目錄

1、編制依據(jù).........................................................................1

1.1設(shè)計文件.....................................................................1

1.2相關(guān)施工規(guī)范、技術(shù)指南及驗收標(biāo)準(zhǔn).............................................1

1.3其他..........................................................................2

2、編制范圍..........................................................................2

3.工程概況........................................................................3

3.1工程簡介......................................................................3

3.1.1軌道主要設(shè)計參數(shù)............................................................................................................................6

3.2工程重難點分析................................................................8

4.施工進(jìn)度計劃.....................................................................8

5、總體施工組織機(jī)構(gòu)..................................................................8

5.1人員、機(jī)械設(shè)備配置..........................................................10

6、臨時設(shè)施.........................................................................12

6.1施工便道....................................................................12

6.2施工用電....................................................................13

6.3鋼筋加工場..................................................................13

6.4水泥乳化瀝青砂漿加料站......................................................13

6.5軌道板存儲..................................................................13

7、施工方案.........................................................................14

7.1梁面打磨整修方案.............................................................14

7.1.1梁面檢測.................................................................................................................................................14

7.1.2梁面打磨.................................................................................................................................................15

7.1.2梁端處理.................................................................................................................................................15

7.1.3橋面排水坡處理....................................................................................................................................16

7.1.4側(cè)向擋塊齒槽、剪力齒槽修整.........................................................................................................16

7.2防水層施工......................................................................16

7.2..1檢查及驗收..........................................................................................................................16

7.2.2基層拋丸.............................................................................................................................17

7.2.3基層缺陷修補(bǔ).......................................................................................................................18

7.2.4底涂施工.............................................................................................................................18

7.2.5噴涂聚服彈性體防水涂料...................................................................................................18

7.2.6特殊部位處理.......................................................................................................................21

7.2.9橋面防水層施工注意事項...................................................................................................25

7.3滑動層施工.......................................................................26

7.4底座板施工.......................................................................30

7.4.1工藝流程圖..............................................................................................................................30

7.4.2底座板單元劃分.....................................................................................................................31

7.4.3鋼筋加工及綁扎......................................................................................................................34

7.7.4齒槽剪力釘?shù)氖┕?.................................................................................................................34

7.4.5后澆帶鋼板連接器制作與安裝.............................................................................................34

7.4.6底座板模板制作與安裝.........................................................................................................35

7.4.7底座板混凝土澆注..................................................................................................................36

7.4.8底座板混凝土養(yǎng)護(hù)..................................................................................................................37

7.4.9混凝土底座板張拉施工.........................................................................................................37

1.5路基支承層施工...................................................................43

7.6、軌道板粗鋪.....................................................................44

7.6.1工藝流程..................................................................................................................................44

7.6.2軌遒板粗鋪方案.....................................................................................................................45

7.6.3軌道板粗鋪施工......................................................................................................................45

7.7軌道板精調(diào).......................................................................48

7.7.1精調(diào)測量數(shù)據(jù)準(zhǔn)備..................................................................................................................48

7.7.2安裝軌道板精調(diào)爪..................................................................................................................48

7.7.3精調(diào)程序..................................................................................................................................48

7.7.4安裝扣壓裝置..........................................................................................................................49

7.8水泥乳化瀝青砂漿灌注............................................................51

7.8.1灌漿前軌道板檢查測量........................................................51

7.8.2軌道板封邊..................................................................52

7.8.4水泥乳化瀝青養(yǎng)護(hù)............................................................55

7.9軌道板縱連.......................................................................56

7.9.1軌遒板張拉連接..............................................................56

7.9.2軌道板接縫混凝土灌注........................................................57

7.10軌道板的剪切連接................................................................57

7.11側(cè)向擋塊的施工..................................................................57

8,進(jìn)度保證措施.........................................................................58

8.1工期保證體系.....................................................................58

8.2保證工期的主要措施.............................................................58

8.2.1縝密超前進(jìn)行施工準(zhǔn)備......................................................58

8.2.2建立高效的指揮系統(tǒng).........................................................58

8.2.3投入一流的專業(yè)隊伍........................................................59

8.2.4確保資源的有效配置........................................................59

8.2.........................................................5運用先進(jìn)的施工工藝生產(chǎn).59

8.2.6規(guī)范工程管理,提高施工效率................................................59

8.2.7重視技術(shù)創(chuàng)新,加速施工進(jìn)度................................................60

8.2............................................8創(chuàng)造良好施工環(huán)境,保證工程連續(xù)推進(jìn).60

9、安全保證措施.........................................................................61

9.1安全施工管理重點...............................................................61

9.2安全保證組織措施...............................................................61

9.3安全保證管理措施...............................................................61

9.3.1建立健全安全作業(yè)制度.......................................................61

9.3.2做好安全生產(chǎn)教育與培訓(xùn)....................................................61

9.3.3嚴(yán)格安全生產(chǎn)檢查...........................................................62

9.4安全保證技術(shù)措施...............................................................63

10、質(zhì)量保證措施........................................................................64

10.1質(zhì)量控制要點................................................................64

10.1.1滑動層施工質(zhì)量控制要點....................................................................................................64

10.1.2高強(qiáng)度擠塑板施工質(zhì)量控制要點........................................................................................64

10.1.3底座板施工質(zhì)量控制要點....................................................................................................65

10.1.4軌道板鋪設(shè)質(zhì)量控制要點....................................................................................................66

10.2質(zhì)量管理措施...............................................................70

10.....................................................................................................................2.1質(zhì)量管理責(zé)任制度.70

10.2.2內(nèi)部監(jiān)督檢查制度..............................................................................................................70

10.2.3質(zhì)量定期檢查及質(zhì)量例會制度..........................................................................................70

10.2.4開展技術(shù)攻關(guān)......................................................................................................................70

10.2.5強(qiáng)化監(jiān)督管理......................................................................................................................70

10.2.6嚴(yán)格執(zhí)行制度......................................................................................................................71

10.2.7加強(qiáng)設(shè)備管理......................................................................................................................71

10.3技術(shù)措施...................................................................71

10.3.1編制高質(zhì)量施工組織方案..................................................................................................71

10.3.2加強(qiáng)施工技術(shù)管理..............................................................................................................71

10.3.3嚴(yán)格工序管理......................................................................................................................72

10.3.4推廣應(yīng)用“五新”技術(shù)......................................................................................................72

10.3.5加強(qiáng)原材料質(zhì)量控制..........................................................................................................72

10.3.6規(guī)范混凝土拌和站管理......................................................................................................73

10.3.7確保施工測量精度..............................................................................................................73

11.環(huán)境保護(hù)措施...................................................................73

11.1環(huán)境保護(hù)工作重點...........................................................73

11.2環(huán)境保護(hù)工作措施...........................................................73

11.2.1植被及水土保持..................................................................................................................73

11.2.2水質(zhì)保護(hù).................................................................................................................................74

11.2.3施工噪聲防治........................................................................................................................74

11.2.4大氣污染防治........................................................................................................................74

11.2.5公眾干擾的防治....................................................................................................................75

11.2.6公眾健康和安全............................................................75

11.2.7施工營地..................................................................76

11.2.8臨時工程..................................................................76

12、文明施工措施....................................................................77

12.1文明施工重點...............................................................77

12.2文明施工措施...............................................................77

12.2.1文明施工組織措施..........................................................77

12.2.3環(huán)境衛(wèi)生管理..............................................................79

中鐵五局滬昆鐵路客運專線江西段2標(biāo)項目二分部

CRTSn型板式無祚軌道實施性施工組織設(shè)計

1、編制依據(jù)

1.1設(shè)計文件

(1)《新建鐵路杭州至長沙客運專線(江西段)軌道設(shè)計技術(shù)交底資料》;

(2)《滬昆鐵路客運專線江西段指導(dǎo)性施工組織設(shè)計》;

(3)《新建鐵路杭州至長沙鐵路客運專線施工圖CRTSII型板式無硅軌道

板結(jié)構(gòu)設(shè)計》杭長客專施圖(軌)-01、《新建鐵路杭州至長沙鐵路客運專

線施工圖橋上CRTSII型板式無碓軌道鋼筋連接器設(shè)計圖》杭長客專施圖

(軌)-22、《新建鐵路杭州至長沙鐵路客運專線施工圖橋上CRTSII型板式

無祚軌道底座設(shè)計圖(一)》杭長客專施圖(軌)-20、《新建鐵路杭州至長

沙鐵路客運專線施工圖橋上CRTSII型板式無柞軌道底座設(shè)計圖(二)》杭長

客專施圖(軌)-21、《新建鐵路杭州至長沙鐵路客運專線施工圖路基上CRTS

n型板式軌道設(shè)計圖》杭長客專施圖(軌)-18等已到設(shè)計圖紙;

(4)、中鐵四院杭長指揮部杭長客專江西段打磨數(shù)據(jù)規(guī)劃;

(5)、中鐵四院杭長指揮部[2011]21號聯(lián)系單《杭長客專曲線地段超高

設(shè)計》;

(6)、中鐵四院杭長指揮部[2011]63號聯(lián)系單《區(qū)間路基基床表層與

CRTSII型板式無祚軌道高程接口大樣圖接口數(shù)據(jù)修改》;

(7)、杭長客專HCJX-2標(biāo)段董團(tuán)至濱江DK365+430?DK430+174.21線

路詳細(xì)縱斷面圖;

1.2相關(guān)施工規(guī)范、技術(shù)指南及驗收標(biāo)準(zhǔn)

《鐵路混凝土工程施工質(zhì)量驗收標(biāo)準(zhǔn)》(TB10424-2010);

《高速鐵路軌道工程施工質(zhì)量驗收標(biāo)準(zhǔn)》;

《高速鐵路軌道工程施工技術(shù)指南》鐵建設(shè)[2010]241號;

《客運專線鐵路CRTSII型板式無祚軌道滑動層暫行技術(shù)條件》科技基

[2009]88號;

《客運專線鐵路無祚軌道支承層暫行技術(shù)條件》科技基12008]74號;

《客運專線鐵路CRTSII型板式無碓軌道混凝土軌道板暫行技術(shù)條件》;

《鐵路混凝土結(jié)構(gòu)耐久性設(shè)計設(shè)計規(guī)范》鐵建設(shè)[2009]44號;

《鋼筋機(jī)械連接通用技術(shù)規(guī)程》(JG107-2003);

《鋼筋焊接及驗收規(guī)程》(JGJ18-2003)等。

1.3其他

(1)項目二分部對當(dāng)?shù)丨h(huán)境及現(xiàn)場踏勘資料;

(2)我分部所擁有的技術(shù)裝備力量、機(jī)械設(shè)備狀況、管理水平、工法及

科技成果和以往的施工經(jīng)驗。

2、編制范圍

中鐵五局滬昆客專江西段站前工程HKJX-2標(biāo)項目二分部CRTSH型無硅

軌道施工范圍為DK400+230.294(弋陽滬昆鐵路立交特大橋長沙臺處路基大

端剌端部)?DK415+156.000(河潭滬昆鐵路立交特大橋長沙臺處路基大端

剌端部),總長度14.926km范圍內(nèi)橋上滑動層、底座板、弋陽車站及路基

上支承層、軌道板粗鋪、軌道板精調(diào)、CA砂漿灌注施工、軌道板縱連及剪

切連接、軌道精調(diào)等。

3、工程概況

3.1工程簡介

中鐵五局滬昆客專江西段站前工程HKJX-2標(biāo)項目二分部CRTSII型無昨

軌道施工范圍為DK400+230.294(弋陽滬昆鐵路立交特大橋長沙臺處路基大

端剌端部)?DK415+156.000(河潭滬昆鐵路立交特大橋長沙臺處路基大端

剌端部)包括弋陽車站、弋陽特大橋、河潭滬昆鐵路立交特大橋,總長度

14.926km。其中,橋梁2座11.138km,包括連續(xù)梁1聯(lián),連續(xù)剛構(gòu)1聯(lián),

簡支箱梁341片;路基共4段(含弋陽站),觥3.788km(含弋陽站1.4km);

共需鋪設(shè)CRTSII型軌道板4127塊及弋陽車站約464塊(正式編號設(shè)計暫未

出來,有補(bǔ)嘗板)。

路基上CRTSII型板式無昨軌道結(jié)構(gòu)混凝土支承層、乳化瀝青砂漿調(diào)整層

和軌道板三部分組成。

直線地段CRTSII型板式無昨軌道橫斷面(1)

直線地段CRTSII型板式無作軌道橫斷面(2)

曲線地段CRTSII型板式無祚軌道橫斷面(1)

曲線地段CRTSII型板式無祚軌道橫斷面(2)

橋上CRTSII無祚軌道結(jié)構(gòu)由兩布一膜滑動層/高強(qiáng)擠塑板、混凝土底座

板、水泥乳化瀝青砂漿調(diào)整層和軌道板四部分組成。自上而下分為:20cm

厚混凝土軌道板、3cm瀝青砂漿墊層、混凝土底座板、“土工布+塑料膜+

土工布”滑動層(簡稱兩布一膜)、梁絳處1.45m范圍內(nèi)為5cm厚高強(qiáng)擠塑

板。

CRTSII型軌道板標(biāo)準(zhǔn)長度6.45m,板絳5cm,板間用張拉鎖縱向連接。

軌道板鋪設(shè)于橋面上,經(jīng)精調(diào)和灌漿后進(jìn)行縱向張拉連接成整體。為了適

應(yīng)底座板連續(xù)結(jié)構(gòu),在橋梁兩端路基上設(shè)置摩擦板及端刺,以限制底座板

中的應(yīng)力及溫度變形,兩端刺間底座板縱向跨梁縫連續(xù),在橋梁固定支座

上方設(shè)置預(yù)埋螺紋鋼筋和剪力齒槽與梁體固結(jié),形成底座板縱向傳力結(jié)構(gòu)。

底座板兩側(cè)設(shè)置側(cè)向擋塊,限制底座板橫、豎向位移和翹曲。水泥乳化瀝

青砂漿是填充于底座板與軌道板之間的結(jié)構(gòu)層,主要起充填、支撐、承力

和傳力作用,并可對軌道提供一定的彈韌性,是軌道結(jié)構(gòu)中的重要結(jié)構(gòu)層,

水泥乳化瀝青砂漿充填層標(biāo)準(zhǔn)厚度為3cm。底座板與梁面之間設(shè)兩布一膜滑

動層(剪力齒槽部分除外),使底座板與梁面可相對滑動。

臺后摩擦板和端刺結(jié)構(gòu)把自橋梁傳來的水平力(牽引/制動力、溫度力)

錨定在路堤里,不致影響其后的軌道結(jié)構(gòu),并滿足端刺縱向位移的要求。

頂面無覆土、全長大于40m的橋梁結(jié)構(gòu)兩端需設(shè)置摩擦板及端刺結(jié)構(gòu)。

當(dāng)橋-橋間路基長度L^200m時,橋端路基上設(shè)置標(biāo)準(zhǔn)摩擦板及端刺結(jié)構(gòu);

當(dāng)橋-橋間路基長度L〈200m(分200m>LNl50m和lX150m兩種情況)時,設(shè)

置橋-橋緊鄰地段摩擦板及端刺結(jié)構(gòu)。示意圖如下,詳見附圖。

橋-橋緊鄰摩擦板及端刺縱斷面(L<150m)

橋-橋緊鄰摩擦板及端刺縱斷面(150<L<200m)

摩擦板寬度一般為9m,厚度為0.4m,長度根據(jù)下部結(jié)構(gòu)設(shè)計確定;標(biāo)準(zhǔn)

大端刺尺寸:上部結(jié)構(gòu)沿線路縱向厚度為沿線路橫向?qū)挾葹?m,高度

為2.75m;下部結(jié)構(gòu)沿線路縱向為8m,沿線路橫向為9m,厚度為1m。

摩擦板、端刺和過渡板混凝土采用C30,鋼筋采用HRB500。摩擦板、端

刺、底座及過渡板在交界處全部固結(jié),底座與摩擦板距主端刺約1m時進(jìn)行

錨固處理。

3.1.1軌道主要設(shè)計參數(shù)

⑴鋼軌

采用60kg/m、100m定尺長、非淬火無孔U71Mn(k)新軌。

(2)扣件

采用WJ-8C型彈性不分開式扣件,扣件高度34mm,墊板靜剛度為23KN/mmo

(3)預(yù)制件

CRTSII型軌道板長度為6450nini,寬度為2550mm,板厚為200mm,采用C55

混凝土澆筑。橫向設(shè)置60根直徑為10mm的預(yù)應(yīng)力筋;縱向通過6根直徑

為20mm的精軋螺紋鋼筋連接成整體??v、橫向鋼筋按設(shè)計要求進(jìn)行絕緣,

鋼筋間電阻值不小于2M。,用500V兆歐表測量絕緣性能。含扣件每塊總重

為9.23t。

(4)砂漿墊層

CRTSII型板式軌道的砂漿墊層設(shè)計厚度為30mm。

(5)底座板

CRTSII型板式軌道底座板寬2950mm,采用C30鋼筋混凝土澆筑,鋼筋采

用HRB500級,設(shè)計按不絕緣施工。精度要求:頂面高程±5mm,中線10mm,

寬度0~+15mm,頂面平整度7mm/4m。

(6)防水層

防水層采用聚胭噴涂

⑺側(cè)向擋塊

側(cè)向擋塊采用C35混凝土,HRB335鋼筋。側(cè)向擋塊上寬下窄,其中不受

底座偏移影響的側(cè)向擋塊上寬590mm,下寬400mm;幾何尺寸It軌道高度的

不同而變化;頂面自軌道板上邊緣向線路外側(cè)成2%的排水坡。

(8)滑動層

滑動層由聚丙烯土工布、高密度聚乙烯薄膜、聚丙烯士工布組成,寬

2.95m(鋪設(shè)時按3.05%多余部分剪去),使用壽命不小于60年,滑動摩

擦系數(shù)不大于0.35。

(9)硬泡沫塑料板

材質(zhì)為擠塑聚苯乙烯塑料板,寬2950mm,長度1450mm,厚50mm,使用

壽命不小于60年。

(10)限位板

限位板基本結(jié)構(gòu)為兩塊鋼板夾一層橡膠板,結(jié)構(gòu)尺寸650x100x11mm。

與底座板接觸的鋼板采用厚度不小于2mm的不銹鋼,與側(cè)向擋塊接觸的采

用厚度不小于5mm熱鍍鋅鋼板(鍍鋅厚度不小于60pm),橡膠板厚度為

11mm。

(11)混凝土的設(shè)計與要求

無硅軌道混凝土結(jié)構(gòu)使用壽命不得小于60年,使用環(huán)境為T2。混凝土

應(yīng)采取措施預(yù)防堿-骨料反應(yīng)。底座板混凝土彈性模量不應(yīng)大于31000MPao

3.2工程重難點分析

(1)重點:一是測量工作。無作軌道施工的前提是沉降評估和CP川網(wǎng)

布設(shè),平面位置放樣及標(biāo)高的控制精度要求高,尤其是軌道板的精調(diào)以及

3cm瀝青砂漿層的灌注質(zhì)量。二是底座板單元劃分。無昨軌道施工前根據(jù)施

工管段的具體情況進(jìn)行底座板單元劃分設(shè)計,這是無碓軌道施工的重點。

設(shè)計方案主要依據(jù)橋面驗收移交進(jìn)展情況、沉降評估、橋面系(如防護(hù)墻)

施工進(jìn)度、橋面防水施工,以及資源配置等因素確定。主要內(nèi)容包括底座

板施工單元段劃分、臨時端刺和常規(guī)區(qū)設(shè)置、后澆帶位置的確定。

(2)難點:一是瀝青砂漿的施工,鑒于其時效性強(qiáng),造價高,能否將軌

道板與底座板緊密相連,關(guān)鍵在于砂漿的工作性能和灌注質(zhì)量。二是底座

板混凝土澆注段分段劃分和張拉縱連。三是軌道板粗鋪精調(diào)和灌漿過程中

的對軌道板的擾動,需采用專用支架固定下進(jìn)行。

4.施工進(jìn)度計劃

計劃開工工日期:2013年1月10日,完工日期2013年11月26日。

工期計劃詳見附件1:2標(biāo)二分部無硅軌道總體施工形象進(jìn)度圖

5、總體施工組織機(jī)構(gòu)

二分部無硅軌道板施工組織機(jī)構(gòu)圖如下:

滬昆客專江西段2標(biāo)二分部無昨軌道板施工組織機(jī)構(gòu)圖

我二分部成立了CRTSII型板式軌道施工領(lǐng)導(dǎo)小組和管理組織機(jī)構(gòu)。領(lǐng)導(dǎo)

小組成員如下:

組長:羅成江,對施工進(jìn)度、施工安全質(zhì)量負(fù)總體責(zé)任;

副組長:總工程師練東海,對現(xiàn)場施工施工技術(shù)管理負(fù)總體體責(zé)任;

副經(jīng)理兼安全總監(jiān)李罡,對施工現(xiàn)場安全質(zhì)量負(fù)總體責(zé)任。

副經(jīng)理劉宇、彭海,對施工生產(chǎn)管理負(fù)總體責(zé)任

組員:沈志、郭丕善、顏林、周露、雷毫、悅祖國、鄭興黔、

馬榮華、李英、黃倫祥、周尚華、潘金、昌天云、王銀行。

具體見附件1:2標(biāo)無祚軌道板施工組織機(jī)構(gòu)圖

5.1人員、機(jī)械設(shè)備配置

無祚軌道施工人員配置表a套工裝設(shè)備)

序號人員分布人數(shù)(人)備注

1現(xiàn)場施工負(fù)責(zé)人4

2技術(shù)、測量、試驗14

3兩布一膜施工10

4模板施工10

兩布一膜底座板施工

5鋼筋加工及安裝10

6混凝土施工10

7底座板張拉連接10

8混凝土養(yǎng)生4

9施工負(fù)責(zé)人2

10安質(zhì)、機(jī)械、工程10

11后勤、食堂、看守、司機(jī)6軌道板鋪設(shè)施工

12庫房裝卸料10

14臨時存板場裝卸車6

15GRP點測量(放樣、抄平)8

16定位錨桿鉆眼及安裝錨桿5

17清洗底座板6

軌道板鋪設(shè)施工

18軌道板吊裝上橋10

19軌道板粗放10

20軌道板精調(diào)20

21軌道板封邊及養(yǎng)護(hù)20

22水泥乳化瀝青砂漿攪拌、實驗8

23軌道板灌注10

24壓緊裝置取安(包括調(diào)整支架)10

25軌道板張拉軌道板寬窄接縫施工、養(yǎng)護(hù)10

26機(jī)械班加工與維修5

27叉車司機(jī)4

人數(shù)合計232

無祚軌道施工機(jī)械設(shè)備配置表

名稱型號規(guī)格單位數(shù)量備注

1高壓清洗機(jī)臺2施工用

250kw發(fā)電機(jī)臺1施工用

35kw汽油發(fā)電機(jī)41施工用

4上橋梯子個2施工用

5水箱1方個2施工用

6汽車吊25TA2施工用

7鋼筋籠懸臂吊臺1施工用

8平板車臺1施工用

9混凝土罐車10m3臺5施工用

10張拉扭力扳手450N.M把4張拉施工

11刮尺長3.2m個2用于底座板碎施工

12提漿整平機(jī)臺2用于底座板碎施工

13大號抹子個10用于底座板磴施工

14小號抹子個6用于底座板碎施工

15專用毛刷把4用于底座板碎施工

16搗固棒直徑50mm套10用于底座板碎施工

17直聯(lián)便攜式空壓機(jī)ZB-0.11/741清除錨桿孔內(nèi)的碎渣

18電焊機(jī)BX-400臺1工點加工用

19氣割設(shè)備套1工點加工用

20電動型材切割機(jī)J3G-400臺1工點加工用

21鋼筋調(diào)直機(jī)LGT4-14臺1工點加工用

22鋼筋彎曲機(jī)A1工點加工用

23剪刀把4滑動層施工用

24漆刷把12滑動層施工用

25墨斗個3滑動層施工用

26三一重工瀝青砂漿車輛1II型軌道板灌注用

27鋪板龍門吊臺1n型軌道板粗鋪、精調(diào)用

28運板車輛2運n型軌道板用

29干料倉A1水泥乳化瀝青砂漿車加干料用(3T量)

30高壓清洗機(jī)臺1施工用

3130kw發(fā)電機(jī)臺車臺1施工用

3215kw發(fā)電機(jī)臺車臺1施工用

33汽油發(fā)電機(jī)臺車臺1施工用

34封邊工作車A1施工用

35干料站套1施工用

36封邊運料臺車輪胎式臺1施工用

37柴油發(fā)電機(jī)STC-30臺1封邊用5kw攪拌機(jī)的動力和夜間照明

38汽油發(fā)電機(jī)5kw(220V)臺1測量打孔用動力

39強(qiáng)制式攪拌機(jī)JW-350臺1寬窄接縫施工用

40直聯(lián)便攜式空壓機(jī)ZB-0.11/7臺1清除錨桿孔內(nèi)的碎渣

41大功率高壓清洗機(jī)PX-58臺2粗放前清洗底座位和灌板時濕潤底座位

43II型軌道板固定裝置套50100個側(cè)壓、50個接縫壓

每塊板用6套,1900塊板共需11400套,

44張拉鎖套4592

分批購買

水泥乳化瀝青砂漿中

45套2購置

轉(zhuǎn)倉

水泥乳化瀝青砂漿中

46臺1購置

轉(zhuǎn)倉運輸臺車

47測量臺車臺2購置

48電焊機(jī)BX-400臺1工點機(jī)加工用

49汽車吊25T臺2施工用

50汽車吊50T臺1施工用

51軌道板運輸車輛4視施工進(jìn)度情況而增加

523.5T叉車3.5T臺2水泥乳化瀝青砂漿料的運輸

53干料運輸汽車5T臺1干料運輸

54瀝青輸送汽車3T臺1施工用

55精調(diào)設(shè)備套2軌道板精調(diào)

56精調(diào)扳手把10包括調(diào)節(jié)托架的拆除

57張拉扭力扳手450N.M把6張拉施工

58鉆機(jī)(剪力筋安裝)價1軌道板及底座板鉆孔

6、臨時設(shè)施

6.1施工便道

為滿足軌道板和底座板鋼筋籠運輸、吊裝和砂漿攪拌車的通行要求,原

線下施工所用過的便道需要進(jìn)行重新整修并對基礎(chǔ)進(jìn)行加固處理,采用清

表面粘土,回填級配碎石和建筑廢渣,用壓路機(jī)碾壓的方式,確保地基承

載力,保證運輸?shù)仁┕ぷ鳂I(yè)的順利進(jìn)行,在橋梁邊緣外側(cè)保有足夠的寬度,

以便汽車吊、砂漿攪拌車等施工設(shè)備??拷粎R作業(yè)。在跨河跨路處采取設(shè)

便橋、繞行和平交道等臨時過渡工程。對于臨時存板點和提漿站,要求便

道以利于吊車擺放及運板車調(diào)頭。滿足水泥乳化瀝青砂漿車調(diào)頭及加料車

的擺放,其加寬便道長度滿足以滿足25T汽車吊、水泥乳化瀝青砂漿車、

干料運輸車成線型縱向擺放,則要求便道要離梁體邊緣不低于7m,長度

50m(跨兩個橋墩)為宜。

6.2施工用電

對于線下臨時電力線尚未拆除的,繼續(xù)使用臨時電力線來供電;對已經(jīng)

銷號的工點,可利用地方農(nóng)電輔以發(fā)電機(jī)發(fā)電供應(yīng)。

6.3鋼筋加工場

底座板鋼筋在加工場加工成半成品,利用鋼筋運輸臺車運到現(xiàn)場,用吊

車吊上橋面,再進(jìn)行人工綁扎連接后澆帶和齒槽部位。根據(jù)三個分部施工

現(xiàn)場情況,考慮利用原鋼筋加工場。

6.4水泥乳化瀝青砂漿加料站

水泥乳化瀝青砂漿加料站設(shè)在DK407+160弋陽特大橋右側(cè)原4號攪拌站。

6.5軌道板存儲

軌道板存儲方式采用沿便道存儲,在跨路、跨河等特殊結(jié)構(gòu)物和路堤處

臨時集中存儲的方式進(jìn)行存儲。

7、施工方案

7.1梁面打磨整修方案

7.1.1梁面檢測

為了滿足防水層噴涂和鋪設(shè)兩布一膜的施工條件,所有梁面都需要進(jìn)行

梁面檢測、修補(bǔ)處理。

檢測內(nèi)容包括:橋面平整度,梁端L45m范圍平整度標(biāo)準(zhǔn)為2nmi/1m,梁

端L45m范圍的梁面高程偏差10mm;橋面底座板范圍內(nèi)梁面平整度標(biāo)準(zhǔn)為

3mm/4mo側(cè)向擋塊齒槽深度、橋面排水坡度。測量方法如下:

(1)橋面及梁端平整度:沿橋面四條線(即每底座板中心左右各0.5m

處)分別使用4m靠尺連續(xù)放置(且每次重疊1m),使用塞尺量測靠尺與梁

面縫隙,取最大值為該4nl范圍梁面的平整度,梁面平整度檢測的四條線排

序均按面向大里程方向從左往右編號為1線、2線、3線、4線,每條線上

的平整度檢測均從小里程往大里程方向進(jìn)行,依次記錄,記錄形式為

Xmm/4m;Ymm/lmo

當(dāng)橋面某處平整度不能滿足3mm/4m但

溫馨提示

  • 1. 本站所有資源如無特殊說明,都需要本地電腦安裝OFFICE2007和PDF閱讀器。圖紙軟件為CAD,CAXA,PROE,UG,SolidWorks等.壓縮文件請下載最新的WinRAR軟件解壓。
  • 2. 本站的文檔不包含任何第三方提供的附件圖紙等,如果需要附件,請聯(lián)系上傳者。文件的所有權(quán)益歸上傳用戶所有。
  • 3. 本站RAR壓縮包中若帶圖紙,網(wǎng)頁內(nèi)容里面會有圖紙預(yù)覽,若沒有圖紙預(yù)覽就沒有圖紙。
  • 4. 未經(jīng)權(quán)益所有人同意不得將文件中的內(nèi)容挪作商業(yè)或盈利用途。
  • 5. 人人文庫網(wǎng)僅提供信息存儲空間,僅對用戶上傳內(nèi)容的表現(xiàn)方式做保護(hù)處理,對用戶上傳分享的文檔內(nèi)容本身不做任何修改或編輯,并不能對任何下載內(nèi)容負(fù)責(zé)。
  • 6. 下載文件中如有侵權(quán)或不適當(dāng)內(nèi)容,請與我們聯(lián)系,我們立即糾正。
  • 7. 本站不保證下載資源的準(zhǔn)確性、安全性和完整性, 同時也不承擔(dān)用戶因使用這些下載資源對自己和他人造成任何形式的傷害或損失。

最新文檔

評論

0/150

提交評論