(jù)批準(zhǔn)的初步設(shè)計(jì)文件開展,其成果文件應(yīng)滿足施工安裝、
材料設(shè)備訂貨、非標(biāo)設(shè)備制作、加工及編制施工圖預(yù)算的要求。
6.1.4施工階段設(shè)計(jì)服務(wù)內(nèi)容應(yīng)包括:設(shè)計(jì)交底、專項(xiàng)設(shè)計(jì)、深化設(shè)計(jì)、參與重要隱
蔽單元工程、分部工程驗(yàn)收和單位工程驗(yàn)收、施工過(guò)程技術(shù)核定及設(shè)計(jì)變更處理、協(xié)
助竣工圖紙編制、歸檔與移交等。
6.1.5施工階段設(shè)計(jì)服務(wù)提交成果應(yīng)包括:設(shè)計(jì)交底記錄、專項(xiàng)設(shè)計(jì)文件、深化設(shè)計(jì)
文件、質(zhì)量檢查報(bào)告、重要隱蔽單元工程驗(yàn)收、分部工程驗(yàn)收和單位工程驗(yàn)收簽字記
錄、施工過(guò)程技術(shù)核定及設(shè)計(jì)變更單等。
6.1.6工程設(shè)計(jì)服務(wù)流程應(yīng)符合下列要求:
a)編制設(shè)計(jì)工作大綱:根據(jù)不同設(shè)計(jì)階段以及項(xiàng)目概況、設(shè)計(jì)依據(jù),提出專業(yè)
團(tuán)隊(duì)方案、設(shè)計(jì)工作內(nèi)容及技術(shù)性要求、設(shè)計(jì)進(jìn)度要求等;
b)下達(dá)設(shè)計(jì)任務(wù):根據(jù)項(xiàng)目實(shí)施過(guò)程中不同階段的設(shè)計(jì)任務(wù),明確設(shè)計(jì)范圍、
劃分設(shè)計(jì)專業(yè)界面、提出勘測(cè)工作需求等;
c)提交工程設(shè)計(jì)成果:依據(jù)項(xiàng)目需求和相關(guān)規(guī)定,開展工程設(shè)計(jì)工作;同時(shí),
根據(jù)設(shè)計(jì)成果批復(fù)意見實(shí)施,保證各階段設(shè)計(jì)成果文件的完整性、準(zhǔn)確性和
符合性。
6.1.7工程設(shè)計(jì)服務(wù)還應(yīng)滿足下列要求:
a)專業(yè)交接:應(yīng)做好各專業(yè)接口質(zhì)量控制管理,實(shí)現(xiàn)各專業(yè)協(xié)同設(shè)計(jì)。咨詢方
應(yīng)對(duì)設(shè)計(jì)成果文件進(jìn)行技術(shù)性和符合性審核,成果應(yīng)滿足安全性、適用性和
耐久性要求;
b)主動(dòng)服務(wù):應(yīng)與項(xiàng)目業(yè)主、勘察單位、施工單位、監(jiān)理單位進(jìn)行工作對(duì)接,
對(duì)工程設(shè)計(jì)文件進(jìn)行解釋說(shuō)明。應(yīng)根據(jù)工程實(shí)際情況深化或合理調(diào)整設(shè)計(jì)方
案,參與和工程設(shè)計(jì)相關(guān)的驗(yàn)收工作。根據(jù)項(xiàng)目業(yè)主、項(xiàng)目主管部門對(duì)設(shè)計(jì)
成果文件的審查意見,落實(shí)完善設(shè)計(jì)成果文件并及時(shí)提交,保證設(shè)計(jì)成果文
件滿足項(xiàng)目報(bào)批或開工建設(shè)需要。
6.2招標(biāo)采購(gòu)
6.2.1招標(biāo)采購(gòu)服務(wù)應(yīng)符合GB/T38357的要求。
6.2.2招標(biāo)采購(gòu)階段的咨詢服務(wù)應(yīng)包括下列內(nèi)容:
a)招標(biāo)采購(gòu)策劃;
b)招標(biāo)采購(gòu)文件編制;
c)過(guò)程管理,如采購(gòu)信息發(fā)布、資格預(yù)審等文件審核、組織開標(biāo)評(píng)標(biāo)定標(biāo)工作、
協(xié)助合同簽訂工作;
d)合同條款策劃。
6.2.3工程招標(biāo)采購(gòu)咨詢服務(wù)主要成果應(yīng)包括下列內(nèi)容:
a)工程招標(biāo)采購(gòu)策劃階段:確定招標(biāo)采購(gòu)策略、選擇招標(biāo)采購(gòu)方式、完成招標(biāo)
采購(gòu)策劃并編制招標(biāo)采購(gòu)方案、配合相關(guān)政府部門辦理工程招標(biāo)采購(gòu)手續(xù);
b)工程招標(biāo)采購(gòu)文件編制階段:明確招標(biāo)采購(gòu)主要條件、招標(biāo)控制價(jià)、合同文
本;
c)工程招標(biāo)采購(gòu)組織階段:發(fā)布招標(biāo)(資格預(yù)審)公告、組織答疑和澄清、組
4
T/CWEAXXX—20XX
織現(xiàn)場(chǎng)踏勘、收取投標(biāo)保證金,組織開標(biāo)、評(píng)標(biāo)工作;
d)工程招標(biāo)采購(gòu)清標(biāo)階段:對(duì)需要清標(biāo)的項(xiàng)目編制清標(biāo)報(bào)告;
e)工程招標(biāo)采購(gòu)定標(biāo)階段:定標(biāo)和簽約。
6.2.4咨詢方應(yīng)按照管理要求,及時(shí)、準(zhǔn)確、完整地將工程招標(biāo)采購(gòu)過(guò)程中形成的咨
詢成果文件進(jìn)行收集、整理、編制、傳遞、移交。
6.2.5招標(biāo)文件中工程量清單及招標(biāo)控制價(jià)的編制或?qū)徍说膬?nèi)容、依據(jù)、格式等應(yīng)符
合現(xiàn)行GB50500、GB50501的相關(guān)規(guī)定及當(dāng)?shù)毓こ淘靸r(jià)管理機(jī)構(gòu)發(fā)布的相關(guān)計(jì)價(jià)依據(jù)、
標(biāo)準(zhǔn);項(xiàng)目的招標(biāo)采購(gòu)合同應(yīng)體現(xiàn)公平、公正和雙方意愿。
6.2.6咨詢方代理工程監(jiān)理、施工招標(biāo)時(shí),應(yīng)科學(xué)策劃工程監(jiān)理、施工招標(biāo)方案,遵
循公開、公平、公正和誠(chéng)信原則,協(xié)助項(xiàng)目業(yè)主優(yōu)選中標(biāo)單位。
6.2.7工程監(jiān)理招標(biāo)代理服務(wù)應(yīng)符合下列規(guī)定:
a)服務(wù)范圍、內(nèi)容、期限和深度、人員、工器具裝備等要求描述應(yīng)準(zhǔn)確;
b)報(bào)價(jià)要求設(shè)置應(yīng)合理;
c)投標(biāo)人資質(zhì)條件、業(yè)績(jī)、能力和信譽(yù)的要求應(yīng)合規(guī)。
6.2.8工程施工招標(biāo)代理服務(wù)應(yīng)符合下列要求:
a)協(xié)助項(xiàng)目業(yè)主合理設(shè)定施工合同邊界和劃分工程施工標(biāo)段,選擇工程施工招
標(biāo)方式;
b)合理設(shè)定工程施工招標(biāo)條件,并應(yīng)編制和發(fā)布招標(biāo)公告或發(fā)出投標(biāo)邀請(qǐng)書。
招標(biāo)采購(gòu)方式應(yīng)合規(guī),注意區(qū)分資格預(yù)審和后審;
c)按照合同要求和工程量清單計(jì)價(jià)標(biāo)準(zhǔn)要求編制或?qū)徍斯こ塘壳鍐?,并?yīng)合理
設(shè)定暫估價(jià)項(xiàng)目;
d)合理設(shè)定工程款支付條件,重點(diǎn)關(guān)注安全文明施工費(fèi)使用支付條款、獎(jiǎng)罰條
款、工程質(zhì)量保證條款等;
e)組織評(píng)標(biāo)委員會(huì)按照招標(biāo)文件中確定的評(píng)標(biāo)方法進(jìn)行工程施工評(píng)標(biāo);
f)協(xié)助項(xiàng)目業(yè)主與擬中標(biāo)施工單位進(jìn)行合同談判,并應(yīng)協(xié)助項(xiàng)目業(yè)主簽訂工程
施工合同。
6.2.9咨詢方代理材料設(shè)備采購(gòu)時(shí),應(yīng)采用直接采購(gòu)、詢價(jià)采購(gòu)或招標(biāo)采購(gòu)方式,采
購(gòu)品質(zhì)優(yōu)良、價(jià)格合理的材料設(shè)備,并應(yīng)保證所采購(gòu)的材料設(shè)備供應(yīng)滿足工程建設(shè)進(jìn)
度要求。
6.2.10材料設(shè)備采購(gòu)代理服務(wù)應(yīng)滿足下列要求:
a)區(qū)分純貨物、工程建設(shè)相關(guān)材料設(shè)備、是否需要帶施工資質(zhì)等類型;
b)技術(shù)性能、參數(shù)、型號(hào)、規(guī)格、數(shù)量、供貨時(shí)間要求等描述應(yīng)準(zhǔn)確;
c)對(duì)投標(biāo)人的生產(chǎn)安裝資格、能力要求應(yīng)合法、無(wú)歧義;
d)投標(biāo)人資質(zhì)條件、業(yè)績(jī)、能力和信譽(yù)的要求應(yīng)合規(guī);
e)招標(biāo)采購(gòu)方式應(yīng)合規(guī),宜采購(gòu)本國(guó)貨物,不應(yīng)歧視和排斥國(guó)貨;
f)制定材料設(shè)備進(jìn)場(chǎng)驗(yàn)收程序,寫入招標(biāo)文件和合同文件;
g)協(xié)助項(xiàng)目業(yè)主進(jìn)行合同談判,列明付款條件、交貨驗(yàn)收要求、交接保存責(zé)任
等主要條款;
h)協(xié)助項(xiàng)目業(yè)主簽訂材料設(shè)備供貨合同,可協(xié)助監(jiān)督管理材料設(shè)備供貨合同履
行。
6.3工程監(jiān)理
6.3.1投資控制
6.3.1.1工程咨詢服務(wù)機(jī)構(gòu)應(yīng)依據(jù)項(xiàng)目合同及其他相關(guān)文件,在滿足工程質(zhì)量和進(jìn)度
5
T/CWEAXXX—20XX
要求的前提下,使工程實(shí)際造價(jià)不超過(guò)預(yù)定投資目標(biāo)。
6.3.1.2設(shè)計(jì)階段投資管理工作內(nèi)容可包括:
a)協(xié)助審查項(xiàng)目設(shè)計(jì)概算;
b)協(xié)助審查施工圖預(yù)算。
6.3.1.3建設(shè)階段投資管理工作內(nèi)容可包括:
a)協(xié)助審定招標(biāo)采購(gòu)文件,確定招標(biāo)采購(gòu)范圍、技術(shù)要求、商務(wù)要求;
b)根據(jù)項(xiàng)目總體需要,統(tǒng)籌協(xié)調(diào)質(zhì)量、進(jìn)度、成本、風(fēng)險(xiǎn)等多方面因素,協(xié)助
審定招標(biāo)控制價(jià);
c)根據(jù)施工合同約定及項(xiàng)目實(shí)施計(jì)劃,協(xié)助編制項(xiàng)目資金使用計(jì)劃,并根據(jù)項(xiàng)
目實(shí)施情況適時(shí)進(jìn)行調(diào)整;
d)進(jìn)行工程造價(jià)的動(dòng)態(tài)管理,協(xié)助編制和審查工程投資動(dòng)態(tài)管理報(bào)告;
e)協(xié)助審查工程支付款的相關(guān)文件;
f)協(xié)助處理工程變更、工程索賠和工程簽證;
g)協(xié)助審查概算調(diào)整;
h)協(xié)調(diào)施工單位編制完工結(jié)算報(bào)告,配合竣工決算審計(jì)工作。
6.3.1.4工程咨詢服務(wù)機(jī)構(gòu)可借助信息技術(shù)進(jìn)行建設(shè)項(xiàng)目投資管理。
6.3.2進(jìn)度控制
6.3.2.1工程咨詢服務(wù)機(jī)構(gòu)應(yīng)建立項(xiàng)目進(jìn)度管理制度,制訂進(jìn)度管理目標(biāo)。
6.3.2.2項(xiàng)目進(jìn)度管理目標(biāo)應(yīng)按項(xiàng)目實(shí)施過(guò)程、專業(yè)、階段或?qū)嵤┲芷谶M(jìn)行分解。
6.3.2.3進(jìn)度管理工作程序應(yīng)包括進(jìn)度計(jì)劃編制、控制、檢查與變更調(diào)整等。
6.3.2.4進(jìn)度管理應(yīng)包括下列內(nèi)容:
a)編制項(xiàng)目總進(jìn)度計(jì)劃,并上報(bào)項(xiàng)目業(yè)主審定;
b)按照經(jīng)審定的項(xiàng)目總進(jìn)度計(jì)劃及合同確定的總工期,審核各階段、各參建單
位的總進(jìn)度計(jì)劃、階段性進(jìn)度計(jì)劃,協(xié)助檢查項(xiàng)目計(jì)劃執(zhí)行情況;
c)編制年、季、月工程進(jìn)度計(jì)劃報(bào)告并按期上報(bào)項(xiàng)目業(yè)主;
d)協(xié)調(diào)解決影響工程進(jìn)度控制的關(guān)鍵問(wèn)題;
e)對(duì)施工單位提交的工程延期申請(qǐng)進(jìn)行審查和評(píng)估;
f)對(duì)項(xiàng)目進(jìn)度進(jìn)行動(dòng)態(tài)跟蹤分析,出現(xiàn)偏差時(shí)提出糾正或調(diào)整措施,組織編制
調(diào)整后的施工進(jìn)度計(jì)劃;
g)協(xié)助開展工程停復(fù)工、工期變更等工作。
6.3.2.5進(jìn)度控制主要應(yīng)注意下列事項(xiàng):
a)針對(duì)項(xiàng)目進(jìn)度偏差,及時(shí)找明原因,提出解決方案;
b)根據(jù)項(xiàng)目總進(jìn)度計(jì)劃合理確定各設(shè)計(jì)階段的設(shè)計(jì)周期。跟進(jìn)設(shè)計(jì)進(jìn)度,確保
設(shè)計(jì)進(jìn)度滿足報(bào)批報(bào)建、招標(biāo)、采購(gòu)和施工等要求;
c)保證階段性施工進(jìn)度計(jì)劃與總進(jìn)度計(jì)劃目標(biāo)一致;
d)以關(guān)鍵線路上的各項(xiàng)任務(wù)和主要影響因素作為項(xiàng)目進(jìn)度控制的重點(diǎn);
e)加強(qiáng)對(duì)項(xiàng)目進(jìn)度有影響的相關(guān)方活動(dòng)的跟蹤與協(xié)調(diào)。
6.3.2.6進(jìn)度計(jì)劃的變更調(diào)整應(yīng)符合下列規(guī)定:
a)調(diào)整相關(guān)資源供應(yīng)計(jì)劃,并與相關(guān)方進(jìn)行溝通;
b)進(jìn)度計(jì)劃調(diào)整應(yīng)符合項(xiàng)目管理制度規(guī)定及相關(guān)合同要求。
6.3.3質(zhì)量控制
6.3.3.1質(zhì)量管理工作應(yīng)貫穿建設(shè)項(xiàng)目全過(guò)程,內(nèi)容應(yīng)包括勘察質(zhì)量管理、設(shè)計(jì)質(zhì)量
管理、施工質(zhì)量管理等方面。
6.3.3.2工程咨詢服務(wù)機(jī)構(gòu)應(yīng)根據(jù)項(xiàng)目管理需求,組織建立整個(gè)項(xiàng)目的質(zhì)量管理體
6
T/CWEAXXX—20XX
系,設(shè)立質(zhì)量管理部門,配備質(zhì)量管理人員,簽訂質(zhì)量目標(biāo)責(zé)任書,建立質(zhì)量管理和
考核制度。
6.3.3.3質(zhì)量管理工作應(yīng)堅(jiān)持缺陷預(yù)防的原則,主要內(nèi)容應(yīng)包括結(jié)合項(xiàng)目特點(diǎn)開展質(zhì)
量策劃、進(jìn)行質(zhì)量控制、實(shí)施質(zhì)量改進(jìn)、實(shí)現(xiàn)項(xiàng)目質(zhì)量目標(biāo)。
6.3.3.4質(zhì)量控制應(yīng)包括對(duì)勘察質(zhì)量、設(shè)計(jì)質(zhì)量、施工質(zhì)量的控制,具體應(yīng)包括下列
內(nèi)容:
a)審查參建單位資質(zhì),組織或參與評(píng)審各專項(xiàng)成果報(bào)告,并提出評(píng)估、優(yōu)化、
深化意見;
b)檢查勘察、設(shè)計(jì)、施工、監(jiān)理、檢測(cè)等單位質(zhì)量管理體系建立情況;
c)協(xié)助項(xiàng)目業(yè)主組織勘察、設(shè)計(jì)、施工、監(jiān)理等工程建設(shè)相關(guān)方進(jìn)行設(shè)計(jì)交底
和圖紙會(huì)審;
d)按照勘察、設(shè)計(jì)、施工實(shí)施過(guò)程的先后次序,做好事前質(zhì)量控制、事中質(zhì)量
控制和事后質(zhì)量控制;
e)協(xié)助項(xiàng)目業(yè)主進(jìn)行施工質(zhì)量檢查和項(xiàng)目法人委托檢測(cè);
f)參與重大技術(shù)方案評(píng)審;
g)參與質(zhì)量缺陷和質(zhì)量事故處理,提出合理化建議和意見;
h)工程完工后及時(shí)協(xié)助項(xiàng)目業(yè)主組織工程質(zhì)量驗(yàn)收;
i)督促參建單位對(duì)質(zhì)量監(jiān)督、質(zhì)量檢查、質(zhì)量巡查和稽查等發(fā)現(xiàn)的質(zhì)量問(wèn)題進(jìn)
行整改。
6.3.3.5質(zhì)量改進(jìn)應(yīng)包括對(duì)事先設(shè)置的勘察、設(shè)計(jì)、施工質(zhì)量控制點(diǎn)進(jìn)行檢查與監(jiān)測(cè),
對(duì)質(zhì)量不符合要求的情況應(yīng)進(jìn)行持續(xù)跟蹤,組織分析原因,研究提出包括方案、工序
和工藝等在內(nèi)的改進(jìn)措施,督促相應(yīng)責(zé)任單位予以落實(shí),確保最終質(zhì)量滿足合同要求。
6.3.3.6工程咨詢項(xiàng)目負(fù)責(zé)人可以根據(jù)合同約定及項(xiàng)目質(zhì)量目標(biāo),組織制訂項(xiàng)目創(chuàng)優(yōu)
計(jì)劃并實(shí)施。
6.3.4合同管理
6.3.4.1工程咨詢服務(wù)機(jī)構(gòu)應(yīng)協(xié)助項(xiàng)目業(yè)主按程序和規(guī)定訂立合同,并在規(guī)定期限內(nèi)
辦理備案手續(xù)。
6.3.4.2工程咨詢服務(wù)機(jī)構(gòu)應(yīng)建立健全合同管理體系,內(nèi)設(shè)部門或安排人員負(fù)責(zé)合同
管理工作。合同管理工作應(yīng)貫徹全面履約的原則。
6.3.4.3合同管理程序應(yīng)包括合同評(píng)審、合同訂立、合同實(shí)施計(jì)劃、合同實(shí)施控制、
合同管理總結(jié)。
6.3.4.4合同評(píng)審工作的內(nèi)容應(yīng)包括對(duì)合同條件的審查、認(rèn)定和評(píng)估;以招標(biāo)方式訂
立合同,應(yīng)對(duì)招標(biāo)文件和投標(biāo)文件進(jìn)行審查、認(rèn)定和評(píng)估。
6.3.4.5合同實(shí)施計(jì)劃應(yīng)包括合同實(shí)施總體安排、分包策劃及合同實(shí)施保證體系建立
等內(nèi)容。
6.3.4.6合同實(shí)施控制應(yīng)包括合同交底、合同跟蹤與分析、合同變更管理和合同索賠
管理。合同實(shí)施控制應(yīng)符合下列規(guī)定:
a)合同實(shí)施前,合同管理責(zé)任人應(yīng)進(jìn)行合同交底。合同交底應(yīng)包括合同主要內(nèi)
容、合同實(shí)施主要風(fēng)險(xiǎn)、合同簽訂過(guò)程中的特殊問(wèn)題、合同實(shí)施計(jì)劃和合同
實(shí)施責(zé)任分配等;
b)合同跟蹤與分析應(yīng)通過(guò)明確合同目標(biāo),進(jìn)行合同結(jié)構(gòu)分解,將合同落實(shí)到合
同實(shí)施的具體問(wèn)題和具體事件中,指導(dǎo)項(xiàng)目具體工作;
c)合同變更管理應(yīng)包括變更協(xié)商、變更處理程序和結(jié)果檢查等;
d)合同索賠管理工作任務(wù)應(yīng)包括索賠和反索賠。合同索賠管理應(yīng)重點(diǎn)做好事前
7
T/CWEAXXX—20XX
控制、事中管理和事后總結(jié);
e)在合同執(zhí)行過(guò)程中,協(xié)助項(xiàng)目業(yè)主進(jìn)行合同的爭(zhēng)議解決、中止和解除等工作,
提供解決方案及措施,并按項(xiàng)目業(yè)主最終批準(zhǔn)的解決方案具體執(zhí)行。
6.3.4.7工程咨詢服務(wù)機(jī)構(gòu)應(yīng)做好各類合同管理工作,包括項(xiàng)目業(yè)主與項(xiàng)目參建單位
簽訂的合同;協(xié)助項(xiàng)目業(yè)主負(fù)責(zé)勘察、設(shè)計(jì)、施工、招標(biāo)代理、造價(jià)、監(jiān)理、采購(gòu)(材
料、設(shè)備供應(yīng)商)等合同協(xié)調(diào)管理工作。
6.3.5信息管理
6.3.5.1工程咨詢服務(wù)機(jī)構(gòu)應(yīng)建立信息管理體系,及時(shí)、準(zhǔn)確、全面地獲得和使用項(xiàng)
目所需的信息。宜利用先進(jìn)技術(shù)實(shí)現(xiàn)信息管理的高效性和協(xié)同性。
6.3.5.2淤地壩基本信息應(yīng)包括淤地壩代碼、名稱、所在位置、所在流域、地理坐標(biāo)、
工程類型、樞紐組成、圖片、視頻、建設(shè)信息、下游影響范圍等。
6.3.5.3淤地壩信息入庫(kù)數(shù)據(jù)應(yīng)與其所屬的流域、支流、小流域以及行政區(qū)域、特定
區(qū)域等空間尺度相對(duì)應(yīng)。
6.3.5.4淤地壩信息入庫(kù)數(shù)據(jù)更新頻次應(yīng)符合下列規(guī)定:
a)大中型淤地壩每年一次;
b)小型淤地壩每五年一次;
c)數(shù)據(jù)更新應(yīng)于五月底前完成。
6.3.5.5淤地壩簡(jiǎn)介應(yīng)包括下列內(nèi)容:
a)修建時(shí)間;
b)除險(xiǎn)加固時(shí)間;
c)樞紐組成部分。
6.3.5.6工程咨詢服務(wù)機(jī)構(gòu)應(yīng)實(shí)施全過(guò)程信息安全管理,建立完善的信息安全責(zé)任制
度,實(shí)施信息安全控制程序,并確保信息安全管理的持續(xù)改進(jìn)。
6.3.5.7工程咨詢服務(wù)機(jī)構(gòu)的檔案管理工作應(yīng)包括:
a)組織編制工程咨詢業(yè)務(wù)服務(wù)過(guò)程中所借閱和使用的各類設(shè)計(jì)文件、施工合同
文件、竣工資料等可追溯性資料的文件目錄,該目錄由全過(guò)程工程咨詢項(xiàng)目
負(fù)責(zé)人審核后歸檔;
b)歸檔工程咨詢成果文件、過(guò)程文件和其他文件;
c)協(xié)助組織檢查參建單位檔案整理和移交工作,協(xié)助落實(shí)工程信息化管理平臺(tái)
填報(bào)工作,配合完成檔案驗(yàn)收。
6.3.6溝通協(xié)調(diào)
6.3.6.1工程咨詢服務(wù)機(jī)構(gòu)的溝通管理工作應(yīng)包括對(duì)項(xiàng)目?jī)?nèi)外關(guān)系的協(xié)調(diào)及信息交
流開展策劃、組織和控制等活動(dòng),具體內(nèi)容包括協(xié)助項(xiàng)目業(yè)主的溝通協(xié)調(diào)管理、服務(wù)
機(jī)構(gòu)內(nèi)部的溝通協(xié)調(diào)管理,及與參建方的溝通協(xié)調(diào)管理。
6.3.6.2溝通協(xié)調(diào)管理可采用會(huì)議、電話、郵件、書面記錄及通訊信息平臺(tái)等媒介形
式傳遞和反饋信息。
6.3.6.3應(yīng)建立項(xiàng)目溝通協(xié)調(diào)管理制度體系,推進(jìn)溝通協(xié)調(diào)管理工作有序開展。溝通
協(xié)調(diào)管理主要流程應(yīng)如下:
a)明確溝通事項(xiàng);
b)對(duì)所需溝通事項(xiàng)進(jìn)行調(diào)查研究及登記;
c)溝通雙(多)方采用相關(guān)信息平臺(tái)進(jìn)行溝通,并留存過(guò)程記錄;
d)對(duì)溝通結(jié)果形成各方確認(rèn)可追溯的書面記錄,及時(shí)向事務(wù)相關(guān)方反饋結(jié)果。
8
T/CWEAXXX—20XX
7驗(yàn)收
7.1驗(yàn)收準(zhǔn)備
7.1.1淤地壩工程驗(yàn)收可分為分部工程驗(yàn)收、單位工程驗(yàn)收和工程竣工驗(yàn)收。
7.1.2申請(qǐng)竣工驗(yàn)收時(shí)應(yīng)提交驗(yàn)收申請(qǐng)報(bào)告、監(jiān)理報(bào)告、施工報(bào)告、質(zhì)量監(jiān)督報(bào)告、
財(cái)務(wù)決算報(bào)告及合同等。
7.2驗(yàn)收條件
7.2.1分部工程驗(yàn)收應(yīng)由項(xiàng)目法人(或委托監(jiān)理單位)主持,并應(yīng)具備下列條件:
a)所有單元工程已完成;
b)已完單元工程施工質(zhì)量經(jīng)評(píng)定全部合格,有關(guān)質(zhì)量缺陷已處理完畢或有監(jiān)理
機(jī)構(gòu)批準(zhǔn)的處理意見;
c)合同約定的其他條件。
7.2.2單位工程驗(yàn)收應(yīng)由項(xiàng)目法人主持,并應(yīng)具備下列條件:
a)所有分部工程已完建并驗(yàn)收合格;
b)分部工程驗(yàn)收遺留問(wèn)題已處理完畢并通過(guò)驗(yàn)收,未處理的遺留問(wèn)題不影響單
位工程質(zhì)量評(píng)定并有處理意見;
c)合同約定的其他條件。
7.2.3竣工驗(yàn)收宜在經(jīng)過(guò)汛期試運(yùn)行后進(jìn)行,并應(yīng)具備下列條件:
a)工程已按批準(zhǔn)設(shè)計(jì)全部完成;
b)工程重大設(shè)計(jì)變更已經(jīng)由具有審批權(quán)的單位批準(zhǔn);
c)歷次驗(yàn)收所發(fā)現(xiàn)的問(wèn)題已基本處理完畢;
d)工程投資已全部到位;
e)竣工財(cái)務(wù)決算已通過(guò)竣工審計(jì),審計(jì)意見中提出的問(wèn)題已整改并提交了整改
報(bào)告;
f)質(zhì)量監(jiān)督部門的工程質(zhì)量評(píng)價(jià)報(bào)告已提交,工程質(zhì)量達(dá)到合格標(biāo)準(zhǔn);
g)運(yùn)行管理單位已明確,工程運(yùn)行管護(hù)合同已簽訂,管護(hù)責(zé)任已落實(shí);
h)竣工驗(yàn)收資料已準(zhǔn)備就緒。
7.3驗(yàn)收成果
7.3.1分部工程驗(yàn)收應(yīng)包括下列主要內(nèi)容:
a)檢查工程是否達(dá)到設(shè)計(jì)標(biāo)準(zhǔn)或合同約定標(biāo)準(zhǔn)的要求;
b)評(píng)定工程施工質(zhì)量等級(jí);
c)對(duì)驗(yàn)收中發(fā)現(xiàn)的問(wèn)題提出處理意見。
7.3.2單位工程驗(yàn)收應(yīng)包括下列主要內(nèi)容:
a)檢查工程是否按批準(zhǔn)的設(shè)計(jì)內(nèi)容完成;
b)評(píng)定工程施工質(zhì)量等級(jí);
c)檢查分部工程驗(yàn)收遺留問(wèn)題處理情況及相關(guān)記錄;
d)對(duì)驗(yàn)收中發(fā)現(xiàn)的問(wèn)題提出處理意見。
7.3.3竣工驗(yàn)收應(yīng)包括下列主要內(nèi)容:
a)工程建設(shè)任務(wù)和投資計(jì)劃完成情況;
b)工程建設(shè)質(zhì)量情況;
c)資金到位和使用情況;
d)運(yùn)行管理責(zé)任主體及防汛責(zé)任落實(shí)情況;
9
T/CWEAXXX—20XX
e)檔案資料情況。
7.3.4存在下列情況之一者不應(yīng)通過(guò)竣工驗(yàn)收:
a)未經(jīng)批準(zhǔn)擅自變更設(shè)計(jì)和壩址;
b)建筑物尺寸和工程質(zhì)量未達(dá)到設(shè)計(jì)要求;
c)歷次驗(yàn)收提出的問(wèn)題未經(jīng)處理;
d)未落實(shí)管護(hù)責(zé)任主體。
7.3.5工程通過(guò)竣工驗(yàn)收后,項(xiàng)目法人應(yīng)及時(shí)與運(yùn)行管理責(zé)任主體辦理移交手續(xù)。
8運(yùn)行維護(hù)
8.1檢查
8.1.1縣級(jí)水行政主管部門應(yīng)按照SL/T804的規(guī)定,劃定轄區(qū)內(nèi)淤地壩工程管理范
圍。
8.1.2淤地壩檢查項(xiàng)目包括壩體檢查、放水建筑物檢查、泄洪建筑物檢查和其他檢查。
8.1.3壩體檢查的內(nèi)容包括:
a)壩頂有無(wú)裂縫、洞穴、異常變形、坑洼、積水等現(xiàn)象;
b)壩坡有無(wú)裂縫、滑坡、洞穴、塌坑、沖溝、喬木,襯砌工程是否損壞;背水
坡有無(wú)渾濁滲水、管涌等現(xiàn)象;排水體是否完整;
c)馬道是否平整;
d)壩體與放水(泄洪)建筑物結(jié)合部是否存在裂縫、沉陷、滲水等現(xiàn)象;
e)壩體與岸坡連接處有無(wú)錯(cuò)動(dòng)、開裂、滲水等現(xiàn)象,兩岸壩端區(qū)有無(wú)裂縫、滑
坡、崩塌、溶蝕、隆起、塌坑、異常滲水等現(xiàn)象;
f)植物綠化等水土保持措施是否完好;
g)是否存在動(dòng)物洞、穴。
8.1.4放水建筑物檢查的內(nèi)容包括:
a)臥管(豎井)的通氣孔是否堵塞,孔塞(擋水板)有無(wú)丟失、損壞,臥管及
臥管消力池有無(wú)裂縫、滲漏、傾斜、堵塞、淘刷、懸空等現(xiàn)象;
b)涵洞(管)身有無(wú)裂縫、坍塌、滲水、堵塞等現(xiàn)象;
c)明渠及明渠消力池有無(wú)裂縫、滲漏、懸空、堵塞等現(xiàn)象。
8.1.5泄洪建筑物檢查的內(nèi)容包括:
a)引水渠和漸變段有無(wú)淤堵,基礎(chǔ)有無(wú)淘刷、懸空,側(cè)墻有無(wú)沉陷、裂縫、缺
損等現(xiàn)象,伸縮縫是否完好;
b)溢流堰有無(wú)裂縫、滲漏、剝落、淤堵、淘刷、懸空等現(xiàn)象,伸縮縫是否完好;
c)泄槽有無(wú)裂縫、滲漏、淘刷、懸空等現(xiàn)象;排水孔及伸縮縫是否完好;
d)泄洪洞洞身有無(wú)裂縫、滲漏、坍塌、剝落等現(xiàn)象;
e)消能設(shè)施有無(wú)裂縫、滲漏、淘刷、懸空等現(xiàn)象;
8.1.6其他檢查的內(nèi)容包括:
a)排(截)水溝是否通暢或損壞;
b)邊坡、近壩岸坡有無(wú)沖刷、裂縫、坍塌、滑坡等現(xiàn)象;
c)管理道路、工作橋是否通暢和滿足管理需要;
d)水雨情及工程安全監(jiān)測(cè)、監(jiān)控設(shè)施設(shè)備,通信、傳輸、供電設(shè)備工作是否正
常;
e)管理房是否安全、整潔;
f)公示牌、標(biāo)志碑是否完好,信息要素是否準(zhǔn)確、清晰及完整,警示標(biāo)志是否
10
T/CWEAXXX—20XX
醒目;
g)庫(kù)區(qū)是否存在垃圾等廢棄物。
8.2養(yǎng)護(hù)維修
8.2.1淤地壩養(yǎng)護(hù)應(yīng)做到對(duì)淤地壩進(jìn)行經(jīng)常保養(yǎng)和防護(hù),及時(shí)消除表面缺陷和局部工
程問(wèn)題,保證工程的完整、安全和正常運(yùn)用。
8.2.2養(yǎng)護(hù)按部位的不同,分為壩體養(yǎng)護(hù)、放水(泄洪)建筑物養(yǎng)護(hù)和其他養(yǎng)護(hù)。
8.2.3壩體養(yǎng)護(hù)應(yīng)包括下列內(nèi)容:
a)壩頂應(yīng)整潔、平整、無(wú)明顯起伏;
b)壩坡應(yīng)平順;
c)砌石護(hù)坡應(yīng)完好,砌縫緊密,填料密實(shí),排水體應(yīng)完好;
d)植物護(hù)坡應(yīng)完整;
e)馬道應(yīng)平整;
f)壩體應(yīng)無(wú)動(dòng)物洞、穴等。
8.2.4放水(泄洪)建筑物養(yǎng)護(hù)應(yīng)包括下列內(nèi)容:
a)臥管(或豎井)放水孔的孔塞(擋水板)應(yīng)齊全、完整;
b)臥管通氣孔應(yīng)通氣順暢并宜設(shè)置安全防護(hù)措施;
c)臥管、明渠及明渠消力池應(yīng)保持暢通;
d)泄洪建筑物應(yīng)外觀完好;
e)伸縮縫應(yīng)保持完好;
f)混凝土和
溫馨提示
- 1. 本站所有資源如無(wú)特殊說(shuō)明,都需要本地電腦安裝OFFICE2007和PDF閱讀器。圖紙軟件為CAD,CAXA,PROE,UG,SolidWorks等.壓縮文件請(qǐng)下載最新的WinRAR軟件解壓。
- 2. 本站的文檔不包含任何第三方提供的附件圖紙等,如果需要附件,請(qǐng)聯(lián)系上傳者。文件的所有權(quán)益歸上傳用戶所有。
- 3. 本站RAR壓縮包中若帶圖紙,網(wǎng)頁(yè)內(nèi)容里面會(huì)有圖紙預(yù)覽,若沒(méi)有圖紙預(yù)覽就沒(méi)有圖紙。
- 4. 未經(jīng)權(quán)益所有人同意不得將文件中的內(nèi)容挪作商業(yè)或盈利用途。
- 5. 人人文庫(kù)網(wǎng)僅提供信息存儲(chǔ)空間,僅對(duì)用戶上傳內(nèi)容的表現(xiàn)方式做保護(hù)處理,對(duì)用戶上傳分享的文檔內(nèi)容本身不做任何修改或編輯,并不能對(duì)任何下載內(nèi)容負(fù)責(zé)。
- 6. 下載文件中如有侵權(quán)或不適當(dāng)內(nèi)容,請(qǐng)與我們聯(lián)系,我們立即糾正。
- 7. 本站不保證下載資源的準(zhǔn)確性、安全性和完整性, 同時(shí)也不承擔(dān)用戶因使用這些下載資源對(duì)自己和他人造成任何形式的傷害或損失。
最新文檔
- 2026年延長(zhǎng)石油油氣儲(chǔ)運(yùn)考試題庫(kù)含答案
- 北京警察學(xué)院《日語(yǔ)聽力》2024 - 2025 學(xué)年第一學(xué)期期末試卷
- 通信原理總復(fù)習(xí)
- 2026年口腔醫(yī)療管理公司員工行為規(guī)范管理制度
- 輕騎集團(tuán)ERP方案草案模板
- 甘肅省白銀市2026屆九年級(jí)上學(xué)期期末考試物理試卷(含答案)
- 2025 小學(xué)五年級(jí)道德與法治國(guó)家發(fā)展歷程了解課件
- 2025年特色小鎮(zhèn)文化旅游產(chǎn)業(yè)項(xiàng)目技術(shù)創(chuàng)新與旅游產(chǎn)業(yè)創(chuàng)新生態(tài)構(gòu)建可行性研究報(bào)告
- 2025年農(nóng)村電商物流配送一體化解決方案與技術(shù)創(chuàng)新前景研究
- 智能養(yǎng)老社區(qū)老年人社交娛樂(lè)平臺(tái)在2025年技術(shù)創(chuàng)新可行性報(bào)告
- 保育員配合教學(xué)培訓(xùn)工作指南
- FSSC22000 V6食品安全管理體系管理手冊(cè)及程序文件
- 2025年保安員理論考試100題(附答案)
- 年終歲末的安全培訓(xùn)課件
- 3單元4 彩虹 課件 2025-2026學(xué)年統(tǒng)編版小學(xué)語(yǔ)文二年級(jí)上冊(cè)
- DBJT15-140-2018 廣東省市政基礎(chǔ)設(shè)施工程施工安全管理標(biāo)準(zhǔn)
- 肝豆?fàn)詈俗冃愿涡阅X病護(hù)理查房
- 特殊作業(yè)之-斷路作業(yè)安全教育培訓(xùn)
- 中華醫(yī)學(xué)會(huì)麻醉學(xué)分會(huì)困難氣道管理指南
- 醫(yī)務(wù)部會(huì)議管理制度范本
- 繪本制作培訓(xùn)課件
評(píng)論
0/150
提交評(píng)論