1、CSPC NANHAI PETROCHEMICALS PROJCECTCSPC 南海石化項目Deaerator frame foundation construction除氧器支架基礎施工WORK INSTRUCTION:WI-8710-8100-0084SEPCO Electric Power Construction Corporation山東電力基本建設總公司REV版次DATE日期REASON FOR ISSUE修訂原因BY編制CHKD審核REVIEW審查APPR批準A4.Mar .2004Issued for ApprovalLu.XWSong.JDCao.ALXiao.TPSheng
2、.XGB17.Mar .2004Issued for ApprovalLu.XWZhao.KCao.ALXiao.TPSheng.XG升版記錄Revision information版次Rev章節(jié)號Section No.主要修改內容Description of main changesB所有章節(jié)all the section 增加了英文翻譯add the English translation7.修改了主要工程量change the main amount of engineering8. 修改了計劃工期change the scheduled construction term9.1修改了鋼
3、筋、模板施工工序change the rebar and formwork construction gradation9.2.1增加了土方開挖及回填參照程序add the procedure of excavation and backfill9.2.6增加了砼強度說明及砼攪拌說明及砼質量要求add the concrete strength explanation and the concrete mixing explanation and and the concrete quality request9.2.6增加了砼泵送布料方式add the concrete pouring po
4、int and pump concrete method目 錄Contents 1.目的 Purposes 2.范圍 Scope 3.職責 Responsibilities 4.參考文件 References 5.計量器具、工具、機械 Measuring instrument, tools and machinery 6.勞動力組織 Labor force 7.主要工程量 Main amount of engineering 8.計劃施工工期 Scheduled construction term of works 9.施工工序和施工方法 Construction procedure and
5、plans 1.范圍 Scope 本作業(yè)指導書適用于CSPC 南海石化項目Steam & Power生產區(qū)除氧器支架基礎的施工。This work instruction applies to the construction of deaerator bracket foundation in S&P production area for CSPC NANHAI petrochemicals project. 2.目的 Purposes 規(guī)定SEPCO在CSPC南海石化項目除氧器支架基礎施工中的施工工藝及標準,以有效的控制施工質量及施工進度。It stipulates the constr
6、uction process and standard for the deaerator bracket foundation for CSPC NANHAI petrochemicals project in order to effectively control the construction quality and schedule. 3.職責 Responsibilities 技術負責人 宋輝、陳群Technical leaders Song Hui, Chen Qun施工負責人 許德利、李曉東,方瑞青Construction leaders Xu Deli, Li Xiaodo
7、ng, Fang Ruiqing技術員 趙克、石青松Technicians Zhao Ke, Shi Qingsong施工員 卜現(xiàn)剛、張勝利、胡燕青、楊志猛、張立平Constructors Pu Xiangang, Zhang Shengli, Hu Yanqing, Yang Zhimeng, Zhang Liping質檢員 高見、王福全Inspectors Gao Jian, Wang Fuquan測量員 鄭小豐、潘江濤Surveyor Zheng Xiaofeng, Pan Jiangtao安全員 李新軍HSE Li Xinjun 4.參考文件 References 4.1相關設計圖紙;
8、Correlative design drawings;4.1.1除氧器支架基礎布置圖(43-8320-8100-0601) Arrangement plan for deaerator bracket foundation(43-8320-8100-0601)4.1.2除氧器支架基礎JC-1,2,3基礎施工圖(43-8320-8100-0602)JC-1,2,3 Foundation construction drawing for deaerator bracket foundation (43-8320-8100-0602) 4.1.2除氧器支架基礎JC-4,5,8,8a基礎施工圖(43
9、-8320-8100-0603) JC-4,5,8,8a Foundation construction drawing for deaerator bracket foundation (43-8320-8100-0603)4.1.2除氧器支架基礎JC-6,7基礎施工圖(43-8320-8100-0604) JC-6,7 Foundation construction drawing for deaerator bracket foundation (43-8320-8100-0604)4.1.2除氧器支架基礎JC-1a,JC-1c基礎施工圖(43-8320-8100-0605) JC-1a
10、,JC-1c Foundation construction drawing for deaerator bracket foundation (43-8320-8100-0605)4.1.2除氧器支架基礎JC-1,2,3基礎施工圖(43-8320-8100-0606) JC-1,2,3 Foundation construction drawing for deaerator bracket foundation (43-8320-8100-0606)4.1.2除氧器支架基礎JC-2a,3a基礎施工圖(43-8320-8100-0607) JC-2a,3a Foundation constr
11、uction drawing for deaerator bracket foundation (43-8320-8100-0607)4.2與施工圖紙相關的設計變更文件The design change document to the construction drawing; 4.3混凝土結構規(guī)范 Concrete structure specification (SP-8320-8100-0002)4.4工程測量 Engineering measure(WI-8710-8100-0003) 4.5現(xiàn)場開挖及回填Site excavation and backfill(PR-8710-810
12、0-0013)4.6除氧器支架基礎施工質量計劃Deaerator frame foundation construction inspection test plan(QC-8710-0100-0056)4.7GB50202-20024.8GB50204-20025.計量器具、工具及機械 Measuring instrument , tools and machinery 計量器具:全站儀、水準儀、鋼卷尺Measuring instrument: Total station, water lever, ribbon 工具:鐵鍬、鎬、小推車、錘頭 Tools: shovel, pickaxe,
13、small handcart, hammerhead 機械:混凝土泵車一臺、攪拌車三臺、砼振動器4臺、4米振動棒6個、鋼筋切斷機2臺、彎鋼機3臺、輥絲機一臺、吸塵器1臺(所有機械進廠前進行認真檢查,并報有關部門審查通過后方能進入現(xiàn)場施工)。Machinery: 1 concrete pump truck, 3 agitator trucks, 4 concrete vibrators, 6 pieces of vibrating rod (4m), 2 rebar cutters, 3 steel benders, 1 roller, 1 dust collector (All machine
14、ry should be inspected carefully and reported to relative department before mobilizing into the site). 6.勞動力組織 Labor force 技術員2人,施工員5人,測量員2名、質檢員2名,安全員1名,壯工20名,熟練操作工3名,駕駛員3人,電工2人,焊工4人,木工50人,鋼筋工25人,瓦工(砼工)25人2 technicians, 5 constructors, 2 surveyors, 2 inspectors, 1 HSE personnel, 20 laborers, 3 skill
15、ed operators, 3 drivers, 2 electricians, 4 welders, 50 woodworkers, 25 rebar workers, 25 concrete workers 7.主要工程量 Main amount of engineering 基礎砼總量 Gross of foundation concrete :1185 m3 鋼筋總量 Rebar amount of engineering: 230 t 模板工程量 Formwork amount of engineering :9508.計劃施工工期 Scheduled construction te
16、rm of works 計劃工期:土方開挖5天、墊層1天、基礎鋼筋7天、基礎模板4天、基礎砼澆灌養(yǎng)護7天、柱頭鋼筋綁扎5天、柱頭模板3天、柱頭砼澆灌養(yǎng)護7天、土方回填6天。The scheduled construction term of works is: excavation 5d,base 1d,rebar of foundation 7d,formwork of foundation 4d,concrete and conserve of foundation 7d,rebar of chapiter 5d,formwork of chapiter 3d, concrete and
17、conserve of chapiter 7d,backfill 6d.9.施工工序和施工方法 Construction procedure and plans 9.1施工工序 Construction procedure 除氧器支架基礎施工工序為:測量放線(土方開挖邊線) 土方開挖 墊層施工 測量放線(軸線定位,模板邊線) 基礎鋼筋、柱頭預埋鋼筋綁扎 模板支設、加固 質量驗收 砼澆灌、養(yǎng)護 拆模清理 測量放線(中心線、標高) 柱頭鋼筋綁扎 模板支設、加固 質量驗收 砼澆灌、養(yǎng)護 拆模清理 測量放線(中心線、標高)整體驗收 土方回填The construction procedure of d
18、eaerator bracket foundation is: measuring and marking ( sideline of earthwork excavation ) earthwork excavation cushioning construction measuring and marking ( locating axes, formwork sideline ) Binding the foundation rebar and embedded rebar of chapiter setting and reinforcing the formwork quality
19、acceptance pouring and curing concrete form removal and cleaning up measuring and marking ( central line , elevation ) binding chapiter rebar setting and reinforcing formwork quality acceptance pouring and curing concrete form removal and cleaning up measuring and marking ( central line , elevation
20、) whole acceptance earthwork backfill 9.2施工方法 Construction plans 9.2.1土方開挖及回填 Excavation and backfill土方開挖及回填要求見現(xiàn)場開挖及回填Site excavation and backfill(PR-8710-8100-0013)9.2.2墊層施工 Cushioning construction 清基完成經驗收合格后,進行墊層施工,可用5 10cm枋木或模板支好側模,木枋接頭處固定,防止混凝土澆注時偏位。用水準儀打上標高線,墊層澆砼時必須壓實、壓平。Start to carry out the
21、cushioning construction after cleaning up the foundation and accepting. Install side formwork with 5 10cm wood or template, and fix it at the junction of wood in order to prevent the concrete from replacement when pouring. Mark the elevation line with water level. Compact and press it even when pour
22、ing cushioning. 9.2.3測量放線 Measuring and marking 施工前將墊層頂部清理干凈,由測量人員組織木工在墊層上放出各中軸線及基礎各中心線,紅油漆涂三角符號標志,經復核無誤后交驗收。中軸線及基礎中心線經復核驗收后,木工人員根據各基礎中心線分別將基礎模板邊線(模板內邊線)、上部柱段模板邊線及預留孔等部位邊線用墨線彈出,必要時四角用紅油漆三角符號標志,經復核無誤后方可進行模板施工。Clean up the top of cushion coat before construction. The surveyors organize woodworker to m
23、ark each central axes and central line of foundation on the cushion coat, then to brush the sign of triangular symbol with red painting and then to deliver it for acceptance through checking. After checking and accepting the central axes and foundation central line, the woodworker will flip the side
24、line of foundation template sideline (inside line of template), template sideline of top column section and pre-left hole with ink thread, even brush the sign of triangular with red painting at the foursquare location if necessary. Then start to carry out the template construction after checking.9.2
25、.4模板工程 Formwork engineering 除氧器支架模板均采用12202440標準鏡光面膠合板,模板表面應干凈,無污漬及缺棱掉角現(xiàn)象。模板相互拼裝時在拼縫內側封貼封箱帶,防止拼縫處漏漿,影響砼質量。模板(包括支撐)應根據具體要求畫出幾何圖形以便支模時能保證他們正確的位置、形狀及橫斷面,從而使得最終的砼構件能夠在允許的尺寸偏差之內。施工時在地面預先按設計尺寸進行組合,與設計尺寸不符時按設計尺寸進行切割,要求斷面整齊,校核無誤后再進行組合安裝。重復使用的模板要求進行編號。模板縫采用封箱紙封堵。模板安裝前應涂刷隔離劑,應涂刷均勻。涂刷后應由專人檢查,避免局部漏刷,影響砼表面觀感。The
26、 deaerator bracket formwork adopts the 12202440 standard mirror veneer. The surface of formwork should be clean and no besmirchment or not being short of edges. To seal the joint sealing strap inside of the joint when combining the template so as to avoid leaking to impact the concrete quality accor
27、dingly. Draw the geometry of templates (including support) according to the drawing dimension so as to ascertain the exact position, shape and transect when template installation. Accordingly make the final concrete component be within the allowable dimension deviation. Combine it according to desig
28、n dimension on the ground in advance in construction. To cut formwork according to the design dimension if it doesnt agree with the design dimension. The cross section should be trim. Combine and install the template after checking. Number the formwork which are used repeatedly. Blocking up the temp
29、late aperture with the sealing paper. Paint dusting agent equably prior to install templates. Also check it after painting in order to avoid omission to impact the external vision. 支撐系統(tǒng)用直徑48mm、長3.5m鋼管搭設腳手架。模板支撐要求具有足夠的強度、剛度和穩(wěn)定性。固定模板用背枋凈空尺寸為150mm。柱模橫向鋼管,從墊層上100mm布置第一道橫鋼管,然后間距500mm一道,最后一道離上口不得超過100mm。支
30、模后,模板幾何尺寸應減少5mm,以減少混凝土脹模對混凝土尺寸的影響。To build the scaffolding with the steel tube which is 48mm in diameter, 3.5m long. The formwork support should have enough strength, rigidity and stability as the requirements. The headroom dimension of wood used for fixing formwork is 150mm. To set the first row of
31、 lateral steel tube from 100mm above the cushion coat, then set a row of them at intervals of 500mm. The last row of steel tube cant be over 100mm away from the upper. The geometrical dimension of formwork should decrease in by 5mm after installing formwork in order to prevent the concrete bulging d
32、ie from impacting the concrete dimension. 除氧器支架基礎承臺模板支撐詳見附圖。See the attached drawing of the cap formwork support for deaerator bracket foundation 模板安裝的允許偏差按下表控制 :Control the allowable deviation of formwork installation according to the following diagram:項 目 Items 允許偏差 Allowable deviation (mm)軸線中心線位置
33、 Position of axes and central line 5底模上表面標高 Surface elevation on the bottom formwork 10截面內部尺寸 Internal dimension of section 柱、梁Column , beam 4,5垂直度 Verticality 5表面平直度 Surface planeness 109.2.5鋼筋施工 Rebar construction 進廠鋼筋經檢測中心取樣合格后,方可使用。The mobilized rebar should be sampled through detecting center b
34、efore using. 首先根據圖紙要求做出鋼筋翻樣單,經建筑隊審批合格后方可進行鋼筋配料,鋼筋配料統(tǒng)一在鋼筋場制作。鋼筋應捆扎放置并且保證離地面至少300mm。To make out the translating sample list of rebar according to the drawing requirements, then to process the rebar on the rebar field after being reviewed and approved by construction team. Bind rebar when placing and k
35、eep them off the ground at least 300mm.現(xiàn)場鋼筋必須按規(guī)格掛好標志牌,注明鋼筋規(guī)格、型號、使用部位及試驗結果、狀態(tài)、情況。放置時可以不用覆蓋,但是有凹痕的地方不能生銹。鋼筋根據國標GB50204-2002進行切割、彎曲。Put up the sign card of the site rebar according to specification, giving clear indication of the specification, type, using part and test results, estate and situations.
36、It can be covered when placing, but there is no rust on the location of dent. Cut and bend the rebar according to the national standard GB50204-2002.鋼筋成品、半成品運至現(xiàn)場后,分別按規(guī)格、型號堆放整齊,底部用枋木等墊高防止泥水污染。在基礎外模板支設加固完畢,進行鋼筋的綁扎。鋼筋綁扎嚴格按圖紙設計規(guī)格、間距施工。鋼筋綁扎點要求:基礎底板最外三排鋼筋滿扎,中間間隔綁扎,柱頭箍筋全部滿扎。固定鋼筋用20號鐵絲綁扎,鐵絲的末端嵌入混凝土中以防腐蝕。上層鋼
37、筋安裝時采用鋼筋馬凳予以支撐固定,為保證馬凳的穩(wěn)定性,馬凳形式采用一根橫桿下設兩個交叉鋼筋的形式。馬凳鋼筋直徑與主筋相同。墊塊采用C30混凝土墊塊,間距1米布置,底板及側墻布置成梅花形,在陽角處綁扎兩塊混凝土墊塊,以保證鋼筋籠不偏移。Pile up the finished and semi-finished rebar in order according to specification and type respectively after they are being mobilized into the site, to block up the bottom with square
38、 wood in order to prevent from being polluted by soil water. Start to bind rebar after installing and reinforcing the formwork outside of foundation. Bind the rebar strictly according to the design specification and distance. The requirement of binding rebar: Three rows of rebar outmost of the found
39、ation soleplate should be bound completely, bind it at intervals for the middle, and bind the chapiter stirrup reinforcement completely. Bind the fixing rebar with No.20 iron wire, the end of iron wire should be insert into concrete in order to prevent from corrosion. Support and fix the top layer o
40、f rebar with rebar bench. The bench is made up of a rail and two crossed rebar so as to assure the stability of bench. The diameter of bench rebar is the same as the main rebar. Set the C30 concrete cushion block at intervals of 1m. The soleplate and sidewall form into the plum blossom type. Bind tw
41、o pieces of concrete cushion block at the positive corner in order to prevent the rebar cage from offset. 鋼筋安裝位置的允許偏差按下表控制:Control the allowable deviation of rebar installing position according to the following diagram: 項 目 Items 允許偏差 Allowable deviation (mm)綁扎鋼筋骨架 Binding the rebar framework 長 leng
42、th 10寬、高 Width, height 5受力鋼筋stress rebar 間距 Space distance 10排距 Row distance 5保護層厚度 Thickness of protective coating 柱、梁 Column, beam 5基礎承臺 Foundation cap 5綁扎箍筋、橫向鋼筋間距Space distance of binding stirrup reinforcement , lateral rebar 20鋼筋彎起點位置Position of bend point for rebar 209.2.6混凝土施工 Concrete constr
43、uction 基礎模板、鋼筋施工完畢,經驗收合格簽證完畢后方可進行澆筑砼。除氧器支架基礎、拉梁、短柱砼強度等級均為C40,墊層為C20。砼由攪拌站集中送料,砼汽車泵澆筑,一臺汽車泵澆筑。Pouring the concrete after the construction of foundation formwork and rebar through acceptance. The strength grade of deaerator bracket foundation, pull beam, puncheon concrete strength are C40 , the cushio
44、n coat is C20。The concrete are centralized delivered by mixing station, pouring it with a concrete automotive pump. (1)、砼澆筑前準備工作 Preparation before pouring concrete A、 重新對鋼筋、模板等仔細復核檢查。 Check and inspect the rebar and formwork carefully. B、 用吸塵器充分清除模板中的垃圾。Clear away the rubbish in the formwork comple
45、tely with dust collector. C、 自模板外側將模板和墊層之間用1:2水泥砂漿嵌填密實,防止漏漿爛根。Embed and compact between formwork and cushion coating with 1:2 cement mortar from outside of formwork in order to prevent from mortar leakage and rotten root. D、 充分檢查水、電源是否到位,電源箱、振動棒、振動器、夜間照明燈具等是否良好、正常。且應有備用的水源及發(fā)電設備。 Inspect completely w
46、hether the water and power supply are all ready, the power supply box, vibrating rod, vibrator and night lights are all right and normal or not. Even there are spare water supply and dynamoelectric equipment. E、 對所有施工人員進行詳細的施工技術交底。Tell all constructors about the detailed construction technique. F、 現(xiàn)
47、場進行清理,為砼泵車出入提供方便。Clean up the site and supply convenience to the concrete pump truck.G、聯(lián)系氣象臺,獲知最近的天氣狀況,做好預防措施。 Contact with the observatory and get the recent weather conditions for preparing the protection measures. (2)、砼澆筑的規(guī)定 Regulation of concrete pouring A、 因除氧器支架基礎尺寸較大,為避免澆注過程中產生施工冷縫,擬采用分層趕漿澆注的
48、施工方法,分層澆注,下一層澆注完以后再澆注上一層。澆筑間歇時間不超過1小時。基礎砼第一層澆筑厚度不宜大于15cm,以上每層厚度不大于30cm。As the size of deaerator bracket foundation is too big, pouring layer by layer to avoid the cold rack. Pouring the layer and then to the upper layer. The interim time of pouring cant be over 1 hour. The pouring thickness for the
49、first layer of foundation concrete is not suitable more than 15cm , thickness for each above is not more than 30cm. 基礎砼澆注共布置6個砼布料點,砼泵車直接將泵管伸至布料點泵送砼。There are 6 points for the foundation concrete pouring, extend the pump pipe to the pouring point with concrete pump truck and pouring concrete by pump.
50、 B、 砼澆筑連續(xù)進行,在一層砼初凝之前,將上一層砼澆下并搗實完畢,確保上、下層砼緊密結合,澆筑間歇時間不超過1小時。Concrete pouring should proceed, pouring the upper layer and vibrating firmly before initial setting to make sure the upper layer and underlayer compact. The interim time of pouring is no more than 1 hour.C、 砼振搗時,振動棒快插慢拔,插點間距以30cm為宜,梅花型布點,深度
51、不得超過振動棒長度1.25倍,振搗時不得振動鋼筋模板。振搗時間以砼面不顯著下沉,氣泡排凈為宜,澆筑上層砼時,振動棒插入下層砼約50100mm,振搗時間一般為30秒,嚴禁過振或漏振。 When vibrating, the vibrated stick should be inserted quickly and pulled out slowly. The space is 30cm, forming the plum blossom type, the depth is not as 1.25 times as the length of vibrator, and can not vibr
52、ate the rebar formwork. It is appropriate for the time to make the concrete surface be not sinkage and empty the air bubble. Vibrator should be inserted into the underlayer concrete about 50100mm,the time of vibration is 30 seconds, strongly vibration and leaving out are strictly prohibited.D、 泵送混凝土
53、,其布料點至少離側模100mm。防止沖擊支設模板。The concrete pouring point of pump transportation concrete should be 100mm at least away from side formwork in order to prevent from impacting the installed formwork. E、 混凝土澆注前考慮天氣的影響,避免雨天施工。 The weather impact should be considered before pouring concrete to avoid constructi
54、on in a rainy day.F、 砼澆注時要有木工、鋼筋工、安裝工、電工負責各自工作監(jiān)護。Send woodworker, rebar workers, erectors and electricians to answer for their respective responsibility when pouring concrete. G、 混凝土澆注前在模板上用紅油漆打上標高線,以控制混凝土的澆注后表面標高,澆注完以后應及時將混凝土表面壓光、抹平。Mark the elevation line with red painting on the formwork before p
55、ouring concrete in order to control the surface elevation after pouring concrete. Press the surface of concrete smooth and even in time after pouring. (3)、砼的養(yǎng)護 Curing 砼澆筑成型后,及時進行保溫養(yǎng)護。砼養(yǎng)護嚴格按要求及砼的施工規(guī)范規(guī)定施工,面層砼用鐵搓板壓光后,灑上適量水分,先鋪一層塑料薄膜,用于保濕,頂面鋪上兩層麻袋,側面包一層棉被,進行保溫,確保成型砼的質量。養(yǎng)護期間派專人24小時值班,保證砼表面長期濕潤。砼在保溫養(yǎng)護期間要將
56、水澆到塑料薄漠內,且應避免將保溫材料澆濕以免影響保溫效果。After concrete forming, the curing should be done in time according to the requirement and concrete construction specification. Surface concrete is pressed smooth, then sprinkle proper moisture, firstly spread a bed of plastic film to keep wet. Spreading two beds of matting on the top surface and wrapping a bed of quilt from side for heat preservation and assure the quality of forming concrete. Special person is sent to be on duty for 24 hours during curing to guarantee the concrete surface wetness for long time. Pouring the w
溫馨提示
- 1. 本站所有資源如無特殊說明,都需要本地電腦安裝OFFICE2007和PDF閱讀器。圖紙軟件為CAD,CAXA,PROE,UG,SolidWorks等.壓縮文件請下載最新的WinRAR軟件解壓。
- 2. 本站的文檔不包含任何第三方提供的附件圖紙等,如果需要附件,請聯(lián)系上傳者。文件的所有權益歸上傳用戶所有。
- 3. 本站RAR壓縮包中若帶圖紙,網頁內容里面會有圖紙預覽,若沒有圖紙預覽就沒有圖紙。
- 4. 未經權益所有人同意不得將文件中的內容挪作商業(yè)或盈利用途。
- 5. 人人文庫網僅提供信息存儲空間,僅對用戶上傳內容的表現(xiàn)方式做保護處理,對用戶上傳分享的文檔內容本身不做任何修改或編輯,并不能對任何下載內容負責。
- 6. 下載文件中如有侵權或不適當內容,請與我們聯(lián)系,我們立即糾正。
- 7. 本站不保證下載資源的準確性、安全性和完整性, 同時也不承擔用戶因使用這些下載資源對自己和他人造成任何形式的傷害或損失。
最新文檔
- 2026年平江縣縣直(街道)單位公開遴選(選調)工作人員備考題庫有答案詳解
- 2026年中國電力工程顧問集團西南電力設計院有限公司招聘備考題庫及參考答案詳解1套
- 2026年中國機械總院集團哈爾濱焊接研究所有限公司招聘備考題庫及答案詳解參考
- 2026年南雄市人武部關于招聘社會用工人員的備考題庫完整參考答案詳解
- 福建省部分高中學校高考適應性練習(一模)數(shù)學試題【含答案詳解】
- 鄉(xiāng)鎮(zhèn)建立完善內控制度
- 法人治理層面內控制度
- 內部管理制度與內控制度
- 內控機制建立中內控制度
- 樂山政府采購內控制度
- 骨折后肢體腫脹課件
- 社區(qū)基金使用管理辦法
- 美團充電寶分成協(xié)議合同
- (2025年標準)打架私了簡單協(xié)議書
- 污水站亮化工程施工方案
- 星間激光鏈路構建-洞察及研究
- 個人形象風格診斷與穿搭指南
- 旅游行程規(guī)劃表模板
- “十三五”規(guī)劃重點-銻礦石及精銻項目建議書(立項報告)
- 環(huán)衛(wèi)公司內部管理制度
- 第3章 同位素示蹤技術課件
評論
0/150
提交評論